Program Managed by OECM Reviews Directed by 3rd Party ... Raytheon. 6. 2006. Project. Management. Workshop. EVMS Certification Process. Readiness Assessment ... – PowerPoint PPT presentation

Number of Views:97
Avg rating:3.0/5.0
Slides: 12
Provided by: s730
Category:

less

Transcript and Presenter's Notes

Title: Earned Value Management Systems


1
Earned Value Management Systems
  • Brian Pleasant
  • Office of Engineering Construction Management
  • November 15, 2006

2006 Project Management Workshop
2
EVMS Certification Overview
  • Certification of Contractor
  • Not Site
  • Not Project
  • Not Contract
  • Review of EVMS, not Project
  • Program Managed by OECM
    Reviews Directed by 3rd Party
  • Key Regulations Requirements
  • OMB Circular A-11, Part 7
  • FAR Subpart 34.2
  • DOE O 413.3A

3
EVMS DOE O 413.3A
  • Certification Required for Projects gt 20M
  • Self-Certification 20M - 50M
  • OECM Certification gt50M
  • Compliance with ANSI/EIA-748
  • Industry Standard for EVMS
  • NDIA EVMS Intent Guide

4
ANSI/EIA 748
  • 5 Categories 32 Criteria
  • Organization
  • Planning, Scheduling and Budgeting
  • Accounting
  • Analysis and Management Reporting
  • Revisions and Data Maintenance

5
EVMS Certified Contractors
  • Washington Savannah River Company
  • Bechtel Jacobs
  • Los Alamos National Security
  • University of California
  • Lawrence Livermore National Lab
  • Lawrence Berkeley National Lab
  • Lockheed Martin (Sandia National Lab)
  • Washington Group International
  • Raytheon

6
EVMS Certification Process
Readiness Assessment
EVMS Review
Follow-Up Review
Certification
7
EVMS Certification Process (Cont.)
  • Readiness Assessment
  • One to Two Days
  • EVMS Overview
  • Determination of Contractor Readiness
  • EVMS Review
  • One Week
  • 3rd Party Directed DOE Team Support
  • EVM System Documentation
  • Senior Management and CAM Interviews
  • Findings and Recommendations

8
EVMS Certification Process (Cont.)
  • Follow-Up Review
  • As Necessary
  • Two to Three Days
  • Validation of Corrective Action Plan
    Implementation
  • Certification
  • Certification Letter to Contractor Based on
    Validation Report from 3rd Party

9
EVMS Certification Process (Cont.)
  • Areas for Improvement (OECM)
  • Planning
  • Organization
  • Communication
  • Areas for Improvement (Program)
  • Team Composition
  • Preparation
  • Post-Review Support

10
EVM Value
  • Objective Measure of Accomplished Work
  • Objective Assessment of Project Performance
  • Projection of Future Performance Based on Trends
  • Prompt Corrective Action

11
EVMS Plan Ahead
  • Continue Reviews Certifications
  • Finalize 07 Schedule
  • Evaluate Contractor Support
  • Develop Surveillance Plan
  • Create EVMS Review Database
  • Update DOE EVMS Application Guide