Title: Ogallala Public School District
1Ogallala Public School District Facility Study
Committee Meeting 4 July 9, 2009
2Master Planning Process
- Meeting 1 May 18 - Organize Community
Facility Study Committee - Meeting 2 June 11 - Review school district
demographics, enrollment Assessment
of existing facility physical plant conditions - Meeting 3 June 25 - Educational space
program analysis review - Meeting 4 July 9 - Facility alternatives
development costs - Meeting 5 July ?? Solution reviewed and
prioritized - Meeting 6 July ?? - Recommendation to School
Board - Meeting 7 ?? - Community awareness /
presentations
Communities forget how fast the process was
completed but, Individuals remember how well it
was done
3Small Group Discussion of Program Options
- QUESTIONS
- Should OPS take steps to renovate / remodel
selected existing district facilities? - Yes ?
- No ?
- Should OPS take steps to improve the efficient
use of educational program space by combining
programs into fewer physical locations? - Yes ?
- No ?
- How many facilities should OPS operate to
facilitate its programs? - One - PK-12 11
- Two - PK-5 6-12 26
- Two - PK-8 9-12 11
- Three - PK-2, 3-5, 6-12 16
- Three - PK-5, 6-8, 9-12 32
- Four PK-2, 3-5, 6-8, 9-12 5
- Should West 5th Elementary continue to be used as
a school site? - Yes 22
- No 78
- Should Progress Elementary continue to be used as
a school site? - Yes 5
4Small Group Discussion of Program Options
- QUESTIONS
- 7. Should the 1929 portion of the MS Building
continue to be used for educational program
purposes? - 1. Yes 22
- 2. No 78
- How can the 1996 portion of the Middle School be
best used? - Middle School 0
- Elementary (Grades 3-5) 16
- District Administration 47
- Other 37
- Should the Auditorium Building continue to be
used for educational program purposes? - 1. Yes 37
- 2. No 63
- How should the Senior High School be best used in
the future? - Continue as the HS 20
- Middle School 35
- Expand to include HS MS 20
- Other 25
- 11. Can the track and football complex be located
remotely from the Senior High? - Yes 41
5Program Options
- OPTION 1
- Renovate, remodel and construct additions to all
existing OPS facilities as required to meet the
identified physical plant and programmatic
deficiencies. - OPTION 2
- Construct an addition to Prairie View Elementary
to add grades PK-5, renovate to meet physical
plant deficiencies - Construct a new Middle School on site TBD
- Renovate, remodel and construct additions to
existing OPS High School facility as required to
meet the identified physical plant and
programmatic deficiencies. - OPTION 3
- Construct an addition to Prairie View Elementary
to add grades PK-5, renovate to meet physical
plant deficiencies - Convert existing HS to MS Minimal renovation
- Construct a new High School on site TBD
- OPTION 4
- Construct an addition to Prairie View Elementary
to accommodate grades PK-2, renovate to meet
physical plant deficiencies - Construct a new grades 3-12 School on site TBD
6(No Transcript)
7(No Transcript)
8(No Transcript)
9(No Transcript)
10(No Transcript)
11(No Transcript)
12(No Transcript)
13(No Transcript)
14(No Transcript)
15(No Transcript)
16(No Transcript)
17(No Transcript)
18(No Transcript)
19Project Cost Summary
- COSTS INCLUDED
- Renovation / Remodeling Cost
- Site Improvements / Site Acquisition
Development - Building Additions / New Construction
- Technology infrastructure equipment ( New
construction only) - A/E Fees
- Site survey, geotechnical investigation
construction testing - Reimbursable expenses Printing, travel,
lodging, postage - Insurance financing costs
- Design construction contingency ( 5)
- Inflation / Escalation factor (7)
- COSTS NOT INCLUDED
- 1. Technology infrastructure equipment
(Remodeled areas) - 2. Moveable furniture equipment
- 3. Construction management fees
20Program Options
- OPTION 1
- REMODEL OGALLALA HIGH SCHOOL 8,859,619
- REMODEL OGALLALA AUDITORIUM 1,099,646
- REMODEL MIDDLE SCHOOL 3,493,633
- REMODEL WEST 5TH ELEMENTARY 3,048,521
- REMODEL PROGRESS ELEMENTARY 2,941,319
- REMODEL PRAIRIE VIEW ELEMENTARY 2,554,804
- TOTAL COST 21,997,543
21Program Options
- OPTION 2
- REMODEL OGALLALA HIGH SCHOOL 8,859,619
- NEW MIDDLE SCHOOL 12,929,206
- DEMOLITION OF EXISTING MIDDLE SCHOOL 209,501
- DEMOLITION OF WEST 5TH ELEMENTARY 83,800
- DEMOLITION OF PROGRESS ELEMENTARY 104,750
- PRAIRIE VIEW ELEMENTARY PK-5 ADDITION 7,769,571
- TOTAL COST 29,956,447
22Program Options
- OPTION 3
- NEW OGALLALA HIGH SCHOOL 18,633,422
- NEW FOOTBALL STADIUM TRACK 1,953,433
- CONVERT EXISTING HS TO MIDDLE SCHOOL 1,944,816
- DEMOLITION OF EXISTING MIDDLE SCHOOL 209,501
- DEMOLITION OF WEST 5TH ELEMENTARY 83,800
- DEMOLITION OF PROGRESS ELEMENTARY 104,750
- PRAIRIE VIEW ELEMENTARY PK-5 ADDITION 7,769,571
- TOTAL COST 30,699,293
23Program Options
- OPTION 4
- NEW OGALLALA GRADES 3-12 SCHOOL 36,615,381
- NEW FOOTBALL STADIUM TRACK 1,953,433
- DEMOLITION OF EXISTING HIGH SCHOOL 349,168
- DEMOLITION OF EXISTING MIDDLE SCHOOL 209,501
- DEMOLITION OF WEST 5TH ELEMENTARY 83,800
- DEMOLITION OF PROGRESS ELEMENTARY 104,750
- PRAIRIE VIEW ELEMENTARY PK-2 ADDITION 3,665,378
- TOTAL COST 42,981,411
24Tax Impact
- THIS INFORMATION IS FOR DISCUSSION PURPOSES ONLY.
- ESTIMATES ARE BASED UPON A 25 YEAR AMORTIZATION
WITH AN ANNUAL GROWTH OF VALUATION OF 4. FINAL
NUMBERS WILL BE DETERMINED ONCE THE FINAL PROJECT
SCOPE AND BUDGET ARE DETERMINED. - 22,000,000 PROJECT
- 18 cents / 100 valuation 180 on a 100,000
property 15.00 / month 49 cents / day - 30,000,000 PROJECT
- 24 cents / 100 valuation 240 on a 100,000
property 20.00 / month 66 cents / day - 43,000,000 PROJECT
- 35 cents / 100 valuation 350 on a 100,000
property 29.17 / month 96 cents / day
25DISCUSSION
- QUESTIONS TO CONSIDER
- WHICH OPTION WOULD YOU SUPPORT?
- HOW MUCH OF A TAX INCREASE ARE YOU WILLING TO
SUPPORT? - IF THE FACILITY MASTER PLAN HAD TO BE IMPLEMENTED
IN PHASES, WHICH PART WOULD LIKE TO SEE BE
COMPLETED FIRST? - ARE THERE ANY OTHER OPTIONS THAT YOU THINK NEED
TO BE CONSIDERED?
Communities forget how fast the process was
completed but, Individuals remember how well it
was done
26Which Option would you be willing to support if
it were propose as a referendum vote?
- Option 1
- Option 2
- Option 3
- Option 4
- Other
27How much of tax increase would you be willing to
support?
- No increase
- 18 cents / 100
- 24 cents / 100
- 35 cents / 100
28If the Facility Plan has to be implemented in
phase, which needs should be met first?
- Elementary Only
- Elementary Middle
- Middle High School
29Master Planning Process
- Meeting 1 May 18 - Organize Community
Facility Study Committee - Meeting 2 June 11 - Review school district
demographics, enrollment Assessment
of existing facility physical plant conditions - Meeting 3 June 25 - Educational space
program analysis review - Meeting 4 July 9 - Facility alternatives
development costs - Meeting 5 July ?? Solution reviewed and
prioritized - Meeting 6 July ?? - Recommendation to School
Board - Meeting 7 ?? - Community awareness /
presentations
Communities forget how fast the process was
completed but, Individuals remember how well it
was done