Description:

Vacation and QA problems. Connectors quality. Bobbins damage ... Shift planner (developed by D. Robinson) works very well for planning the ... – PowerPoint PPT presentation

Number of Views:92
Avg rating:3.0/5.0
Slides: 19
Provided by: acio
Category:

less

Transcript and Presenter's Notes

Title: SCT Service Installation


1
SCT Service Installation
  • Overview
  • Status of Type IV Cable Installation
  • Type II/III Cable Installation
  • Plan for the next six months
  • Safety course today _at_ 1245

2
Overview
  • 2044 (spares) double length Type IV cables
    (Power Control) from PP3 racks through holes to
    US(A)15 racks
  • 4088 (100 spares) Type II/III (spliced on the
    outside of the calorimeter and up at z0) from
    PPB(F)1 to PP3 racks
  • DCS, Heater Cables, and PP3 (will be discussed in
    the ID installation)
  • 8 PP3 racks in each side of the cavern (USUSA
    sides)
  • Up to 10 crates of 30 PP3 units
  • 11 power racks in US15 and 11 in USA15
  • Up to 4 crates of 48 channels
  • TC installation team
  • S.Malyukov, E.Kudinov, L.Reed, N.Massol
  • 27 people from IHEP Protvino
  • Several teams are working in parallel (9 people
    per team)

3
PP3 Racks in UX15 (US15 side)
Y.52-4.X7, Y.53-4.X7 Y.52-1.X6,
Y.46-1.X6 Y.43-1.X6, Y.34-1.X6 Y.51-2.X2,
Y.52-2.X2
4
PP3 Racks in UX15 (USA15 side)
Y.51-23.X8 Y.52-23.X8 Y.53-23.X8 Y.51-26.X5,
Y.53-26.X5 Y.52-25.X2, Y.53-25.X2 Y.51-25.X1
5
Layout of PP3 rack in UX cavern
6
PP3 to US
PP3 rack US rack hole UX/US
Y.37-1.X6 Y.05-14.S2 12
Y.43-1.X6 Y.10-15.S2 11
Y.43-1.X6 Y.11-15.S2 10
Y.47-1.X6 Y.11-15.S2 10
Y.43-1.X6 Y.12-15.S2 9
Y.47-1.X6 Y.12-15.S2 9
Y.52-1.X6 Y.23-15.S2 7
Y.52-4.X7 Y.23-15.S2 7
Y.52-4.X7 Y.24-15.S2 21
Y.53-4.X7 Y.25-15.S2 20
Y.53-2.X2 Y.26-15.S2 6
Y.51-2.X2 Y.27-15.S2 19
Y.53-4.X7 Y.27-15.S2 19
Y.51-2.X2 Y.28-15.S2 5
Y.52-1.X6 Y.28-15.S2 5
Y.52-2.X2 Y.29-15.S2 4
7
Installation of Type IV Cables
  • Type IV cables are delivered in double lengths
    and pulled between the UX15 and the US(A) caverns
  • 800 pieces (double length cables) installed on
    US side (almost completed)
  • Up to 40 cables per day pulled from UX to US(A)

Hole
Dummy PP3
Racks on Level 6 US side
8
In US15
  • Cut cables and connectors on the power supply
    side installed in situ
  • First rack (200 cables/connectors) completed
    early in July
  • Work performed by SEDELEC (subcontract of
    KontaktSysteme that provides the double length
    cables
  • Many mistakes (20 connectors have just been
    repaired) several label mismatch still to be
    fixed
  • They raised the cost significantly for future
    connector work
  • New Plan
  • TC will help with connector attachment
  • Nicolas Massol joined TC in September. One of
    his tasks is to organize connector activity
  • Work with Petr Kubik (Prague) to discuss
    technical aspects and qualify samples made by
    other companies being contacted
  • Meanwhile cables are being cut to some extra
    length and all tooling has been purchased to
    make prototypes

9
Delivery Issues
  • Installation rate driven by delivery schedule
  • Delivery in July/August was very slow
  • Vacation and QA problems
  • Connectors quality
  • Bobbins damage
  • Bobbins already at CERN are going to be sent back
    to the fabrication company (Novacavi) to get
    cleaned up
  • Delay of components delivery from CERN to company
  • Need to keep contact with CERN purchasing and
    Vendor
  • Ramp up
  • 200 pieces/week expected soon after bobbins
    damage crisis is solved but so far the max number
    of pieces we have seen is 120
  • Hopefully all type-IV delivered by mid-November

10
Delivery (QA - Connectors)
  • Connectors signal wires too long
  • Some cables couldnt be used
  • One week halt of production

11
Delivery (QA - Packaging)
  • Packaging palette were sent with only plastic
    wrap around bundles
  • Cables were getting wet during transportation and
    delivery at CERN
  • About 40 cables lost (30 in one delivery)

12
Delivery (QA - Bobbins)
  • Cable bobbins dirty and damaged
  • Bobbins are kept outside (at CERN) for long time
  • Other (than water) damage under investigation
  • Company claims delay in fabrication to deal with
    these problems
  • Dont know yet delay due to shipping bobbins back
    to Italy

13
Type II/III Cables
  • Double harness ordered from Ineo
  • Work on splicing started in August
  • Installation of connectors on the PP3 end at the
    factory
  • Need to provide exact length for both types
  • Use dummy PP1 with some load to test that the
    splice didnt get damaged after installation
  • JST and FCI connectors very delicate better to
    test at the PP3 end
  • Two Contracts first to produce all the harnesses
    and then to install the connectors
  • Splice is verified at the company
  • Need QA going on during production
  • Last visit by Pepe B. Maarit W. and Laurent
    Gillain(CERN purchasing) quite satisfactory
  • By November all harness will be made
  • Cables with PP3 connectors between November and
    March

14
Current Installation Activities (Type IV)
  • Overall coordination (Sandra)
  • Work closely with Sergei Malyukov and the TC team
  • Provide complete layout/mapping for racks in both
    sides
  • Bjarne is still helping from Bergen
  • Regular presence to check mapping/labels and
    prepare racks
  • Discussion on installation priority and
    occasional revise original layout
  • update DB table and EDMS documents
  • Organize cable testing shifts
  • Connector at the power supply end (Petr
    Kubik/Prague)
  • Cable testing (Sandra, Petr and SCT
    Collaboration)
  • Follow up cable procurement and delivery (Pippa,
    Sandra, Maarit/TC)
  • PP3 installation soon (Ashley French/Melbourne
    with Petr)
  • SCT Cables EDMS ID 624679, Cable Procurement
    Follow up table ID508310,
  • Overall Safety and Health Procedure ID 593278

15
Type IV Testing
  • Tester designed and provided by Ljubljana
    (Gregor, Erik)
  • 2 Test box 2 Laptops test cables
  • Gregor and Erik upgraded features of tester in
    July
  • Web based DB
  • Test steps
  • Cables are tested at reception (acceptance test)
  • After being pulled from UX15 to US(A)15
    (uncut-double length)
  • After they are cut in the US side at connectors
    are installed
  • Shift planner (developed by D. Robinson) works
    very well for planning the activities and have
    people to sign up
  • http//www.hep.phy.cam.ac.uk/si-bin/sctworkplanner
    .cgi
  • (register and contact me)
  • What is needed to be able to take a shift
  • take the 3-levels safety training course (at the
    pompiers station)
  • make the access request on EDH (ATLAS-U, LHC
    Tunnel)
  • get your safety boots helmet at the CERN store
    (or borrow them)

16
Procurement Schedule
  • Type IV delivered and installed December
  • Connector work of Type IV
  • (power supply end) could start
  • in 3 weeks and it will take 4 months January
  • Type II/III double harness with splicing January
  • single cable with PP3 connector Nov-March
  • PP3 delivery and installation Oct/Nov

17
Work Plan
18
Safety Training Course
  • Building 65-1-003
  • (Pompiers station)
  • At 1245
  • Please arrive 5 minutes earlier
  • to register
Write a Comment