1Grøn gas gennem metanisering
- Claus Friis Pedersen clfp_at_topsoe.dk
2Vehicle to grid (V2G) is the future!
3An integrated energy infrastructure
CH4 CO2 4H2 2CH4 2 H2O
4The right factors for biogas upgrading
5Haldor Topsøe group (2011)
- Catalyst and engineering for
- Fertilizers
- Refineries
- The environmental sector
- Synthetic fuels
- Turnover DKK 4.4 billion
- Result DKK 397 MM
- 2091 employees
- 250 employees in RD
6Synthetic Natural Gas (SNG) - Xinjiang Qinghua
Transport SNG in pipelines rather than coal on
trucks
- 50 PJ corresponding to gt50 of the total Danish
Natural gas consumption - 5 PJ gasified biomass SNG plants are projected
- 0.1 PJ would be a large biogas methanation unit
7Fuel Cell and Electrolyser
SOFC
SOEC
H2
H2O
H2
H2O
H2O 2e- ? H2 O2-
H2 O2- ? H2O 2e-
O2-
O2-
O2- ? 2e- ½O2
½O2 2e- ? O2-
½O2
½O2
8Exergy Flows
9Biogas upgrade value proposition 1
CH4 30-40 CO2
Biogas
BioGas CH4 40 PJ
Biogas Upgrade
CO2
Electro-gas CH4, 27 PJ
H2
Electrolysis
Fuel synthesis
10Biogas upgrade value proposition 2
11Pre studies
Metan samfundet
SOEC biogas upgrade
12The business case (w. 5 interest)
2020 100 Electrolysis
2035 91 Electrolysis
Plant size 75 mio Nm3 biogas/year
Mio DKK
13Pilot test at Foulum 5 Nm3/h
CH4 CO2 4H2 2CH4 2 H2O
14Summary
- Electrolysis based biogas upgrade has the
potential to - Store electricity as fuel
- Increase the biogas production
- The business case is interesting but many aspects
are still uncertain - A pilot scale field trial is planned for 2015