Title: TRD Status Report
1TRD Status Report
Technical Board 10 May 2007, Johannes P. Wessels
Univ. of Münster
- chamber production
- status
- super module
- production
- testing
- installation
- services
- electronics
- production status
- test results
- detector control system
- summary
2ROC Production Status
C. Adler, Heidelberg
stable production at 5 sites Bucharest, Dubna,
Frankfurt, GSI, Heidelberg about 60 of entire
TRD produced keeping production rate in line with
SM production
3Radiator Production Status
W. Verhoeven, C. Riemann, Muenster
- production rate 3 rad./day
- shipment of L2C1 to Bucharest in week 13
4Production of Cooling Meanders
A. Marin, R. Fleige, N. Heine
- thermal contact epoxy loaded with Al powder
(plate-meander) - Thermaglue - heat conducting silicone between
plate and MCM - full production under way
- meanders for first 3 SM finished within 3 weeks
from now -
5Detector Summary
- 1st super module installed
- construction of TRD moving steadily ahead
- 5 sites working on chamber production
- pad plane assembly now in Darmstadt
- electronics integration now in Frankfurt
- final assembly of super modules now in Münster
- expecting significant additional manpower from
Japan - installation of 2nd and 3rd super module now
Sep-Oct
6Super Module Production Status
V. Chepurnov, B. Windelband, W. Verhoeven
-gt first super module installed October 06 -gt all
pieces finished and pre-assembled for 2nd super
module -gt remaining pieces ordered / partly
finished
7Production Status SM-II
T. Dietel, E. Sicking, S. Wulf, H. Grimm, U.
Westerhoff, B. Bathen
- all parts available in Münster Apr 9
- hull assembled Apr 13
- w/ cooling profiles, power bus bars
- Layer 0 installation
- installed and cabled Apr 27
- fully tested May 9
- 3-4 weeks include setup of infrastructure/software
- goal lt 1 week per layer
8Tests
- Electronics
- function data transfer, configuration...
- long-term stability 1 kHz L1A
- performance noise, gain (cosmics)
- Cooling
- leaks over- and underpressure
- function check for clogged cooling pipes
- Gas leaks, oxygen concentration
- HV anode drift current monitoring
9Front End Electronics
- Electronics integration in Frankfurt
- all ROCs tested before installation
- final tests in SM
- Read-out boards from series production
- Performance as in SM-I
- No problems with solder connections (seen in
SM-I)
10Cooling of SM-II
- Leak test of SM-II, Layer 0
- underpressure stable lt1mbar
- overpressure 0.7 bar ok
- excellent tightness
- Functional test
- cooling of layer 0 fully working
- New black hose
- replaces transparent hose
- recommended by CERN
- deforms with underpressure!
11Cosmics Ray Test Setup
B. Bathen, V. Yurevich, L. Efimov
- Large scintillator arrays
- top 2x2m2
- bottom 5x1m2
- typical rate 30Hzseveral hundred per day and
pad - shower trigger possible
- Relative gain calibration
- first gain tables immediately available
- Chamber alignment within super module
Electronics
12SM Production/Testing Schedule
- Super module II
- start of production 13.4.2007
- duration 8 weeks
- finished 8.6.2007
- Super module III
- start of production 8.6.2007
- duration 6 weeks
- finished 20.7.2007
- Afterwards 1 SM every 6 weeks
- Installation Sep, 17 - Oct, 17
13TRD sector 08
1st TRD super module installed in sector 08
since October 2007.
14Super Module SM08
operationalsince March 07
15 2007 Planning
Services will be prepared assuming TRD
detector will consist of 4 SM by end of 2007
08
2007
00
09
- sector 00
- sector 08
- sector 09
- sector 17
17
16 TRD-O-Meter
D. Emschermann
http//alice.uni-hd.de/trd-o-meter
TRD-O-Meter gives an overview of the status of
the TRD infrastructure at P2
17 Operation of SM08
- still waiting for the report of the safety
commission on our infrastructure - TRD operating
during nights only - Rack internal power (e.g.
Ethernet switches) available 24h/7d - Cosmics
data taking to start in week 19
18 SM 08 Full Cabling on C-Side
D. Emschermann, M. Kweon, K. Schweda, K. Oyama
mounting and testing
side view
top view
is 2-3 days of work
19 LV Power Supply Installation
- 50/90 power bins are
- installed at Point 2
- 16/90 Wiener power
- supplies are mounted
- 09/90 Wiener power
- supplies are operating
- sector 08 operating
- sector 09 installed
- GTU power operating
- PCU commissioned
20 LV Cabling and Sense Cabling
- a few bugs were found
- during LV cable testing
- - 1x flipped polarity
- - 2x loose screws in 6
- power bins we checked
-
- cabling of LV senses now
- performed by company
- no pretrigger LV cables
- installed yet
21 Inverted LV Channel Pin Out
LV power polarity occasionally flipped
photo shows correct connection after fixing the
bug
22 Trouble with Hot LV Cables
LV cable temperature was rising to 60 on one
cable during operation (default is 30) screw
connection inside Wiener power bin built at CERN
was faulty proper tightening of screws cures
the problem
23 HV System Patch Box
- 2 ISEG crates
- ready for operation
- using patch boxes
- as temporary HVDS
- replacement
- we will switch to
- ISEG-only solution
- as replacement for
- the HVDS
- this requires 40 new
- cables from CR4 to
- level 4 I/O 4 racks
24 DCS Network Monitoring Tools
D. Emschermann
developed monitoring tools for status control of
- Netgear switches
- DCS boards
- Wiener power supplies
25 DCS Network
TRD DCS network almost commissioned still
fighting bugs together with IT in the access to
our Netgear switches. operation of
devices within DCS network works smoothly
26DCS Status
J. Mercado, K. Schweda
- All worker nodes (WNs) upgraded to PVSS 3.6
- FSM based controls are being set up currently
- Distributed system using the standard ALICE user
interface (goal operate next week from ON) - Controls designed for full TRD (LV, HV, FEE and
PCU) - Upcoming devices (Wiener, Iseg, FEE) will just be
added - Pre-trigger pre-installation ongoing
- Needs still FSM integration ? will be rather
straightforward - FSM commissioning of LV, HV, FEE and PCU will
continue until the end of next week
27Gas Cooling
C. Garabatos, A. Marin, J. Mercado
- Xe/CO2 system fully operational (Ar/CO2)
- racks commissioned (10 in total)
- purifier still missing
- control system in place with PLC and PVSS
supervisory - analysis done with external monitor
- several major leaks in piping fixed
- gas recirculating at 300l/h (10l/h fresh gas) -
started Monday - 80 ppm O2 yesterday around lunch
- pressure stability 0.400.02(!) mbar
- gas system ready
- cooling plant operational minor modifications
needed
28 Commissioning Summary
- SM08 start of operation end of March
- found and fixed a lot of bugs
- entire infrastructure for sector 08
- is almost commissioned
- next sector 09 under preparation
- focus on FSM, FEE configuration and
- cosmic data taking with GTU from now on
- we thank CERN TC for continuous support
29ROB Production by MSC (I)
I. Rusanov, Th. Blank
production status until end of 2006 yield
90 sufficient ROBs for next super module
30ROB Production by MSC (II)
I. Rusanov
- first production in 2007
- yield 30
- - problem traced to insufficient tempering after
balling of MCMs - solution in hand - production restarted
- all ROB boards for 3.5 super modules finished
and tested - Have 270 ORI boards (4.5 SM) - another 330 end
of June
31GTU Status
J. deCuveland, V.Angelov
60 fibers to first SM
Setup at Point-2Rack C18 April 2007
- one crate with 5 TMUs, 1 SMU and 1 TGU spares
successfully installed at Point-2 - DCS boards on the SMU and TGU units accessible
via Ethernet - remote programming of FPGAs and flash memories
32GTU Status (2)
J. deCuveland, V.Angelov
Trigger Concentrator Backplane
- access to PowerPC processors and to internal
configuration registers in the FPGA designs via
DIM server - stable optical link between the SM and the TMUs,
optical power from ORIs measured - correct number of data words received at the TMUs
after each event - stable data transmission over the GTU backplane
between the 5 TMUs and the SMU
Main GTU Backplane
Setup at Point-2, Rack C18, April 2007
final data rates SM-gtDDL achieved 60 1.92
Gbits/s
33GTU To-Do
- Problems
- data packet sent via the DDL has expected size,
however contains obvious errors - debugging in progress
- To be done
- solve above problem
- test with pretrigger simultaneously sent to all
ROBs - test the interface to CTP
- PVSS/ECS integration
- extend existing designs
- Multi-Event buffering mode
- Tracking
- production, test, and integration of remaining
hardware
The GTU Team, April 2007
34TRD Pre-Trigger Status
K. Oyama, R. Schicker, R. Wagner, H.K. Soltveit
- Front-end-boxes with T0/V0 pre-amps production
for C-side finished - under test in Lyon - FPGA configurations (JTAG) and SCSN controls from
DCS board over long (10 m) lines for cascaded
boxes work fine - CB-TOF (control box with TOF signal inputs)
propagated clock and trigger from TTCviTTCex to
DCS boards in lab - found problem with imprecise PPL of TTCex in
repeater solution separate TTC clock generator
from TTC group - CB-TOF parts arrived at CERN (Tuesday)
- commissioning with cosmic trigger planned for end
of this week
35Electronics Summary
- electronics production now entirely done in
industry - MCM production with good yield
- ROB production now with good yield
- testing and thermo-cycles done in Heidelberg
- production/commisioning of GTU under way
- full integration of 1st super module successful
- noise level as measured in the lab