Title: Dr. Henry Deng
1Dr. Henry Deng
IS 488 Information Technology Project Management
- Assistant Professor
- MIS Department
- UNLV
2Today
- Course schedule and dates
- Questions from PERT lecture 1
- In class exercise for PERT lecture 1
- Review some of your exam questions
- Activity time example
- Lecture 2 on PERT
- Exercise 2 on PERT
- Project team and topic
3Lets try this exercise before Lecture 2
-Calculate ES,EF,LS,LF, Slacks, and CP
E 5
4
5
D 3
2
F 1
C 1
B 2
8
3
6
A 2
I 2
1
G 2
H 1
7
4Solution ES,EF,LS,LF, Slacks, and CP
E6,11 56,11
4
5
D3,6 33,6
2
F11,12 111,12
C2,3 12,3
B0,2 20,2
8
3
6
A0,2 21,3
I14,16 214,16
1
G12,14 212,14
H0,1 113,14
7
CP B,C,D,E,F,G, and I
5PERT - Estimating activity time
- Consider following question
- What is the average waiting time in line at the
registrars office? - How would you go about calculating an average
score?
6PERT - Estimating activity time
- Consider following question
- How long does it take to test codes for an
accounts receivable program? - How would you get an average score? Different
from previous question?
7PERT - Estimating activity time
- Consider following question
- How long does it take to get sufficient responses
to a RFP? - How would you estimate that?
8PERT - Estimating activity time
- Calculating the duration of the entire project
and the scheduling of the specific activities
depends on how we calculate time for each
activity. - Obtaining estimates for projects that are repeat
or projects that we have experience with is
relatively easy. Estimating activity time for new
and unique projects is significantly more
difficult. - To factor uncertainly into the network analysis,
often three estimates are used Optimistic time
(a), most probable time (m), and pessimistic time
(b).
9Estimating uncertain activity time
- The three estimates (a, m, b) enable the systems
analyst to develop the most likely activity time
that ranges from the best possible (optimistic)
time to the worst possible (pessimistic) time. - The expected time (t) can be calculated using the
following formula - t (a4mb)/6
- To measure the dispersion or variation in the
activity time values, the common statistical
measure of the variance can be used - ?2 (b-a)/62
- (This formula assumes that a standard deviation
is approximately 1/6 of the difference between
the extreme values of the distribution (b-a)/6.
The variance is simply the square of the standard
deviation).
10Example of estimating activity time
- Consider the optimistic, most probable, and
pessimistic time estimates for a project that
involves the following activities - Activity Optimistic Most probable Pessimistic
- (a) (m) (b)
- ------------------------------------------------
------------------------- - A 4 5 12
- B 1 1.5 5
- C 2 3 4
- D 3 4 11
- E 2 3 4
- F 1.5 2 2.5
- G 1.5 3 4.5
- H 2.5 3.5 7.5
- I 1.5 2 2.5
- J 1 2 3
11Estimating time for activity A
- Using the expected time (t) formula
- t (a 4m b)/6
- we have an estimated average or expected
completion time of - tA 4 4(5) 12/6 36/6 6 weeks
- and using the variance formula
- ?2 (b - a)/62
- we can determine the measure of uncertainty or
the variance for activity A - ?2A (12 - 4)/62 (8/6)2 1.78
12Estimating time for all activities
- Activity Expected time Variance
- (in weeks)
- -------------------------------------------------
------------------------ - A 4 4(5) 12/6 6 (12 - 4)/62
1.78 - B 2 0.44
- C 2 4(3) 4/6 3 (4 - 2)/62
0.11 - D 5 1.78
- E 3 0.11
- F 2 0.03
- G 3 0.25
- H 2.5 4(3.5) 7.5/6 4 (7.5
2.5)/62 0.69 - I 2 0.03
- J 2 0.11
- Total 32
- Once expected activity times are calculated, we
can proceed with the critical path calculations
to determine the expected project completion time
and a detailed activity schedule.
13Network with expected activity times
C 3
2
5
F 2
D 5
A 6
E 3
G 3
J 2
1
4
7
8
B 2
I 2
H 4
3
6
14Network with ES EF
C 6,9 3
2
5
F 9,11 2
D 6,11 5
A 0,6 6
J 15,17 2
G 11,14 3
E 6,9 3
1
4
7
8
B 0,2 2
I 13,15 2
H 9,13 4
3
6
15Network with ES, EF, LS LF
C 6,9 3 10,13
Earliest Start Time
Earliest Finish Time
2
5
D 6,11 5 7,12
A 0,6 6 0,6
F 9,11 2 13,15
J 15,17 2 15,17
G 11,14 3 12,15
E 6,9 3 6,9
1
4
7
8
B 0,2 2 7,9
I 13,15 2 13,15
Latest Finish Time
Latest Start Time
H 9,13 4 9,13
3
6
16Activity schedule (in weeks)
- Earliest Latest Earliest
Latest - Start Start Finish Finish
Slack Critical - Activity (ES) (LS) (EF)
(LF) (LS - ES) Path? - --------------------------------------------------
-------------------------------- - A 0 0 6 6 0 Yes
- B 0 7 2 9 7
- C 6 10 9 13 4
- D 6 7 11 12 1
- E 6 6 9 9 0 Yes
- F 9 13 11 15 4
- G 11 12 14 15 1
- H 9 9 13 13 0 Yes
- I 13 13 15 15 0 Yes
- J 15 15 17 17 0 Yes
- Critical path - A, E, H, I, and J Project
duration - 17 weeks
17Variance in critical path activities
- Variation in critical path activities can cause
variation in the project completion date. - If a non-critical activity is delayed beyond its
slack time, then that activity would become part
of the new critical path, and further delays
would affect the project completion date. - Variation in critical path activities resulting
in shorter critical path will result in an
earlier than expected completion date. - The variance in the project duration is the same
as the sum of the variance of the critical path
activities.
18Probability of meeting deadline
- The expected (E) project time (T) for the
previous example is - E(T) tA tE tH tI tJ
- 6 3 4 2 2 17 weeks
- The variance (?2) for that example is
- Var (T) ?2 ?2A ?2E ?2H ?2I ?2J
- Since standard deviation is the square root of
the variance, then - ? ? ?2 ? 2.72 1.65
19Estimating time for all activities
- Activity Expected time Variance Variance
- (in weeks) ?2 (for critical
path) ------------------------------------------
------------------------------- - A (CP) 6 1.78 1.78
- B 2 0.44
- C 3 0.11
- D 5 1.78
- E (CP) 3 0.11 0.11
- F 2 0.03
- G 3 0.25
- H (CP) 4 0.69 0.69
- I (CP) 2 0.03 0.03
- J (CP) 2 0.11 0.11
- Total 32 2.72 Var
(T) - Standard deviation for critical path
activities - ? ? ?2 ? 2.72 1.65
20Probability of meeting deadline
- Assuming a normal (bell-shaped) distribution of
the project completion time allows us to compute
the probability of meeting a specified project
completion date. - Suppose the management has allowed 20 weeks for
the previous project. What is the probability
that we will meet the 20-week deadline? - We are looking for the probability of T lt20.
- The z value for the normal distribution of T 20
is - z (20 - 17)/1.65 1.82
- We need to use the normal distribution table.
21Normal distribution of project time
-
-
-
- -------------------------------------------------
------- - 17
20 - Time (weeks)
22(No Transcript)
23Normal distribution of project time
-
- 0.4656 0.5000 z
- 0.9656 (20 -17)/1.65
- 1.82
- p(Tlt 20)
-
- -------------------------------------------------
------- - 17
20 - Time (weeks)
24Summary
- PERT procedure can be used to schedule projects
with uncertain activity times. - The three time estimates (optimistic, most
likely, pessimistic) help calculate an expected
time and variance for each activity. - The time for critical path activities provides
the expected project completion time. - The sum of the variances of activities on the
critical path provides the variance in the
project completion time. - Normal probability distribution assumption and
procedures are used to compute the probability of
the project being completed by a specific time.
25(No Transcript)
26Time-Cost Trade-off Crashing
27Resource Limitations
- critical path crashing
- (cost/time tradeoff)
- other methods
28Crashing
- can shorten project completion time by adding
extra resources (costs) - start off with NORMAL TIME CPM schedule
- get expected duration Tn, cost Cn
- Tn should be longest duration
- Cn should be most expensive in penalties,
cheapest in crash costs
29Time Reduction
- to reduce activity time, pay for more resources
- develop table of activities with times and costs
- for each activity, usually assume linear
relationship for relationship between cost time
30Crash Example
- Activity programming
- Tn 7 weeks
- Cn 14,000 (7 weeks, 2 programmers)
- if you add a third programmer, done in 6 weeks
- Tc 6 weeks
- Cn 15,000
- cost slope (15000-14000)/(6-7)-1000/week
31Example Problem
- activity Pred Tn Cn Tc Cc slope max
- A requirements none 3 cant crash
- B programming A 7 14000 6 15000 -1000 1 week
- C get hardware A 1 50000 .5 51000 -2000 .5
week - D train users B,C 3 cant crash
- Crashing Algorithm
- 1 crash only critical activities B only choice
- 2 crash cheapest currently critical B is
cheapest - 3 after crashing one time period, recheck critical
32Crash Example
- Import critical software from Australia late
penalty 500/d gt 12 d - A get import license 5 days no predecessor
- B ship 7 days A is predecessor
- C train users 11 days no predecessor
- D train on system 2 days B,C predecessors
- can crash C 2000/day more than current for up
to 3 days - B faster boat 6 days 300 more than current
- bush plane 5 days 400 more than current
- commercial 3 days 500 more than current
33Crash Example
- Original schedule 14 days, 1,000 in
penalties 1000 - crash B to 6 days13 days, 500 penalties, 300
cost 800 - crash B to 5
- C to 10 12 days, no penalties, 4002000 cost
2400 - to 11 days is worse
- NOW A SELECTION DECISION
- risk versus cost
34Crashing Limitations
- assumes linear relationship between time and cost
- not usually true (indirect costs dont change at
same rate as direct costs) - requires a lot of extra cost estimation
- time consuming
- ends with tradeoff decision
35Resource Constraining
- CPM PERT both assume unlimited resources
- NOT TRUE
- may have only a finite number of systems
analysts, programmers - RESOURCE LEVELING - balance the resource load
- RESOURCE CONSTRAINING - dont exceed available
resources