Title: Folie 1
1Task number SIS18- 4
Injection / extraction upgrade
Jürgen Florenkowski GSI, Darmstadt Agenda Annual
Report Meeting EU construction ( CNI )
contract "DIRAC-PHASE-1" for the FAIR
project September 26, 2006
2Upgrade Motivation
- Extraction
- We have to analyse the extraction in booster
mode. Further investigations has to find out,
where is the limitation for the acceptance. - The first assumption is that the dipole chamber
in front of the extraction channel is the reason
for the limitation.
3Upgrade Motivation
- Injection (e septum)
- The maximum field strength of the electrostatic
septum is not sufficient for injection of U28 -
beams at the standard energy of 11.4 MeV/u - (at present 7.1 MeV/u).
- Currently the electrostatic septum is not
protected against beam losses in the injection
channel. The new one has a scraper to protect the
anode made of 0.1mm wires. - Beam diagnostic is necessary to minimize the
losses while injection from transfer channel to
SIS. This is not present yet.
4Upgrade Motivation
- Inflector Magnet
- The acceptance limitation is given by the present
inflector magnet in front of the injection
septum. The present magnet is divided in 3 parts.
A new development optimise the beam path to the
limited space between transfer channel and SIS
beam pipe. - For the bake procedure we have to raise the coils
from the beam pipe. Only then we are able to
install the heating seal. After the bake
procedure we have to reinstall the coils. The new
inflector magnet has the heating seal build in.
That minimize the time for service.
5The heavy ion synchrotron SIS 18
Injection septum
SIS 18
Inflector magnet
Experiments
UNILAC
Extraction beam line
6Main components of an e - septum
Deflection unit
Cathode
Anode
High voltage power supply
Vacuum chamber
7Parameters of the e-septum
Comparison of existing and new e-septum
8Electrostatic field calculations
SIS 18
UNILAC
Anode
Cathode
- Design values
- Voltage 300 kV
- Gap width 3 cm
- Field strength max. 100 kV / cm
- Deflection angle 2.5
9Septum design
- Design goals
- Adjustable anode and cathode
- 300 kV insulation
- Back able up to 300
- Beam diagnostic (profile monitor)
- Septum protection (scraper)
10Cathode surface treatment
- Requirements
- 300C back able surface
- Field strength 100KV / cm
- Cooperation with Fraunhofer Institut
Elektronenstrahl- und - Plasmatechnik
- Plasma activated high rate deposition of
Aluminumoxid - GSI will ship a test cathode of high-grade steel
and aluminum in October 2006 - After treatment GSI will test the maximum
reachable field strength and heat the test
cathode up to 300C
11Option electron - beam treatment
In parallel we have the treatment procedure with
pulsed electron beams developed by the Institute
of High current electronics in Tomsk (RU)
Radiation facility
Stainless steel treatment
After
Before
12Time schedule
13Costs e - septum
- Construction costs GSI
- Preliminary investigations and project analyses
110 h - 3D construction 470 h
- Drawings 2D 100 h
- Summary 680 h
- Manufacturing costs GSI and other companies
- Material 42.600
- Assembly 261h / 60 15.660
- Unexpected or additional work 21.847
- Summary 80.107
- Cathode Treatment
- Fraunhofer Institut Elektronenstrahl- und
Plasmatechnik 20.900 - Institute of high current electronics in Tomsk
(RU) 200.000 - 300KV power supply
- Supplied by FUG and examined by GSI 160.000
14Inflector Magnet
Inflector Magnet
Device to raise the Magnet
Connector side
e - septum
SIS beam pipe
Rack
15New design
- Design goals
- Build in heating seal
- Optimized beam path
Magnet
Injection channel
Connector box
SIS beam pipe
16Inflector Magnet
- To finish the project inflector magnet we have to
- Fix the design
- We have to examine the offers from outside firms.
The dead line for the offers was 22.09.06. - Check the personnel involvement
- Cost estimate
- Commissioning parts
- Assembling the magnet
- Testing
- Installation