SCT Services Installation
  • Type IV
  • PP3
  • Type II-III and PP1
  • Fibre Cables
  • DCS
  • Testing Installation Plan

Workpackage https//edms.cern.ch/document/593278/
2
Status of Type IV Cables
  • Cables production
  • resumed in February after 3 months stop
  • See ID week February 06
  • Delivery of doubles harnesses completed (last
    week)
  • 2125 double harnesses (4250 cables)
  • Installation
  • All racks in US side 2 USA racks were installed
    last year by TC teams (Russian)
  • Installation resumed at the end of March with a
    new TC team (French)
  • Very slow startup
  • Completion of USA side was expected by the end of
    May
  • Unlikely even with 2 teams (2 shifts) and with
    participation of Russian teams
  • Connector in situ (CPE)
  • All cables (except for a few) in US15 completed
    on March 10
  • Most racks are tested
  • Very good yield
  • 2 techs returned on April 18 and currently
    working on one USA rack
  • Complete US side and continue racks in USA15 when
    full team will be back

Racks on Level 6 US side
3
PP3
  • 4261 PP3 units needed
  • 173 are spares
  • 139 empty shield cases
  • Standard subracks of 30 units
  • Mini subracks (of 5 units)
  • Special subracks (PP3 empty cases)
  • Layout of each rack can be found at
  • http//www-atlas.lbl.gov/ciocio/SCTcables/Racks_L
    ayout
  • Much of the installation done but lots of work to
    complete all racks
  • Most of subracks installed
  • Some subracks sitting by racks to be installed
  • Small fraction of cables partially plugged in
  • Rework for damages (due to installation)
  • Parts missing
  • 4 standard subracks

4
Type II-III by Sector
US PP3 racks
USA PP3 racks
336 Barrel 247 EC
336 Barrel 247 EC
Level 8
Level 7
384 Barrel 494 EC
384 Barrel 494 EC
Level 5 2
Level 6
336 Barrel 247 EC
336 Barrel 247 EC
Level 2
Level 1 2
5
SCT ServicesSequence
  • Sector 5 (top) and Sector 13 (bottom)
  • heater cables, and DCS cables (completed)
  • Sector 9 - Installation completed on May 1
  • 878 SCT cables (384 Barrel, 494 EC)
  • 18 Fibre cables (EC)
  • Sector 3 - Installation started May 2 two
    weeks to complete
  • 583 SCT cables (336 Barrel, 247 EC)
  • 27 Fibre cables (9 EC,18 Barrel)
  • Sector 1 next can start this week to allow
    parallel team work
  • 878 SCT cables (384 Barrel, 494 EC)
  • 18 Fibre cables (Barrel)
  • Sector 7 Lengths measured Length will be sent
    to company this week
  • 583 SCT cables (336 Barrel, 247 EC)
  • 27 Fibre cables (9 EC,18 Barrel)

6
Type II/III PP1 Production
  • INEO/Thurmelec are making type II-III cables in 2
    steps
  • double length harnesses as they receive
    information about the lengths
  • type II cable and type III spliced
  • type II FCI/JST connectors on both ends of double
    harness
  • Single length cables with FCT connector (PP3) are
    produced when length finalized with test cable
    measurement from cryostat to PP3 racks sector by
    sector
  • Delivery rate reached the promised 400
    cables/week
  • We are ahead with cable preparation!
  • So far good quality
  • No fatal defect found on some cables (the color
    coat is gone is some section/pattern but kapton
    insulation OK)
  • PPB1 clamps, clips, cable tray covers were
    late, not used yet during installation
  • Clamp mounting finalized today
  • Clip under revision
  • PPF1 most parts available
  • Found the best way to crimp group of drain wires
    in a ferrule and catch the ferrule with the grub
    screws into clamps holes

7
Type II/III cables Installation
  • About 1000 cables installed
  • ½ bundle /day/side/team
  • 48 cables/day but can reach 100 in the future
  • Problem with testing related to the grounding in
    cryostat (OK)
  • Mechanical problems to fit layers of 6 cables
    between clamp holder pins (all cables installed
    have been retrofit)
  • Clamp installation
  • Barrel today
  • EC final
  • Details given in April SCTSG

8
SCT Readout Cables - Status
  • All 18 (SCT readout) cables for end-cap in sector
    9 installed and tested, all OK (this was the
    first sector with SCT fibre cables).
  • 18 barrel cables installed in sector 3 during
    last two weeks (9 on side A and 9 on side C).
    These were the first SCT barrel readout cables
    installed. Barrel cables are quite fragile due to
    a 3 meter long strip-back of the cable cladding
    at the end of the cables. No serious problems
    were encountered during the installation. The
    cables need to be tested, probably with the help
    of people coming from Oxford.
  • 9 end-cap cables in sector 3 will be installed in
    the next phase, perhaps this week (6 cables on
    side A and 3 cables on side C).
  • Sector 1 should be installed afterwards. There
    are 18 end-cap cables and no barrel cable.

9
FSI delivery cables and tubes
  • 38 cables
  • The first FSI delivery cable cut and prepared for
    the installation in sector 3. The length of the
    cable taken from the EDH table.
  • After the first cable is installed, 8 more cables
    will be cut, labeled and installed (i.e. all
    cables for sector 3). The lengths to cut will be
    determined from the first cable.
  • The first FSI tube is going to be bent, cut and
    installed this week by the technicians.
  • The drawings of the tubes are not precise and
    needed some modifications to respect the real
    situation on the cryostat flange

10
SCT DCS Cables
  • 128 type II and 40 type IV
  • All cables for the barrel are in the pit and
    ready for installation
  • Sector 13 24 cables are installed and tested
  • Sector 5 24 cables are installed and tested
  • 3 cables in sector 5 were damaged during
    installation (caught on sharp edge of cable tray)
    repaired
  • 20 cables to be installed in sector 3 are ready
    but installation should occur soon
  • Installation of SCT DCS cables interleaved with
    ID DCS cables

11
Installation Testing Activities
  • Type IV (2 people Petr Prague)
  • Acceptance test
  • Test in rack after installation
  • Test of cut cables after connector in situ work
  • Plug-in cables into PS crates test with
    feedtrough
  • Type II-III Preparation (5 people Vlastik Kuo
    Ming)
  • Acceptance test (partial)
  • Visual inspection
  • Folding the shield and cut it the right amount,
    fix it
  • Organize boxes with right cables to send
    following installation sequence
  • Type II-III Installation(2 people Lars Neil
    part time Jacek)
  • Mount dPPB1 and dPPF1
  • For Barrel
  • Squeezing the cables to fit between pin and clamp
    holder
  • Plug-in of the delicate JST/FCI connectors to
    dPPB1
  • Placing the clamp (now), placing the clip (later)
  • For Endcap
  • crimp group of drain wires in a ferrule and catch
    the ferrule with the grub screws into clamps
    holes

12
Issues
  • PP3
  • Damaged In the pit left by racks
  • Damaged In the racks after installation/plug-in
    of type IV by French team
  • Parts to finish assembly and installation too
    late
  • Connector damage
  • In US15 they are left too long on the floor
  • Other cables installation interference
  • Tester
  • Different flavor that work with different
    configuration of cable chain
  • Multiple laptops failure (ok now)
  • Several software updates to cope with different
    configurations (over last few months)
  • Getting parts in time
  • Spares installation
  • 2 spare type ii-iii EC cables installed but too
    short need splicing extension
  • Defective dPPF1
  • Faulty cable was actually due to a bad channel on
    dPPF1 (that was marked color dots but it was used
    anyway)
  • Type III installation testing
  • Difficult conditions for testing because sequence
    of cables installed doesnt match order in PP3
    rack, cables are set aside and plug-in has to
    happen for all cables when rack completed
  • Extra length to reroute on additional trays

13
Schedule
  • Type II-III installation (from Marzio) by
    mid-June
  • New schedule is expected this week
  • Likely to go until end of June

Our schedule
  • Type IV installation end of May going into
    June
  • Connector in situ/testing mid-June/end of June
  • PS crates mid-June (US side) July (USA side)
  • PP3 assembly, installation end of May
  • All cables plugged into PP3 end of June
  • To meet this schedule we need continuous presence
    of people at CERN
  • Last couple of weeks went relatively well but
  • Hard/inefficient to train/instruct/introduce so
    many people
  • Mistakes
  • Difficulties to direct people to tasks in the pit
    because
  • underground access not requested or level4A not
    taken before hand
  • Critical area in the type II-III acceptance
    installation and testing
  • SCT participation very valuable to add to people
    who are resident
  • NEED technical participation to go into July

14
(No Transcript)
15
To work on cabling
  • http//www.hep.phy.cam.ac.uk/si-bin/sctworkplanner
    .cgi
  • To sign up for shifts (and contact me because of
    unexpected changing in rate delivery/testing
    problems)
  • Safety courses
  • 1) basic safety training course (level 1-2-3
    video in B55)
  • http//safety-commission.web.cern.ch/safety-commi
    ssion/SC-site/sc_pages/training/basic.html
  • 2) Level 4 for working in US15 Oxybox (we have
    them)
  • If you have an AIS LOGIN (used for EDH
    documents), you can follow the course from
    anywhere
  • (even outside CERN) with AIS login by accessing
    http//sir.cern.ch.
  • If you have no AIS LOGIN, you need to register at
    the following address level4.training_at_cern.ch
  • 3) Level 4A mandatory to enter the ATLAS
    underground areas
  • This course is composed of 4 modules Cryogeny,
    Evacuation, Installation and Magnet. Each of
    these modules is followed by a small test which
    you have to take and pass.
  • If you do not yet have an AIS login, please
    contact the ATLAS secretariat and ask
    for this AIS account (they must be registered
    with ATLAS). If this is not possible, we will
    organize special training at CERN.
  • 4) make the access request on EDH
  • 5) get your safety boots helmet (or borrow
    them)
  • TRY TO GET AS MUCH AS POSSIBLE DONE BEFORE COMING
    TO CERN

16
LINKS Summary
  • SCT Cables Web page
  • http//www-atlas.lbl.gov/ciocio/SCTcables/
  • Mapping, technical appendices, cables related
    documents
  • https//edms.cern.ch/document/624679/1
  • Shifts
  • Shift planner (developed by D. Robinson) works
    very well for planning the activities and have
    people to sign up
  • http//www.hep.phy.cam.ac.uk/si-bin/sctworkplan
    ner.cgi
  • Safety courses
  • Level 1-2-3 basic course for access underground
    and point 1
  • http//safety-commission.web.cern.ch/safety-commis
    sion/SC-site/sc_pages/training/basic.html
  • Level 4 with AIS login http//sir.cern.ch.
  • Level 4A AIS login
  • Overall Safety and Health Procedure Document
    PPSPS
  • https//edms.cern.ch/document/593278/
  • Rack Wizard
  • http//atlas.web.cern.ch/Atlas/TCOORD/Activities/I
    nstallation/Database/rack.htm
Write a Comment
User Comments (0)
About PowerShow.com