Title: Folie 1
1COOLSB2
Ramped superferric dipole magnet for NESR
Hanno Leibrock, GSI Darmstadt Kick-off meeting
for EU Design Study "DIRACsecondary-Beams" for
the FAIR project April 14-15, 2005
2NESR in FAIR
FAIR Stage 1
versatile storage ring NESR
decelarated beams gt ramped dipoles
3Tasks
- EU FP6 task COOLSB2
- superferric NESR-dipole for 1 T/s ramp rate
- Subtasks
- Magnet layout, yoke design
- Superconducting coil design
- Cryostat design
- gt functioning prototype magnet
4Dipole Parameters
NESR Dipoles
Numbers 24
Maximum field 1.6 T
Minimum field 0.06 T
Ramp rate 1 T/s
Maximum ?B 1.5 T
Bending radius 8.125 m
Deflection angle 15
Effective length 2.128 m
Useable gap width 250 mm
Useable gap hight 70 mm
Real gap height (heating) 90 mm
Field quality ?1?10-4
moderate field (lt1.6 T), large aperture ?
superferric design
- Because
- allows large apertures since the flux is guided
by the iron and the field quality is defined by
the pole shape, - field enhancement by the iron,
- low operation costs
challenges in red !
5Preliminary 2D - design (by C. Muehle)
Nuclotron cable
6000 A, 10 turns, 150 A/ mm2 (coil) curved
(sagitta 69 mm)
6Field distribution
7Field distribution
8SC coil design choice of the conductor
- ramp rate 1 T/s ? low inductance needed ? cable
Nuclotron cable
Rutherford cable
CICC
- eddy currents in helium containment (bobbin)
and cryostat
- ? 'tube' forced-flow-cooling
- ? 'non'-conducting cryostat
9Gantt diagram for RD with milestones
Milestones
Feasibility studies December 31, 2005 Model
cryostat delivered June 30, 2006 Prototype
dipole delivered December 20, 2007
10Conclusions
- moderate field (lt1.6 T), large aperture ?
superferric design (low operation costs) - ramp rate 1 T/s ? low inductance needed ? cable
- a preliminary magnet design exists
- the design of the cryostat has to make sure that
eddy current effects are negligible - planned prototype dipole delivery december 2007
11Die Leere
12Advantages of superconducting and resistive
magnets
13Normal conducting CR-dipoles
- Use of the same yoke for the normal conducting
solution - gt Problems
- Purcel filter -gt loss of ampere turns
- High flux density in yoke -gt loss of ampere turns
- Small coil window -gt high current density
- gt 465kW power loss per magnet
- Use of an appropriate (enlarged) yoke for the
normal conducting solution - No purcel filter, but enlarged pole
- Enlarged yoke for lower flux density
- Enlarged coil window
- gt approx. 200kW power loss per magnet
14Investment costs
Costs for 24 dipoles Normal conducting CR-dipole Superferric CR-dipole
Magnets yoke coil,cryostat, etc. 4880k 2000k 4880k 5763k
Cryogenics (feed boxes, transfer lines) 7 share of 7kW cryo plant Conventional cooling - - ?k 1800k 1260k -
Power supply 1250k 180k
Sum 8130k?k 13883k
15Operation costs
Normal conducting CR-dip. Superferric CR-dipole
Losses at 4.5K (magnets, feed boxes, transfer) - 24x19W456Wcryo
El. power losses 24x465kW11160kW 456Wcryox250W/Wcryo114kW
Operation costs for 20a with 6000h/a and 80 operation of CR and 9 c/kWh 96422k (with optimized nc-solution 200kW/magnet gt up to 2x higher investment 41472k) 984k
Normal cond. quadrupole
El. power losses 26x66kW18x58kW 2760kW
Operation costs 23846k
16Superferric dipole in the A1900 FRS at MSU
17Nuclotron dipole at JINR in Dubna