CMS RPC Endcap RE1 Status Report
Schedule V34.1
RE-1048 HALF RE1/2 and RE1/3 ready for installation
April 05
Sep 05
RE-1049 RE2, 3 installed on YE
2005 Milestones Production 18 RE1/2 and 18
RE1/3 Installation April end 60 RE1/2 60
RE1/3 Installation October-November Cosmic Tests
/ Magnet Test Preparation
2004 Milestones 3 RE1/2 1 RE1/3 pre
production chambers tested Korean gaps
deliveries ISR Assembly Lab on schedule
CSCRPCLB Beam Tests Cosmic QC 20 RE1/2 10
RE1/3
On behalf of Peking University Colleagues And
all at ISR
2
Dec. 2004
HV connector Last step
Cosmic stand and DAQ
RE1/2 Completed chambers ready for quality
control tests in the cosmic stand
3
Production Status 20 RE1/2 30 RE1/3 Assembled
Preparation gas pipes 120 chambers Cables 60
chambers Mechanics .. Cover closing Alu
plates Chamber production rate Expected 5 per
week March 20 RE1/2 mass production
re-launch GOAL June RE1/2 complete April end
RE1/3 Gaps expected mass production
re-launch GOAL Sept 30 RE1/2 complete
36 needed _at_ X5 April 2005
Chambers
Planned
Constructed
GOAL Dec 05 All certified!
4
Database developed to store RPC production
information http//forwardrpc/cms_forward_rpc/prod
uction_db/Main_db.htm
5
Create plots from cosmic test data
Strip response profile
6
Cosmic QCSee Andreys talk

HV 9.2kV
mA
Noise lt 10Hz/cm2
7
Chamber QC
4 Checklists At different stages of production
Cosmic Tests Andrey
Waiting for Final Destination Point 5
8
Barrel and Forward (Endcap) RPCs Configuration
and Condition database requirements for CMS Core
DB Team Document history - Following DB Workshop
Jan 24-28
Version Number Description Author Date
0.1 First draft about RPC sub-detector description and related database requirements after having discussion with Frank Glege, Anil Kumar, Saima Iqbal and Marcello Abbrescia Archana Sharma 31-JAN-2005
0.2 Initial draft provided by Archana Sharma is edited to add the configuration database requirements jointly for Forward (Endcap) RPC (requirements given by Archana Sharma) and for Barrel (given by Marcello Abbrescia) and on the basis of discussions with Frank Glege, Andrew Branson and Norbert Zoltan Toth. Saima Iqbal 14-Feb-2005
0.3 Comments to v0.2 by Archana Saima Archana 15-Feb-2005
0.4 Comments to v0.3 by Marcello Saima Marcello 17-Feb-2005
0.5 Ambiguities mentioned in v0.2 resolved. Add Configuration database schema (Initial version is provided after editing discussion based on requirements among Norbert, Andrew, Saima and Marcello ) and add condition database schema requirements as provided by Marcello Saima 06-Mar-2005
0.6 Question mentioned in V0.5 are resolves Saima 13-Mar-2005
9
Schema for RPC Barrel and Endcap
See Marcellos talk DB meeting Wednesday 16 at
8.30
10
Magnet Tests
SX5 Cables Services horizontal distances inside
SX5
18m
Counting House (see next page)
HB
HB
10m
10m
49m
15m
YE2
YE2
YE2
YE1
20m
magnet test position YE1
6 RE1/2 Chambers (One sector 60o) 6 Link Boards
available
11
(No Transcript)
12
Summary and Conclusions
  • Mass production gas gaps Korea full steam
  • Assembly RE 1 ramped up _at_ ISR lab and has reached
    5 chambers per week
  • The final RE 1/2 RPC has been mated to ME 1/2
  • RE1/3 installation exercise performed
  • Preparation for magnet tests started

RE 1 production expects to meet the CMS master
schedule for its installation and commissioning