1SCT Service Installation
- Overview
- Status of Type IV Cable Installation
- Type II/III Cable Installation
- Plan for the next six months
- Safety course today _at_ 1245
2Overview
- 2044 (spares) double length Type IV cables
(Power Control) from PP3 racks through holes to
US(A)15 racks - 4088 (100 spares) Type II/III (spliced on the
outside of the calorimeter and up at z0) from
PPB(F)1 to PP3 racks - DCS, Heater Cables, and PP3 (will be discussed in
the ID installation) - 8 PP3 racks in each side of the cavern (USUSA
sides) - Up to 10 crates of 30 PP3 units
- 11 power racks in US15 and 11 in USA15
- Up to 4 crates of 48 channels
- TC installation team
- S.Malyukov, E.Kudinov, L.Reed, N.Massol
- 27 people from IHEP Protvino
- Several teams are working in parallel (9 people
per team)
3PP3 Racks in UX15 (US15 side)
Y.52-4.X7, Y.53-4.X7 Y.52-1.X6,
Y.46-1.X6 Y.43-1.X6, Y.34-1.X6 Y.51-2.X2,
Y.52-2.X2
4PP3 Racks in UX15 (USA15 side)
Y.51-23.X8 Y.52-23.X8 Y.53-23.X8 Y.51-26.X5,
Y.53-26.X5 Y.52-25.X2, Y.53-25.X2 Y.51-25.X1
5Layout of PP3 rack in UX cavern
6PP3 to US
PP3 rack US rack hole UX/US
Y.37-1.X6 Y.05-14.S2 12
Y.43-1.X6 Y.10-15.S2 11
Y.43-1.X6 Y.11-15.S2 10
Y.47-1.X6 Y.11-15.S2 10
Y.43-1.X6 Y.12-15.S2 9
Y.47-1.X6 Y.12-15.S2 9
Y.52-1.X6 Y.23-15.S2 7
Y.52-4.X7 Y.23-15.S2 7
Y.52-4.X7 Y.24-15.S2 21
Y.53-4.X7 Y.25-15.S2 20
Y.53-2.X2 Y.26-15.S2 6
Y.51-2.X2 Y.27-15.S2 19
Y.53-4.X7 Y.27-15.S2 19
Y.51-2.X2 Y.28-15.S2 5
Y.52-1.X6 Y.28-15.S2 5
Y.52-2.X2 Y.29-15.S2 4
7Installation of Type IV Cables
- Type IV cables are delivered in double lengths
and pulled between the UX15 and the US(A) caverns
- 800 pieces (double length cables) installed on
US side (almost completed) - Up to 40 cables per day pulled from UX to US(A)
Hole
Dummy PP3
Racks on Level 6 US side
8In US15
- Cut cables and connectors on the power supply
side installed in situ - First rack (200 cables/connectors) completed
early in July - Work performed by SEDELEC (subcontract of
KontaktSysteme that provides the double length
cables - Many mistakes (20 connectors have just been
repaired) several label mismatch still to be
fixed - They raised the cost significantly for future
connector work - New Plan
- TC will help with connector attachment
- Nicolas Massol joined TC in September. One of
his tasks is to organize connector activity - Work with Petr Kubik (Prague) to discuss
technical aspects and qualify samples made by
other companies being contacted - Meanwhile cables are being cut to some extra
length and all tooling has been purchased to
make prototypes
9Delivery Issues
- Installation rate driven by delivery schedule
- Delivery in July/August was very slow
- Vacation and QA problems
- Connectors quality
- Bobbins damage
- Bobbins already at CERN are going to be sent back
to the fabrication company (Novacavi) to get
cleaned up - Delay of components delivery from CERN to company
- Need to keep contact with CERN purchasing and
Vendor - Ramp up
- 200 pieces/week expected soon after bobbins
damage crisis is solved but so far the max number
of pieces we have seen is 120 - Hopefully all type-IV delivered by mid-November
10Delivery (QA - Connectors)
- Connectors signal wires too long
- Some cables couldnt be used
- One week halt of production
11Delivery (QA - Packaging)
- Packaging palette were sent with only plastic
wrap around bundles - Cables were getting wet during transportation and
delivery at CERN - About 40 cables lost (30 in one delivery)
12Delivery (QA - Bobbins)
- Cable bobbins dirty and damaged
- Bobbins are kept outside (at CERN) for long time
- Other (than water) damage under investigation
- Company claims delay in fabrication to deal with
these problems - Dont know yet delay due to shipping bobbins back
to Italy
13Type II/III Cables
- Double harness ordered from Ineo
- Work on splicing started in August
- Installation of connectors on the PP3 end at the
factory - Need to provide exact length for both types
- Use dummy PP1 with some load to test that the
splice didnt get damaged after installation - JST and FCI connectors very delicate better to
test at the PP3 end - Two Contracts first to produce all the harnesses
and then to install the connectors - Splice is verified at the company
- Need QA going on during production
- Last visit by Pepe B. Maarit W. and Laurent
Gillain(CERN purchasing) quite satisfactory - By November all harness will be made
- Cables with PP3 connectors between November and
March
14Current Installation Activities (Type IV)
- Overall coordination (Sandra)
- Work closely with Sergei Malyukov and the TC team
- Provide complete layout/mapping for racks in both
sides - Bjarne is still helping from Bergen
- Regular presence to check mapping/labels and
prepare racks - Discussion on installation priority and
occasional revise original layout - update DB table and EDMS documents
- Organize cable testing shifts
- Connector at the power supply end (Petr
Kubik/Prague) - Cable testing (Sandra, Petr and SCT
Collaboration) - Follow up cable procurement and delivery (Pippa,
Sandra, Maarit/TC) - PP3 installation soon (Ashley French/Melbourne
with Petr) - SCT Cables EDMS ID 624679, Cable Procurement
Follow up table ID508310, - Overall Safety and Health Procedure ID 593278
15Type IV Testing
- Tester designed and provided by Ljubljana
(Gregor, Erik) - 2 Test box 2 Laptops test cables
- Gregor and Erik upgraded features of tester in
July - Web based DB
- Test steps
- Cables are tested at reception (acceptance test)
- After being pulled from UX15 to US(A)15
(uncut-double length) - After they are cut in the US side at connectors
are installed - Shift planner (developed by D. Robinson) works
very well for planning the activities and have
people to sign up - http//www.hep.phy.cam.ac.uk/si-bin/sctworkplanner
.cgi - (register and contact me)
- What is needed to be able to take a shift
- take the 3-levels safety training course (at the
pompiers station) - make the access request on EDH (ATLAS-U, LHC
Tunnel) - get your safety boots helmet at the CERN store
(or borrow them)
16Procurement Schedule
- Type IV delivered and installed December
- Connector work of Type IV
- (power supply end) could start
- in 3 weeks and it will take 4 months January
- Type II/III double harness with splicing January
- single cable with PP3 connector Nov-March
- PP3 delivery and installation Oct/Nov
-
17Work Plan
18Safety Training Course
- Building 65-1-003
- (Pompiers station)
- At 1245
- Please arrive 5 minutes earlier
- to register
-