Title: Existing Facility Profiling
1Existing Facility Profiling Assessment
CANDO Presentation November 16, 2005 1005 am
to 1055 am
Making buildings work. Better.
- Don Davenport, P.E. Exec. VP
- E M C Engineers, Inc.
2Poor Building Performance
- Unfortunately, most buildings are performing
well below their potential. - Why is this?
- How can we address this?
- Why address it?
3Where does Our Energy Go?
- Transportation 27 in 1997 and 2004
- Industrial 38 in 1997, 33 in 2004
- Buildings 36 in 1997, 40 in 2004
- In Buildings - Approximately half in
Residential and half in Commercial - Electrical Capacity 70 to Buildings
4Why Commission Anything?
- An LBNL study of 60 buildings of different types
showed that - Over 50 had control problems
- 40 had HVAC equipment problems
- 15 had missing equipment
- 25 had BAS with economizers, VFDs, and advanced
applications that were simply not operating
correctly.
Source Assoc. of State Energy Research
Technology Internships and US Department of
Energy
5Quick Fix Solutions
- Maintenance staff try to correct problems after
the fact, while building is occupied - Staff receives little or no training in the
integrated systems in the building - Poor documentation
- Makeshift solutions can lead to unintended
consequences - Can cause invisible and costly results in
building performance
6Have you experienced these??
- Complaints about being too hot or too cold??
- Air quality complaints or concerns??
- Building systems not cooling adequately??
- Constant call backs to Service Contractors for
issues?? - Systems doing the opposite of what you would
otherwise expect?? - Lights on at night or lights on when daylighting
would indicate they should be off?? - High energy bills??
7Benchmarking
- Building Based
- Annual Utility Consumption from Billing
- Calculate EUI (energy use per SF)
- Compare to databases available SIC, NAICS,
CalArch, EIA, Energy Star, others - Use EUI to identify savings potential and best
candidate opportunities - Understand any unique differences in your
building systems or equipment as compared to
buildings in the database
8Benchmarking Example
Utility Consumption Data
Energy Use Index (SF)
9Example Benchmark Energy Use Index
10Benchmark Example Benchmark Against Database
CAL-ARCH DATABASE Your whole building EUI is 127
kBtu/ft2-yr, which is higher than 92 of
comparison buildings shown.
11Benchmark Example Electrical Demand History
12Benchmark Example Natural Gas History
13Benchmark Example Normalize Against Weather Data
14Investigation Building Operations
- What is the equipment actually doing?
- Validate the direct digital control (DDC) system
- Trend system points
- Document conditions
- Identify changes to setpoints, schedules,
sequences and cost/benefits
15Evaluate Trend Data
16Evaluate Trend Data
17Evaluate Trend Data
18Evaluate Trend Data
19Example - System Operations
20Example - System Operations
Problem Closed fire damper in RA path
21Track Monthly Energy Use
22Track System Level Metrics Simultaneous Heating
and Cooling
23Top 10 Opportunities Found
- 10. Reduce reheat for dehumidification/optimize
controls - 9. Reset supply air static pressure setpoints
- 8. Terminal unit tune-ups dampers valves
- 7. Return VFDs to variable speed operation
- 6. Improve clg. tower sequencing/lower cond.
wtr. temps - 5. Improve chiller sequencing
- 4. Ensure proper ventilation airflow rate
- 3. Optimize/restore economizer operation
- 2. Eliminate simultaneous heating and cooling
- 1. Turn off equipment when not needed
(Scheduled S/S)
24Top 5 Gas Opportunities
- 5. Improve boiler efficiency (tune-up or
replace) - 4. Implement aggressive air and water
temperature reset strategies (HWS vs OA, MAT vs
RAT, night setbacks, space temperatures) - 3. Tune-up terminal units to eliminate
simultaneous heating and cooling (valve leakage) - 2. Optimum start/stop vs. scheduled start/stop
(close OSA!! let Building coast to end of
day) - 1. Turn off heating plant when not needed
(Scheduled S/S)
25Heating Water Plant - Example
- If occupied, enable 60F outdoor temp
- If all AHU are off, enable at 50F
- Reduce heating plant runtime
- less energy
- less maintenance
- Close the hot water valves!
- Coil radiative losses can be extensive
- Compromise with regards to freeze protection to
maintain minimum MAT
26Energy Analysis Tool - Spreadsheets
- Spreadsheet based
- Simpler EEMs
- Non interactive EEMs
- Calibrate to available measured data
- Ease of use
- Easier to debug and troubleshoot
- Limited in ability to handle complex utility
rates or schedules
27Energy Analysis Tools - Simulations
- Hourly Simulation Models
- EQuest, Trace 700, Energy Plus, others
- Complex energy savings measures
- Handle interactive measures
- Require advanced engineering knowledge
- Quirks and nuances abound difficult to debug
- Typically 2 to 3 times effort of spreadsheets
- Good for multiple alternative assessments
28Energy Analysis Tools
- Simulation Models
- Tend to over-predict savings
- Difficult to reconfigure geometry sometimes
- Only means to handle multiple measures
- Difficult to model poor buildings
- Spreadsheets
- Good for individual measure assessments
- Everything seen no hidden algorithms
- Easy to modify for specific situations
29Key to Implementation
- Clear and easy to understand results
- Back up findings and recommendations with REAL
DATA!!! - Show the economics of lost opportunities
- Implement changes that make the life of the OM
staff EASIER not harder - Train operating staff to sustain implemented
improvements
30Case Study RetroCx for Operability Energy
Savings Cheyenne Depot
31Cheyenne Depot Background
- Constructed about 100 years ago
- Renovated between 2002 2004
- Contains
- Museum
- Brew Pub
- Lobby Offices
- EMC asked to Retro-Cx due to concerns about HVAC
quality and reliability
32Cheyenne Depot HVAC
- Chilled water system
- 4-pipe fan coils for offices
- DX system for Snake River
- Pub
- AHU with humidity control
- for museum
- Hot water natural gas boilers
- JCI Metasys BAS
33Cheyenne Depot Planning Phase
- HVAC system new, but not commissioned not
working well - Point to point BAS sensor verification
- Functional testing
- Sample air and water flow measurements to check
TAB - Energy use is greater than expected
- Utility data analysis
- Trending with BAS supplemented with
- temporary monitoring equipment
- Energy disaggregation
- Thermo graphic scans to check envelope
- integrity
- Deliverables
- List of deficiencies for correction under
warranty - Recommendations for additional energy savings
34Cheyenne Depot Warranty Items
- Implement night fan setback control
- Adjust duct high-limit humidity setpoint
- Replace valve actuators on dry coolers
- Replace air purge valve on hot water system
- Replace hot water pump bearing
- Balance museum fan for proper airflow
- Change BAS address for fan coil heat valve
- Provide BAS training to maintenance staff
35Snake River Pub AHU Control
36Cheyenne Depot Energy Disagregation
37Cheyenne Depot Additional Energy Opportunities
- Fully close museum outside air dampers at night
- Control ventilation with CO2 sensors
- Reset chilled water temperature on demand
38Cheyenne Depot Thermo Graphic Analysis
39Cheyenne Depot Savings Payback
Wyoming has cheap energy
40Example Resources
- Portland Energy Conservation Inc www.peci.org
- Building Commissioning Association, www.bcxa.org
- Practical Guide to Commissioning Existing
Buildings, Haasl Sharp, 1999, - ateam.lbl.gov/mv/docs/RetroCommissioningGuide.pdf
- ASHRAE, Guideline 1-1996, The HVAC Commissioning
Process, www.ashrae.org - Continuous Commissioning Guidebook for Federal
Energy Managers http//www.eere.energy.gov/femp/
pdfs/ccg01_covers.pdf - U.S. DOE / FEMP,www.eere.energy.gov/femp
- GSA Commissioning Handbook, www.gsa.gov
41EMC Engineers Inc.
- 29 years experience specialized in
- Energy Engineering
- Retro-Commissioning
- Commissioning
- Sustainable Design
- Energy Project Implementation
- Over 150 Commissioned Projects and 75
Retro-Commissioned Projects - www.emcengineers.com
42Thank You!