Title: From INTERFET To UNTAET
1From INTERFET To UNTAET
- Planning For UN PKO
- New Zealands Commitment To Timor Lesté
- A Case Study
2Purpose
- Describe NZs planning for the intervention in
Timor Lesté from 1999 2003 - Examine the similarities in planning for
combined, coalition operations and UN PKO - Highlight the respective responsibilities of the
UN and TCN in respect of commitment to UN PKO - Highlight the planning considerations for
Discussion Topic 1
3INTERFET (Sept 1999 Feb 2000)
- A UN sanctioned Chapter 7 Intervention, led by
Australia a coalition - NZ initial commitment - a joint task force of
around 1500 personnel - (SF, battalion group,
APC troop, 6 x UH-1H Iroquois, 2 x C-130, two
frigates, supply ship (15 of NZDF) - NZ ongoing commitment - a battalion group of
around 700, APC troop, 6 UH1H Iroquois, - NZ AO was assigned Canadian Coy, Nepalese
Platoon, Irish Platoon, Fijian Coy under OPCON
4INTERFET (Sept 1999 Feb 2000)
- INTERFET Log planning was based on UN model and
PKO experience - Initial planning was assumption based (no recon)
- NZ knew it had to self deploy and be self
sufficient for at least 60 days. Elected for 90
days - Planned for ops in and around DILI Allocated AO
was Suai
5NZBATT AREA OF OPERATIONS INTERFET AND UNTAET
Roads Closed 5 Months/Year 12 Hr Drive - 100 km
West Timor
No Seaport Restricted Airport Harsh
Environment No Infrastructure
NZ Battalion Area of Operations
6(No Transcript)
7This is what we found on arrival in SUAI. Our
experience tells us that it is pretty typical of
a UN intervention environment
8(No Transcript)
9(No Transcript)
10(No Transcript)
11(No Transcript)
12(No Transcript)
13(No Transcript)
14(No Transcript)
15(No Transcript)
16(No Transcript)
17(No Transcript)
18(No Transcript)
19(No Transcript)
20(No Transcript)
21(No Transcript)
22(No Transcript)
23(No Transcript)
24(No Transcript)
25(No Transcript)
26 27INTERFET Characteristics
- NZ Forces OPCON to Australian Force Comd- NZ
retained OPCOM - NZ had Implementing Arrangement with Australia
for common item support - NZ planned to support Bn Gp for 90 days ended
up supporting a multinational Bde Gp (-) for 180
days - Lines Of Communication NZ to Timor Lesté 6500km
Logistics Over the Shore only way to resupply
28(No Transcript)
29(No Transcript)
30(No Transcript)
31INTERFET Characteristics
- No HNS available initially and no contractor
support until May 00 - NZ established National Support Element in Darwin
to orchestrate logistic support - Log support was mostly a national responsibility
- INTERFET always intended to pass to UN but
mandate was unclear (Chapt 6 or Chapt 7) - UN intimated a Feb 00 handover about Dec 99
32UNTAET
- UN mandated Chapt 7 operation
- Planning was for transition ops (most TCN were
already in theatre) - Planning was for TCN to remain self sufficient
for 60 days until UN support network had been
established - UN accepted extant forces and structures and
accepted allocated AOs
33UNTAET
- NZ sent negotiation party to DPKO early (Jan 00)
- Negotiation team empowered to commit NZ national
resources - Team Terms Of Reference
- Determine how support was to be provided
- Determine what UN would reimburse NZ for and how
- Strike NZ COE list
34UNTAET
- UN/NZ Negotiation
- Defined the UN desired effect (Self contained Bn
Gp with Level 2 Med Facility) - Defined structures (troop numbers)
- Defined equipment lists (UN provided/NZ provided)
COE list - Agreed support to be provided to other TCN in NZ
AO - Confirmed leasing arrangements (dry lease in NZs
case)
35UNTAET
- UN/NZ Negotiation
- Negotiated LOA for painting of remaining UH-1H
Iroquois helicopters (INTERFET NZ camouflage
UN white) - Negotiated start-up serviceability rates (NZ
equipment had been in theatre for five months and
support was very difficult) - Confirmed provision of Classes 1 (Food) and 3
(POL) - Confirmed ROE
36UNTAET Planning Issues
- NZ had deployed specific equipment to theatre to
support itself in an austere, isolated AO. - Quads, and Swing Thru Container Handling System
were sticking points in negotiation - UN COE list does not contain all specialist
military equipment both parties must be
flexible - What constitutes a medical capability is a real
issue (Level 1 versus Level 2)
37(No Transcript)
38UNTAET Planning Issues
- NZ support to other TCN in AO was contentious and
time consuming. Ended up a three-way MOU/LOA
negotiation - During negotiation UN had not conducted recon
again both parties must be flexible and TCN in
theatre must be prepared to share intelligence - Come as you are issues
39UNTAET Planning Issues
- Deployment/Redeployment are issues
- National standards versus commercial reality
- NZ used national charter for deployment (B747-C
and two commercial vessels) Agreement to
reverse this for redeployment - Agree POE/POD up front affects reimbursement
- Equipment availability expectations on transition
NZ equipment was tired!
40UNTAET The Practicalities
- NZ staff were not trained in the verification
process - Verification very contentious initially because
UN had not told in-country verifiers of NZ
MOU/LOA (e.g. UN in country verifiers were not
aware of the agreement re painting of UH-1H) - Refrigeration in humid climates
- UN requests 60 days configure for 90 days
41General Traps For Players
- Troop Rotation policy
- NZ ground forces six months. NZ aircrew
three months (This was a sustainability issue
that was tied to aircraft painting but it did
cause friction) - Ammunition
- Who pays for training ammunition?
- Medical Controversy over what constitutes L1
and L2 difference in national standards - Whole blood and blood products (national policy)
42General Traps For Players
- What constitutes serviceable equipment
national standards - Who rectifies non-availability?
- Us versus Them
- TCN perceive that verification is to minimise
payment...TCN think it is to rip them off - Bureaucracy
- Personalities
43General Traps For Players
- Understanding that TCN reimbursement ceases when
TCN no longer mission committed. - Troop allowance does not go to the troops in
the first instance - Understand that TCN dont deploy with spare
capacity and neither does the UN - Contractor performance You Get What you Pay for
44General Traps For Players
- Backup arrangements if the shooting starts will
contracted staff remain? UNOSOM example - Understanding LOGCAP
- Huge utility but at a cost
- Start-up time typically- 6 8 weeks
- Planning to the endstate national
reconstitution
45Lessons For Us All
- Preplanning
- Engage MPS and DPKO early, face-to-face with a
senior decision maker - Strike the COE List
- Agree the sustainment plan
- Agree Ts Cs and MOU/LOA
- Draft MOU
- ESTABLISH PERSONAL RELATIONSHIPS!!!
- Dont assume the problem away (HNS)
46Lessons For Us All
- Plan to end-state has to be national
reconstitution - Information flow back to national planners
- Familiarity with TCN Handbook. If in doubt read
the instructions! - Identify and empower a single national Point Of
Contact - Do all this right and this is what you get....
47(No Transcript)
48Questions And Discussion