Title: Power Supply Adequacy Assessment Model/Methodology Review
1Power Supply Adequacy AssessmentModel/Methodology
Review
- Steering Subcommittee Meeting
January 29, 2010
2Outline
- Model Validation
- Benchmarking Process
- Sample Historical vs. Simulated Dispatch
- Methodology Review
- Current Adequacy Metric LOLP
- The Problem with LOLP
- LOLP Subcommittee Suggestions
- Next Steps
3Model Validation
- HYDSIM vs. actual monthly generation
- GENESYS vs. HYDSIM hydro generation output
- Hydro peaking calibration
- Trapezoidal Model/HOSS/Capacity Survey
- Check random variable distributions
- Water, wind, forced outage, load/temperature
- Simulated thermal dispatch vs. historical
dispatch - Simulated hydro dispatch vs. historical dispatch
- Simulated dispatch vs. schedulers perspective
4(No Transcript)
5- Sample Comparison of Historical vs. Simulated
Hydro Dispatch - Hourly hydro dispatch is highly dependent on
hourly load shape - Historical and Genesys hydro load following is
consistent - Illustrative only based on old data and FW
constraints
6Methodology ReviewCurrent Adequacy MetricLOLP
7GENESYS Simulation
Illustrative Example Only
Cold
Hydro Limited
8Curtailment Events(Peaking problems and energy
shortages)
Each event has a peak and duration.
9What do we Count?
- Ideally, we count significant events (those
that we want to avoid) - Energy threshold (or contingency resource) is
1,200 MW for one day or 28,800 MW-hours from
Dec-Mar - Capacity threshold (or contingency resource) is
3,000 MW in any hour from Dec-Mar and from Jun-Sep
10Curtailment Events(non-events not shown)
11Loss of Load Probability
Simulated 300 winters (December through March)
Out of 300 winters, 15 had an average curtailment
greater than 10 MW-seasons, which means that the
Winter Loss of Load Probability (LOLP) 15/300
5 percent
12Energy LOLP(Sum of Curtailed Energy Dec-Mar)
13The Problem with LOLP
14Potential Problem with LOLPSame LOLP Bigger
Magnitude
15Potential Problem with LOLPLower LOLP Bigger
Magnitude
16LOLP Subcommittee Reportand Recommendations
17LOLP Subcommittee Report
- Clearly define all reserve requirements
- Operating reserves
- Planning reserves
- Wind integration reserves
- Determine which reserve curtailments count toward
LOLP - Add temperature-correlated wind as a random
variable - Decouple temperature and water condition
- Define a contingency resource for each month of
the year instead of defining threshold events - Record curtailment events across all months of
the year - Consider using other adequacy metrics
- Continue to assess climate change impacts
18LOLP Review Status
- Reserves
- Work being done by PNUCC committee
- Temperature-correlated wind
- BPA working on a test data set
- Decouple temp and water
- Done
- Contingency resource
- Work needs to be assigned
- Annual metric
- Not yet started
- Other metrics
- BPA draft methodology
- PSRI review
- Climate change
- Ongoing
19Next Steps
20Possible Modifications to the Current Method
- Replace LOLP with an alternative metric
- Use LOLP in conjunction with an alternative
adequacy metric - Use LOLP in conjunction with the magnitude of the
most severe event (or an average of the worst 10
of events)
21Examples of Other Adequacy Metrics
- LOLE loss of load expectation ()
- Number of hours with curtailment divided by the
total number of hours simulated - Can be more intuitive, i.e. 99.5 reliable
- Does not address magnitude
- EUE expected unserved energy (MW-hr)
- Average amount of unserved energy per year
- Lacks specific information about severe events
22Work Plan
- PSRI review complete by early 2010
- Benchmark GENESYS by early 2010
- Tech Committee propose new metric and threshold
by April of 2010 - Use new metric to assess 3 and 5 year adequacy by
June 2010