DOE Review of the LCLS Project. LCLS Project Management. M. Reichanadter / SLAC ... Mar1-2, 06 LCLS to conduct an EVMS review using an external review team. ... – PowerPoint PPT presentation

Number of Views:54
Avg rating:3.0/5.0
Slides: 26
Provided by: Rei7152
Category:
Tags: doe | lcls | mar1 | project | review

less

Transcript and Presenter's Notes

Title: DOE Review of the LCLS Project


1
DOE Review of the LCLS Project
  • LCLS Project Management
  • M. Reichanadter / SLAC
  • LCLS Chief Engineer

2
Review Documentation
  • LCLS Project Review weblink has all review
    information
  • http//www-ssrl.slac.stanford.edu/lcls/doe_reviews
    /2006-february/index.htm
  • Thumb drives, hardcopy binders for plenary and
    breakout presentations.
  • Project Documentation
  • Estimate to Complete (ETC) with contingency
    assessment on remaining work.
  • LCLS Summary Schedule and Schedules according to
    WBS Level 2
  • L1, L2 and L3 Milestones baseline dates and
    milestone performance.
  • Nov-Dec 2005 Monthly Report progress/issues,
    CPR, milestones, BCRs
  • LCLS Preliminary Safety Assessment Document
    (PSAD)
  • Responses to Recommendations from the May05 DOE
    Review
  • Facilities Advisory Committee October 2005
    Physics Presentation
  • Risk Management Plan/Registry risk
    identification and risk handling plans.
  • WBS Dictionary - WBS organization and scope
    description.
  • Anything else? See Helen ODonnell.
  • X3368, heleno_at_slac.stanford.

3
Outline
  • Project Status
  • Funding, Obligations Costs
  • Cost and Schedule Performance
  • Project Critical Path Milestones
  • Procurements
  • Organization Integration
  • Issues Ahead
  • Plans for the next six months
  • Summary

4
Project Status-1
  • SLAC has aligned the lab for the LCLS
    project/science.
  • More visibility into SLAC Ops and Photon Science
  • Director daily briefings, Project Management
    Oversight Group (PMOG), additional support from
    Stanford Construction Project Management (CPM).
  • ISMS, construction/contractor procedures
    extensively revised.
  • LCLS _at_ ANL, LLNL and SLAC is peak staffing for
    design/procure/construct phase.
  • SLAC Staff Strengthened (CF, ESH, Integration,
    Controls in particular)
  • LCLS Procurements well advanced.
  • Most major technical procurements under contract.
  • CM/GC under contract (17Oct05).
  • LCLS System Integration performing well.
  • ISEMS integrated into the LCLS work processes
  • Integration team strengthened with many new
    faces.
  • LCLS Change Control Board working well.
  • Technical Specifications continue to mature.

5
Project Status-2
  • LCLS preparing for construction phase.
  • Title 2 Design (Jacobs) has submitted 100 design
    package.
  • CM/GC (Turner) is on-board. Phase1
    (preconstruction)
  • Turners schedule and procurement plan meet LCLS
    milestones
  • Jacobs and Turner cost estimates reconciled to
    7
  • Initiated Owner-Architect-Constructor (OAC)
    meetings
  • Construction planning integrated with SLAC
    operations
  • FFTB, SPEAR-3, BaBar, emergency and normal
    traffic
  • On-going outreach with University and local
    community
  • Phase construction contracts to ensure scope fits
    TPC
  • Adequate contingency remains to address project
    risks
  • PSAD, HA, FHA, NEPA, Davis-Bacon approved. Lab
    and contractor ISEMS plans in place
  • S20 and MMF provide good feedback for main
    construction
  • LCLS is ready for CD-3b

6
Funding, Obligations BCWS
  • Planned work and obligations fall within the DOE
    funding profile.
  • The goal of the PO is to manage LCLS work
    activities to maximize the effectiveness of
    available funds.
  • Phase-fund construction contracts.

7
Earned Value Status Jan06
  • Process 4M of BCRs in Jan06 business.
  • TEC 20 Complete
  • Total cum obligations 72.2M

8
Cost and Schedule Performance
  • LCLS showing OK cost and schedule performance to
    date.
  • SPI is at 0.92
  • CPI is at 1.01
  • CPI tracking well with baseline.
  • Trending indicates slight lag in schedule, and
    slight underrun.
  • LCLS in the green

9
Cost and Schedule Variances
Cost Performance PM _at_ .92CPI Higher than
anticipated start-up costs related to the project
staffing. Prorated budget. Expect slow recovery
now that full team is in place.
Variances are reviewed at the monthly cost and
schedule meetings. Work-arounds are immediately
developed.
10
LCLS Critical Path
  • LCLS Critical Path Jan06
  • Constr Start Undulator B.O. Undulator
    Install First Light
  • 213d (10-1/2 months) schedule float to CD-4
  • Unchanged from last review
  • LCLS summary schedule (with Critical Path
    identified) are in backup documentation
  • Key schedule issues
  • Awarding construction contracts on time
  • Technical component readiness for installation
  • System integration needs good coordination
  • Preparation for SLAC shutdowns also to be
    well-planned
  • Apr06 FFTB Shutdown ( 3-1/2 mos. prep for
    Turner)
  • Aug06 SLAC Shutdown (4 mos. Install Injector
    some Linac)
  • Jul07 (3 mos. Install Linac)

11
Recent L3 Milestone Performance
  • Prerequisite for start of construction
  • Full list of LCLS L1-L3 milestones in backup
    documentation

12
Upcoming L3 Milestones
  • LCLS to realize key deliverables in FY06
    (undulators, laser, S20, MMF)

13
Contingency Allocation to Date
  • CF 30M allocated to CF. Interim FY04 effort
    and T2 design increase (Cont Res), MMF and S20,
    CM/GC and 60 reconciled estimate.
  • Over time, LCLS has identified offsets in other
    areas of the project.
  • Guidance on scoping decisions
  • No impact on CD-4, little or no impact on
    science, preservation of expansion capability,
    items that can be restored later.

14
Contingency Performance
  • Dec05 CF BCR for 60 cost reconciliation.
  • January pending business.
  • Maintain 27 contingency on WR until 1st group
    of CF bids are in (Apr06).

15
LCLS Procurements are well advanced
  • LCLS using a stand-alone procurement group
  • 1 Manager, 3 Buyers, co-located in B280
  • Uses all approved SLAC/DOE procurement policies /
    procedures
  • G. Desaulniers provides periodic consulting
    support
  • Weekly technical/procurement staff meetings
  • Procurements monitored via Status Sheet.
  • APP, Est Cost vs Actual, SOW/Specs, RFP/Req
  • Award Date, PO, Delivery Date
  • All major LLPs are under contract.
  • Injector - Drive Laser, beamline devices, RF Gun
    (SLAC)
  • Linac - BC1/BC2 Magnets, RF X-Band (SLAC)
  • Undulator - Strongbacks, Magnet Poles/Blocks, 1st
    Art.
  • CF - S20 Facility, MMF Facility
  • CM/GC contract awarded 17Oct 2005 (Turner)
  • CM/GC awards and manages the construction
    subcontracts.

16
Awarded Contracts
  • 38 of LCLS contracts awarded.
  • By end of FY06, 80 of contracts will be awarded.
  • At that point, cost risk is down.
  • Remaining contracts have some specialty
    components but most are commodities. (vacuum,
    cabling, etc.)
  • Cost Risks
  • CF subcontracts
  • Schedule performance
  • System Integration

17
LCLS Organization Chart (Jan06)
  • LCLS has strengthened its senior level expertise.
  • CF, ESH, Integration in particular.
  • PMOG, CM/GC also added.
  • Recently hired Controls Manager
  • Dedicated Procurement Group

18
LCLS Staffing
FY2009 annualized rate
  • SLAC _at_ 108 FTEs (Dec05)
  • At Peak Staffing Level
  • Does not include additional staff
  • A/E (Jacobs)
  • Turner (CM/GC)
  • PMCS Team
  • Consultants
  • Indirect Support

FY05 Funding
Award Title I
Treading water. CR or full-funding?
19
ISEMS _at_ LCLS
  • Personnel
  • Management Commitment
  • Qualified and Competent staff
  • Training
  • Work Processes
  • Procurement
  • Work Planning Execution
  • Review by PD/CE
  • Technical Design Reviews
  • Incorporate ISEMS into design
  • Documentation
  • Safety Documents
  • Technical Reports
  • Work Planning

LCLS Safety Walk Through                        
                                      Laboratory
Director Jonathan Dorfan conducted a safety walk
through of the LCLS project facilities
accompanied by John Galayda (LCLS). Pictured
above (right to left) are David Saenz (LCLS),
Gary Meadows (XL Construction), Michael
Scharfenstein (LCLS), Jonathan Dorfan (DO) and
Javier Sevilla (LCLS). (John Galayda took the
picture)
20
System Integration Engineering
  • System integration people/processes are in place
  • ESH, System Mgrs, Physics Liaisons, Deputy CE,
    QA Mgr, IT Mgr
  • Recent hires of Controls Manager and PPS/BCS Mgr
    will improve controls integration
  • ISEMS, CCB, CPR, design reviews, technical specs,
    risk registry
  • Recent schedule risk to Injector shutdown
    readiness indicates an opportunity for
    improvement.
  • System engineering processes are working
  • Technical specifications drive the process. Flow
    down from PRD
  • Interaction between physics liaison and
    engineering teams
  • Risk Registry develops path forward.
  • Design reviews help vet solutions.
  • Recent examples of solved problems
  • SLC-EPICS Interface, Undulator stands, Undulator
    tunnel HVAC

21
Technical Baseline Requirements
  • LCLS Specs
  • Defines the LCLS technical baseline.
  • Approved specs posted to website.
  • Under revision control.
  • Continue to document design specs, particularly
    ESDs in Inj, Lin, and Und.
  • Physics support recently added to Photon System.

22
LCLS Issues
  • System Integration Planning
  • Laser controls integration in S20
  • Improving. Controls Manager, PPS/BCS Manager
    will help.
  • Readiness for shutdowns
  • Improving. Deputy CE conducting weekly
    installation meeting
  • Undulator integration and MMF coordination
  • Improving. Assistant Undulator Manager will
    help.
  • Construction Safety Coordination
  • SLAC and LCLS entering a new work phase.
  • Good University Technical Representative (UTR)
    team in place with experienced manager (Bob Law).
  • Construction Procurements
  • Cost risk. Phase procurements (see Galayda
    talks)
  • Turner manages the subs, but still a large demand
    on the LCLS procurement group (funding transfers,
    change orders, etc.)
  • Arranging for SLAC procurement support to cover
    heavy demand times

23
Plans for the Next Six Months (last review)
  • Advance the Design
  • Complete staffing and co-location of LCLS team at
    3 labs. Done
  • Continue to push ISMS into LCLS work processes.
    Approved ISMS
  • Continue to define technical requirements. 70
    Complete
  • Complete Title II on schedule (Nov30) Complete on
    Feb17.
  • Put in place interim CM. Decided not to do this.
  • Procurements and procurement staffing
  • Procurement staffing and organization in place
    Done
  • Laser, Inj Und Materials, S20 and MMF all well
    advanced. Done
  • Award CM/GC Sep30. Done. Awarded Oct17.
  • Prep for Constr (CD-3b) Construction Prep Done.
  • LCLS ISMS established, add ESH staff to PO Done
  • Establish LCLS Construction Safety Plan Done
  • S20 and MMF construction. Both on schedule, cost
    and no injuries.
  • Start construction March 2006! Ready
  • Maintain cost, schedule and contingency control.
    Track monthly. Decoupled procurements to ensure
    scope matches TPC.

24
Plans for the Next Six Months (Feb06)
  • Obtain DOE CD-3b approval to start construction
  • PSAD, PEP, FHA, Readiness Review
  • A/E 100 Complete, CM/GC preparing for
    construction
  • Start LCLS construction phase (GC-Turner)
  • 100 cost estimates from Turner and Jacobs
  • Award construction subcontracts
  • Execute the FFTB removal safely and on schedule.
  • Continue performance on cost, schedule,
    milestones and procurements.
  • Conduct LCLS EVM certification review
  • Continue to proactively manage risk (RR).
  • Take B.O and commission S20 and MMF
  • Install begin drive laser commissioning in S20
  • Strengthen System Integration Engineering
  • Continue to document specs and advance design
    through review. Mature design reduces risk
  • Utilize POC staff for uniformity and quality
    across LCLS
  • Roadmap to LCLS EVM Certification
  • Sep05 LCLS conducted an assessment of EVMS.
    Positive comments. Good recommendations.
  • Mar1-2, 06 LCLS to conduct an EVMS review
    using an external review team.
  • Mar27-31 06 OECM EVM certification through
    DCMA.

25
Summary
  • The Project has made good performance thus far
    (20 complete)
  • SLAC is organized and aligned to support the LCLS
  • FY05 shutdown went well
  • LCLS Management Systems, configuration control
    working well
  • Cost and schedule contingencies are adequate for
    stage of the project.
  • Overall milestone performance is good, but 06
    will be a challenging year.
  • Critical path is understood. Look for
    opportunities to improve schedule.
  • LCLS is fully staffed up at all Labs
  • Procurements and procurement staffing
  • Procurement staffing and organization in place
  • Laser, Injector components, Undulators, S20 and
    MMF all well advanced.
  • CM/GC phased procurement plan shaping up.
  • LCLS ready for CD-3b
  • ESH _at_ SLAC/LCLS strengthened, PSAD, HA, FHA,
    Davis-Bacon all approved.
  • T2 100 Complete. CM/GC on-site
    (pre-construction planning)
  • MMF/S20 to be completed safely, on-time, on cost
  • Phased CF procurements to ensure scope matches
    TPC.