WREZ Phases 2, 3, 4 - PowerPoint PPT Presentation

1 / 24
About This Presentation
Title:

WREZ Phases 2, 3, 4

Description:

WREZ project Phases 1, 2, 3, 4. Status of activities. Phase 2 ... FERC pre-emption authority under EPAct 2005 undercut by 4th Circuit Court decision ... – PowerPoint PPT presentation

Number of Views:29
Avg rating:3.0/5.0
Slides: 25
Provided by: DougL89
Category:
Tags: wrez | phases

less

Transcript and Presenter's Notes

Title: WREZ Phases 2, 3, 4


1
WREZ Phases 2, 3, 4
  • Doug Larson and Tom Carr
  • Western Interstate Energy Board

2
Outline of Presentation
  • WREZ project Phases 1, 2, 3, 4
  • Status of activities
  • Phase 2
  • Activities (WREZ model WREZ request to WECC)
  • Key players
  • Phase 3
  • Feb 24-25 Resource Planning meeting
  • Key players
  • Phase 4
  • Context
  • Key players
  • Changing role of Technical Committee in Phases
    2-4

3
WREZ Project Phases
  • Phase 1
  • Identify developable renewable energy zones
  • Develop renewable resource supply curves for each
    zone
  • Phase 2
  • Develop model to estimate delivered price of
    power from renewable energy zones to load centers
  • Develop conceptual transmission plans
  • Phase 3
  • Foster coordinated renewable resource acquisition
    by utilities
  • Phase 4
  • Facilitate interstate transmission for renewables

4
Phase 2 WREZ Model
  • Released Model to public March 13
  • Model webinar training sessions held
  • GTMWG March 12 16
  • Resource and transmission planners March 18 24
  • Website for WREZ Model
  • http//www.westgov.org/wga/initiatives/wrez/gtm/mo
    del.htm
  • Download User guide, methodology and assumptions
  • Video of the March 24 training session
  • Solicit comments from model users
  • Peer analysis tool under construction
  • Improvements being made per public comments
  • Version 2.0 ready about 2 weeks after REZs
    finalized

5
(No Transcript)
6
(No Transcript)
7
(No Transcript)
8
(No Transcript)
9
(No Transcript)
10
(No Transcript)
11
Phase 2 Conceptual Transmission Plans
  • January WREZ request to WECC
  • WECC/TEPPC review, work plan, modeling
  • TEPPC review process of study requests from 8
    entities Feb. April 28.
  • Database and scenario inputs to model
    (spring-summer 2009)
  • Modeling runs (summer-fall 2009)
  • Analysis and drafting report (fall 2009)
  • Complete and approve report (winter 2010)

12
Phase 2 Key Players
  • Utilities and other model users
  • WECC (TEPPC and TEPPC stakeholders)
  • Sub-regional planning groups
  • Depending on Congressional action, FERC

13
Phase 3 Coordinated Procurement
  • Status
  • Feb 24-25 Western Interconnection Resource
    Planning meeting
  • 80 attendees (25 utilities, 12 states/provinces
    including 10 PUCs)
  • Secured LSE volunteers to help scope out Phase 3
  • Takeaways
  • Resource planners looking at near-term options
    those requiring multiple years of transmission
    develop at disadvantage
  • Ron Lehr ongoing research on utility acquisition
    processes
  • Next steps
  • Scope further Phase 3 work
  • Guesstimate of direction
  • Common research areas (e.g., any legal barriers)
  • Meetings of LSEs and PUCs who are interested in
    the same REZs

14
Phase 3 Key Players
  • Utility resource planners and generation
    procurement personnel
  • PUCs

15
Phase 4 - Facilitate interstate transmission for
renewables
  • Fluid playing field
  • Unprecedented number of proposed transmission
    projects
  • Some facing downsizing
  • Others facing corridor constraints
  • All face uncertainty about demand for renewable
    generation (e.g., no federal carbon or renewable
    rules)
  • FERC pre-emption authority under EPAct 2005
    undercut by 4th Circuit Court decision
  • 5 major bills in Congress
  • Obama Administration developing its policy on
    transmission for renewables
  • Potential revision and readoption of WGA
    Transmission Permitting Protocol

16
Proposed major transmission projects
17
Situation Analysis
  • Administration
  • FERC Chair and Secs of Energy, Interior, Ag and
    meeting to formulate Obama plan on transmission
    for renewables and response to Congress
  • Meeting with Govs in Park City?
  • Congress
  • Five bills so far (Reid, Bingaman,
    Dorgan/Voinovich, Nelson, Waxman-Markey)

18
Outline of Bills
  • Dorgan/Voinovich
  • No REZ language
  • Applies to transmission for renewables, fossil
    with CCS
  • Generally same, but allows multiple planning
    entities in an interconnection and more detail
    (e.g., avoid areas,
  • Generally same
  • FERC in control but greater constraints on FERC
    ability to ignore state
  • Reid
  • Pres. designates REZs
  • Applies only to transmission for renewables
  • Generally same
  • Generally same
  • Bingaman
  • No REZ language
  • Applies to all transmission
  • Transmission plans
  • FERC designates interconnection-wide planning
    entity/entities
  • FERC approves transmission plans if no plan,
    FERC does plan
  • Financing
  • Regional planning entity proposes cost allocation
    for project OR FERC will
  • If FERC does, then spread cost as broadly as
    possible
  • Siting
  • FERC ultimately decides
  • Nelson
  • No REZ language
  • Applies to National Energy Superhighway and
    connector lines
  • FERC develops plan
  • Govt pays

19
Feedback from WIEB/WIRAB/CREPC Discussions
  • Governors need to weigh in with Congress and
    Administration and be prepared to respond rapidly
    to changing policy proposals
  • Support interconnection-wide plans that have
    consequences
  • Governors must have a major role in plans (e.g.,
    approve electricity futures to be studied,
    approve plan)
  • WECC is the right entity to develop transmission
    plan
  • Feds should have to follow approved plan
  • Feds pay to right size lines to
    geographically-constrained, low-carbon generation
    (existing WGA policy)
  • Support to review Section 368 corridors on
    federal land (existing WGA policy)
  • Pre-empting state siting wont speed up the
    permitting process
  • Need new interstate permitting agreement with
    federal agencies
  • Governors need to support actions to reduce cost
    of integrating wind and solar, including urging
    FERC and DOE action

20
Phase 4 Key Players
  • Congress
  • Carbon/RPS rules
  • Changes to transmission development process
  • Obama Administration
  • Allocation of stimulus money
  • WAPA and BPA
  • Loan guarantees
  • 4.5 billion smart grid (80 million for
    transmission to conduct a resource assessment and
    an analysis of future demand and transmission
    requirements)
  • New Administration policy
  • Western Governors
  • Others
  • LSEs and transmission developers
  • WECC and sub-regional planning groups
  • PUCs

21
Summary of Key Players on Phase 2-4
22
Changing Role of Technical Committee
  • The success of Phases 2-4 is in the hands of a
    much broader group of decision-makers than Phase
    1
  • Technical Committee may need to shift to focus on
    transmission-related issues
  • Oversight of work group activities

23
Potential Future Tasks
  • Phase 1
  • Refine environmental data
  • Update technology cost information (late 2009?)
  • Phase 2
  • Encourage parties to use model to specify
    preferred REZs
  • Upgrade model through 2009
  • Transfer of model to WECC in 2010
  • Review WECC analysis of transmission needs under
    WREZ scenarios (late 2009/early 2010)
  • Assemble environmental data useful in
    transmission siting

24
Potential Future Tasks
  • Phase 3
  • Approve refined work plan for Phase 3 (after REZ
    info and Model version 2.0 available, e.g. June)
  • Monitor utility procurement plans (June
    2009-forward)
  • Phase 4
  • Monitor changing federal playing field on
    permitting, cost recovery
  • Monitor proposed transmission projects serving
    REZs and obstacles to such projects
  • Offer advice on needed improvements to
    transmission project development and permitting
    processes
Write a Comment
User Comments (0)
About PowerShow.com