Title: LCLS Gun Commissioning Status
1LCLS Gun Commissioning Status PlansDavid H.
DowellLCLS Injector Commissioning Workshop
October 9, 2006
- Status of gun fabrication and testing
- Gun test results
- Characterization of magnetic components
- Systems to be commissioned
- The 3-Pass Commissioning Plan
- Summary
2Gun Fabrication and Testing Process
- Fabricate parts
- Cold test sub assemblies and clamped parts
- Machine and measure for resonance and field
balance - Braze and weld final assembly
- Low power RF and cathode tests
- Furnace bake at 500deg C
- Assemble and configure for high power RF test
(hot test) - Vacuum bake of assembly in Klystron test vault
- Perform hot test
- Vacuum qualification of gun
- Alignment of assembly with CMM
- Install at S20
3RF Gun Fabrication and Cold RF Testing Finished
Preparing for High-Power Tests
Gun only pictures
CAD cut away view of gun interior
4RF Field Balance Measured Using Bead Drop
Technique
Data compliments J. Wang, ATR Dept., SLAC
5Gun Design and Measured Specifications
RF Parameters Design Measured
fp (GHz) 2.855987 2.855999
Q0 13960 14062
ß 2.1 2.03
Mode Sep. ?f (MHz) 15 15.17
Field Balance 1 1
6LCLS RF Gun Beam Side
dual rf power feeds
focusing solenoid
beam port Attach 2-km linac here
7LCLS RF Gun Cathode Side
8Description of gun magnet system
- Gun solenoid SOL1
- Bucking coil SOL1BK
- X,Y dipole correctors
- XC00YC00 (inside SOL1)
- Normal skewed quad correctors CQ01SQ01
(inside SOL1) - Field maps and calibrations measured
9Gun Solenoid and Dipole Corrector Magnetic
Measurements
10Bucking Coil Magnetic Measurements
11What were commissioning
e- to L0A
- Q 1 nC
- f 120 Hz
- G 120 MV/m
- gex,y 1 mm
- Dt 10 ps
- I 100 A
- E 6 MeV
spec. dipole
UV laser
e-
solenoid
YAG screens
RF gun
cathode
12The Gun Gun-to-Linac Region with the Drive
Laser Launch Optics
Laser tube from laser room
13CAD Model of the Drive Laser Launch Optics (top
view)
14Schematic of Drive Laser Launch Optics
Laser beam from drive laser
Virtual in-vacuum mirror camera
lens
Virtual cathode camera
M2
M1
Polarizer
Virtual image of in-vacuum mirror
mirrors used to steer laser on cathode
Wave plate
BS2
BS beam splitter
BS1
Joule meter
shutter (BCS), rate control
To the Gun window and in-vacuum mirror
15Gun and Gun-to-Linac Components
16Injector Commissioning Philosophy
- Commissioning plan is organized into three passes
through the injector - Tasks 2.3.3 1st pass
- Pre-beam and beam-based hardware software
checkout - Tasks 2.3.4 2nd pass
- First-order optics
- Tasks 2.3.5 3rd pass
- Full beam characterization and optimization
- In each pass the beam is transported from the gun
through DL1 and BC1 stopping at the beam dump,
TD-11.
17The Injector Commissioning Schedule and the
3-Pass Plan
Approximation of real schedule!
18Pass 1 Pre-Beam Commissioning
RF Processing and Water RF Controls
- Characterize and test gun water system controls
- Water system only, no RF
- Control loop bandwidth
- Temp stability
- RF processing with resonance control (water
LLRF) - Test of LLRF phase/amplitude controls (4-gun
probes) (0.1deg s-band, 0.1) - Measure recovery time after trip
- Interaction between LLRF water controls
19Pass 1 Commissioning
Setting RF Centering Laser in SOL1. Then
continue transport thru L0a, L0b ending at BXS to
set the injector beam energy
- Use fast diode at gun to time laser in rf
envelope - Set launch phase within rf period
- SOL1 at nominal field, scan laser phase until
beam observed on YAG01 - Meas. base width of charge vs. laser phase (is it
correct?, i.e. 110deg) - Locate zero crossing set laser phase to 30deg
- Center laser beam on SOL1
- Vary SOL1 current move laser on cathode until
there is no motion on YAG01 - Observe beam on YAG02, vary SOL1 current move
laser until there is no motion - Record settings on virtual cathode, virtual
mirror, etc.
20Pass 2 Commissioning
Overview of Second Pass Gun/GTL Commissioning
21Pass 2 Commissioning
Second Pass Commissioning Details of Gun/GTL
Optimization, 1st of 3 parts
- Calibration of charge and energy diagnostics
- Alignment procedure for energy measurements
- Measurements of gun beam energy
22Pass 2 Commissioning
Second Pass Commissioning Details of Gun/GTL
Optimization, 2nd of 5 parts
- Schottky scan to determine QE and presence of
satellite laser pulses - Charge vs. laser energy to measure QE and
linearity (no space charge limit of emission) - QE uniformity measurement by rastering laser beam
23Pass 2 Commissioning
Second Pass Commissioning Details of Gun/GTL
Optimization, 3rd of 5 parts
- Determination of emission uniformity by imaging
cathode onto YAG01 and YAG02 - Thermal emittance by solenoid scan at different
gun fields - Divergence of beam at cathode by
parallel-to-point imaging at YAG02 - Confirm parallel-to-point optics by varying laser
radius - Repeat at different gun fields
24Pass 2 Commissioning
Second Pass Commissioning Details of Gun/GTL
Optimization, 4th of 5 parts
- Beam alignment and calibration checks of BXG and
quads - Gun beam energy and energy spread vs. laser phase
- Low charge, short bunch
- Low charge, 10ps bunch
- High charge, 10ps bunch
25Pass 2 Commissioning
Second Pass Commissioning Details of Gun/GTL
Optimization, 5th of 5 parts
- Beam-based feedback systems tested and enabled
- First emittance and bunch length measurements
26Pass 3 Commissioning
Third Pass Commissioning Details of Gun/GTL
Optimization
- Integrated operation with entire injector
- Projected and slice emittance optimization (Gun
solenoid laser shape) - Longitudinal phase space measurements
27Summary of Gun Commissioning Status Plans
- Gun fabrication and cold testing completed
- Gun meets all design goals
- All magnetic components calibrated and
characterized - Gun integrated with solenoid and waveguide
assembly - Installed in test vault at Klystron
- First bake of assembly (gun vacuum in high 10-10
Torr) - High-power RF (hot) testing has begun
- Final vacuum qualification alignment performed
after Hot-Testing - Gun on schedule for Dec06 installation
- Commissioning will be done in three passes
- Pass 1 Pre-beam checkout and beam-based checkout
- First transport beam through entire injector
BC1 to TD-11 - Pass 2 First-order optics
- Characterize components and beam throughout
injector - Pass 3 Full beam Characterization
- Optimize beam quality