Single Undulator Test and Integration - PowerPoint PPT Presentation

About This Presentation
Title:

Single Undulator Test and Integration

Description:

Single Undulator Test and Integration Geoff Pile Overview of results from the Single Undulator Tests Our First Renderings of the SUT Original Goals of the Single ... – PowerPoint PPT presentation

Number of Views:116
Avg rating:3.0/5.0
Slides: 50
Provided by: pil63
Category:

less

Transcript and Presenter's Notes

Title: Single Undulator Test and Integration


1
Single Undulator Test and Integration
  • Geoff Pile

2
Overview of results from the Single Undulator
Tests
Information taken from various presentations of
An Internal SUT review Thanks to the SUT
construction team.
3
Our First Renderings of the SUT
4
Original Goals of the Single Undulator Test
  • Provide critical input to the S/M system design
    reviews.
  • Help to determine whether the support/mover
    system design is ready for final production.
  • Measurement of girder and rollaway motions
  • Determine precision and reproducibility of
    motions, including start and stop. Check for
    interference
  • Measure vibration damping or (hopefully not)
    amplification.
  • Measure position stability and temperature
    dependence of components and subcomponents.
  • Practice Undulator replacement technique on SUT
    translation stages
  • Enhance the Final Integrated Design for
    production

5
The actual SUT set up in MM1
6
The Test Plan Included
  • Support Mover System Testing
  • Control System Testing
  • Mock Vacuum System Testing
  • Diagnostic Quad System Testing
  • Kinematic Undulator Replacement
  • Alignment Checks/Tests

7
Support/Mover System Testing
8
Support/Mover System Testing
Salient Support/Mover System Physics Requirements
  • Quadrupole Motion Positioning Repeatability 7
    µm
  • Quad. Center Stability after Fiducialization 1
    0 µm
  • Short-Term (1 h) BPM and Quad Stability 2 µm
  • Long-Term (24 h) BPM and Quad Stability 5 µm
  • Horiz. Segment Pos. Repeatability in Roll-Away
    Cycle 10 µm
  • Vert. Segment Pos. Repeatability in Roll-Away
    Cycle 5 µm
  • Quad Transverse Position Change in Roll-Out
    Condition 25 µm
  • Quad Position Reproducibility after Roll-Away
    Cycle 2 µm
  • BPM Transverse Position Change in Roll-Out
    Condition 25 µm
  • BPM Position Reproducibility after Roll-Away
    Cycle 2 µm
  • Note The MM1 Facility Lacks Adequate
    Temperature Control

9
Support Mover System Testing
  • SUT Keyence CCD Laser Displacement Sensor Layout

10
Support/Mover System Testing
Sensor Name Measuring Range Resolution Sensor Measurement Function
XUpstream 5 mm 0.05 µm Horizontal Upstream Beam Center Position BFW Manual Stage
YUpstream 5 mm 0.05 µm Vertical Upstream Beam Center Position BFW Manual Stage
XDownstream 5 mm 0.05 µm Horizontal Downstream Beam Center Position BPM Manual Stage
YDownstream 5 mm 0.05 µm Vertical Downstream Beam Center Position BPM Manual Stage
YMidstream 5 mm 0.05 µm Middle Edge of Girder at Beam Height for System Roll
XQuad 5 mm 0.05 µm Horizontal Position at Beam Height for Quad Manual Stage
YQuad 5 mm 0.05 µm Vertical Position at Beam Height for Quad Manual Stage
XUpstream Translation 40 mm 0.5 µm Upstream Undulator Segment Position for Roll-Away System
XDownstream Translation 40 mm 0.5 µm Downstream Undulator Segment Position for Roll-Away System
YFloor 1 -250 mm/500 mm 2.0 µm Upstream Outboard Vertical Position of Girder Relative to Floor
YFloor 2 -250 mm/500 mm 2.0 µm Downstream Outboard Vertical Position of Girder Relative to Floor
YFloor 3 -250 mm/500 mm 2.0 µm Inboard Middle Edge Vertical Position of Girder Relative to Floor
11
Support/Mover System Testing
XDownstream Translation
XQuad
YQuad
XDownstream
YDownstream
YFloor 2
12
Support/Mover Roll out System Testing
LCLS Undulator Roll out Requirements 8.12
Wire center ? ?40 mm (not in PRD) in ID roll-out
condition.
Girder Upstream
BPM/Quad center ? ?25 mm in ID roll-out condition.
Girder Downstream
Total weight 4060 lbs. ID weight 2140 lbs. ID
motion range 80 mm. Load change max /-350
lbs.
13
Support/Mover Roll out System Testing
Test Results with the Original System
Wire center X16 mm, Y37 mm in ID roll-out
condition.
Girder Upstream
CAM 5
CAM 4
BPM/Quad center X103 mm, Y10 mm in ID roll-out
condition.
Girder Downstream
CAM 2
CAM 3
CAM 1
14
Modified Downstream Wedge Blocks both from 45 to
25.6 and 43
Test Results with the Cam System swapped end to
end with 1 modified wedge block (overcorrected
negative)
Wire center X66 mm, Y22 mm in ID roll-out
condition.
BPM/Quad center X-23 mm, Y-12 mm in ID
roll-out condition.
Fully optimized system meets spec
15
Modified Downstream Outboard Wedge Block from 45
to 25.6/41.9
Readings from the Keyence Sensors During a Full
Cycle of the 80 mm. Roll-Out and Roll-In Cycles
(2 sets of data/round trip)
16
Support/Mover System Testing
Conclusions
  • The Cam-Mover System Tests Resolution and
    Backlash Results are Excellent for all Degrees
    of Motion Freedom and Well Within Specifications
  • With Feedback Added, The Cam-Mover System is
    Able to Achieve Any Move Within the Command
    Space to Within 2 µm with No More Than One
    Iteration
  • The Roll-Away System Backlash and Resolution
    Results are Excellent and Well Within
    Specifications
  • All Motions for Both Motion Systems are
    Extremely Repeatable
  • With the New Gearbox Design Motor Heating
    Effects are Non-Existent
  • Engineering Solutions to Make the System Even
    Better are Underway

17
Control System Testing
18
Control System Testing
  • The electronic rack for the SUT incorporates
    most of the hardware control systems for the
    undulator components.
  • It requires 120 volts and an Ethernet
    connection.
  • The real rack will conform to SLAC rack systems
    earthquake specs

19
Control System Testing
The SUT control system is based on Lab View. Here
is the main operating screen The Epics control
system will be utilized on the Long Term
Tests The engineering operating screens will be
designed and integrated with SLAC (Stein, Xu and
Dalesio)
20
Control System Testing
Wiring on SUT was point to point traditionally
wired. Prototype cableway for control and
monitoring system has been developed. Locates
under Undulator Girder. Final design is being
reviewed now. Vendor-made with standardized
connectors. gt30 matching cables will be
manufactured to interconnect with hardware e.g.
motors, thermocouples, potentiometers, BFW, etc.
etc. 33 cableways needed x 30 cables each
1000 cables. Installation will be easy
commissioning will be even easier due to ISO 9000
build and testing.
21
Control System Testing
Special test equipment was constructed to aid
with control system testing. Keyence Inclinometer
Thermal Vibration
22
Mock Vacuum System Testing
23
Vacuum Chamber Adjustment Mechanism
Compound screws - 5/8-18 screw - 7/16-20
screw
Z-adjustment 5/16-18 screws
X-adjustment 5/16-18 screw
  • Y Vertical Adjustment - Compound screws
  • Total 26 threaded holes
  • 14 screws for vertical adjustment
  • Other 12 threaded holes for lifting / adjustments
  • X-Z Horizontal Adjustments Cap screws

24
Compound Screw Tests
  • Performed the compound screw adjustment tests (2,
    6, 14 screws).
  • Adjustment test showed that it is possible to get
    fine adjustment, but it was cumbersome to align.
    It also showed that the locking nut makes the
    process difficult, but that it is sufficient to
    use. It works in both directions to adjust the
    vertical height of the mockup.
  • A laboratory test is set-up with a single
    compound screw and with the proper selection of
    materials, EP SST and MoS2 lub, also brass. The
    backlash is small enough not to hinder micron
    level adjustments.
  • Finally, we chose 5/8-18 Brass and 7/16-20 SST
    compound screws to prevent galling

Six Compound Screws Set-up (42 long)
Fourteen Compound Screws Full Chamber Mock-up
25
Lifting tests
  • Lifting spreader was designed to help lifting up
    the vacuum chamber assembly and lifting plan was
    documented.
  • Lifting spreader was certified from the ESH
    inspector after QA inspection and static load
    test (500 lb).
  • No hazards found during the chamber installation.



Figure 7. Figure
8. Figure 9.
26
Breakdown of the spacing

between the undulator and the vacuum chamber
27
Mock Vacuum System Testing Vacuum Chamber
alignment
mm
Vertical Adjustment Screws (14)
28
Diagnostic Systems Testing
  • Ersatz Quad, Beam Position Monitor and Beam
    Finder Wire alignment and positioning was
    successful.
  • The Support and translation systems for these
    items have been studied and the designs are
    acceptable. All positioning and roll out specs
    have been met.

29
Assemblies and Cross Sections
  • Assembly

Bellows Flange
BFW Flange Seal
Locating Pins
Beam Tube Spider
Shielding Cut-out
Vacuum Flange
Vacuum Chamber Flange
30
Diagnostic Systems Testing
  • Beam Finder Wire
  • As part of the SUT, vibration tests were run on a
    BFW system mock-up. The mock-up was sufficiently
    stable.
  • As part of the SUT, the mounting system for the
    BFW was tested for positioning accuracy. The
    mount system can locate the Chamber to within /-
    10 µm in X and Y.

31

Kinematic Undulator Replacement
32
SUT Undulator Segment Replacement Testing
Background
  • The Magnetic Axis of each Undulator Segment is
    Fiducialized to a Fixed Horizontal and Vertical
    Dimension using Shim Plates Underneath and on
    the Ends of the Undulator Support Plates in
    order to make all Undulator Segments Identical
    and Interchangeable.
  • When Referenced to the Undulator Alignment Pins
    on the Stage Transition Plates, Undulator
    Segments can be Interchanged Without the need for
    Realignment.
  • The Total Tolerance Budget Mandates that this
    Process Must be Repeatable to within 180 µm rms
    Horizontally and 70 µm rms Vertically. In
    Reality, the Process Needs to be Repeatable to
    Within a Percentage of this Tolerance to Allow
    for Additional Tolerance Stack Up Elsewhere.

Purpose
  • Using only One Undulator Segment, Determine the
    Positioning Repeatability at Both End of the
    Undulator after Removal and Reinstallation.

From Robert Rulands 7/7/05 Presentation
Alignment Considerations
33
SUT Undulator Segment Replacement Testing
34
SUT Undulator Segment Replacement Testing
Lifting/Positioning Fixture
35
SUT Undulator Segment Replacement Testing
August 2006 Testing Method
  • Dual Sets of Four Keyence Sensors were used to
    Measure the X and Y Displacement at Both Ends of
    the Undulators Relative to the Girder. The
    Dummy Undulator and the Actual Undulator had
    their Own Dedicated Set of Keyence Sensors so
    that Zero Positions Could be Maintained when
    Switching Between the 2 Undulators
  • Positions were Zeroed at the Undulator Zero
    Position. The Undulator was then Retracted to
    the 80 mm Position, Unbolted and Removed from the
    Stages using our Lifting and Positioning
    Fixtures.
  • The Weight of the Undulator was Removed from the
    Girder using a Forklift.
  • The Undulator was then Lowered to the Lifting
    Fixtures and Brought back Down onto the Stages.
  • Bolts were Retightened using a Torque Wrench and
    then the Undulator was Returned to the Home
    Zero Position. The Keyence Sensors were Read
    and Recorded at this Time and Compared with the
    Laser Tracker System Results.
  • This Method was Repeated 4 Times for the Dummy
    Undulator and 3 Times for the Actual Undulator.

36
SUT Undulator Segment Replacement Testing
Xupstream
Yupstream
37
SUT Undulator Segment Replacement Testing
38
SUT Undulator Segment Replacement Testing
Kinematic replacement of undulator Conclusions
  • The Process of Replacing an Undulator Segment is
    Quick and Easy Using the Lifting and Positioning
    Fixtures.
  • The Process is Very Accurate and Repeatable.
  • The Worst Case Repeatability for Vertical
    Alignment is Less than 10 Microns.
  • The Worst Case Repeatability for Horizontal
    Alignment is Less than 40 Microns.
  • The Laser Tracker Network Established around the
    SUT Provides Excellent Results that are in Good
    Agreement with the Keyence Sensor Measurements.
  • The Laser Tracker Network will be Used
    Throughout SUT Testing to Provide a Secondary
    Set of Measurements for Comparison to The Keyence
    Sensors and Positioning Potentiometers.

39
Support/Mover System Testing
Survey Alignment Support
  • LEICA LTD 500 Laser Tracker System Used for
    System Alignment
  • Local Reference Network Established with 9 Fixed
    Monuments Distributed Around the SUT at Various
    Elevations
  • Largest Measured Distance was around 3.5 m and
    Thus the Measurement Accuracy was On the Order
    of Tens of Microns
  • Mini-Monuments Used on the Girder, Undulator,
    and Fixed Bases for Alignment of these
    Components. Tracker Also Used to Set Translation
    Stage Alignment Pins
  • Optical Level System Used to Align Vacuum
    Chamber
  • Taylor-Hobson Talyvel 4 Used for System
    Distortion Measurements During the Roll-Away
    Cycle

40
Final Alignment Summary
Support/Mover System Testing
  • Support Stands were set in elevation, pitch and
    roll to 0.10 mm.
  • The Interface Plates fell within 0.05 mm in all
    areas.
  • Final alignment of the girder was achieved to
    within 10 µm in pitch, roll and elevation, yaw
    and x were within 40 µm.
  • 80mm roll out tests were successfully tracked
    with the laser and compared very well against
    Keyence sensor results.

41
So how did we do? - We learned a lot!
  • Support Mover (inc. fixed supports) System
    Testing
  • Initial tests were very successful Most
    of the requirements have been achieved and we
    learned what we had to change to meet or exceed
    the remaining requirements. Final designs will
    incorporate all of the experience we gained and
    changes required to meet these specs.
  • Changes include modifications to the fixed
    supports, girder, translation stages, wedge
    blocks, cam movers and gearboxes.
  • Undulator Roll Out
  • Testing and rapid wedge block development has
    resolved very challenging specs that could have
    been a significant problem.
  • Kinematic Undulator Replacement
  • Initial tests (dummy only) were very successful
    We appeared to be well in spec but had to
    complete the tests with the First Article 1 and
    the dummy undulator. Final numbers are well in
    spec. Making all undulator equal in production
    will be a relatively easy process.
  • Diagnostic System Testing
  • Initial installation, alignment and integration
    of ersatz BPM and BFW look very good.
  • Setting the stages (settability) to a go to
    position is very good.

42
Final Design enhancements
  • Larger clearance holes on the base plate.
  • More anchor points around the base plate.
  • Illustration of possible mounting points. (8)
    total points will be used in the final design.
  • Larger diameter support structure.
  • Standard parts will be investigated for this
    improvement.
  • Larger threaded rods between the base top plate
    and the interface plate.
  • Thinner grout with an improved floor mounting
    method.

43
Design Summary
Earthquake Restraints
Cam Mounting Pads
1 ½ Interface Plate
1 ½ Top Plate
1½ Support Rod
3 Fiber Wool Insulation (Not Shown)
1- 8 Base Leveling / Anchor Bolts
1 ½ Bottom Plate
Support Pads
Expanding Grout (Not Shown)
44
  • Integration

45
Integration
  • Rodd Pope is talking about schedule and assembly
    integration at SLAC. Heres a different look at
    an example of some of our project integration.
  • in?te?grate '?n t??gre?t

verb (used with object)
1 to make up, combine, or complete to produce a whole or a larger unit, as parts do.
2 to bring together or incorporate (parts) into a whole.
We made up the following integration tool and are
currently developing it. It will be web
accessible by Lehman Review.
46
Integration
We all need to ASK for information to integrate
efficiently. This is called the ASK
system. Assembly Sub-assembly Kit
  • Example
  • Select Support mover on this interactive web
    page.
  • Support Mover box opens up main three areas
  • 2. Select Fixed Support

47
Integration
Fixed Support Assembly. wbs 1.04.03.08 B.O.M A.
S.K. S.O.W Installation info
48
Integration
49
Integration
Microsoft Access Links P3 Information PARIS
Procurement info Intralink Free form entry allows
input from QAR CAMs SLAC integration engineers.
Write a Comment
User Comments (0)
About PowerShow.com