Title: Single Undulator Test and Integration
1Single Undulator Test and Integration
2Overview of results from the Single Undulator
Tests
Information taken from various presentations of
An Internal SUT review Thanks to the SUT
construction team.
3Our First Renderings of the SUT
4Original Goals of the Single Undulator Test
- Provide critical input to the S/M system design
reviews. - Help to determine whether the support/mover
system design is ready for final production. - Measurement of girder and rollaway motions
- Determine precision and reproducibility of
motions, including start and stop. Check for
interference - Measure vibration damping or (hopefully not)
amplification. - Measure position stability and temperature
dependence of components and subcomponents. - Practice Undulator replacement technique on SUT
translation stages - Enhance the Final Integrated Design for
production
5The actual SUT set up in MM1
6The Test Plan Included
- Support Mover System Testing
- Control System Testing
- Mock Vacuum System Testing
- Diagnostic Quad System Testing
-
- Kinematic Undulator Replacement
- Alignment Checks/Tests
-
7Support/Mover System Testing
8Support/Mover System Testing
Salient Support/Mover System Physics Requirements
- Quadrupole Motion Positioning Repeatability 7
µm - Quad. Center Stability after Fiducialization 1
0 µm - Short-Term (1 h) BPM and Quad Stability 2 µm
- Long-Term (24 h) BPM and Quad Stability 5 µm
- Horiz. Segment Pos. Repeatability in Roll-Away
Cycle 10 µm - Vert. Segment Pos. Repeatability in Roll-Away
Cycle 5 µm - Quad Transverse Position Change in Roll-Out
Condition 25 µm - Quad Position Reproducibility after Roll-Away
Cycle 2 µm - BPM Transverse Position Change in Roll-Out
Condition 25 µm - BPM Position Reproducibility after Roll-Away
Cycle 2 µm - Note The MM1 Facility Lacks Adequate
Temperature Control
9Support Mover System Testing
- SUT Keyence CCD Laser Displacement Sensor Layout
10Support/Mover System Testing
Sensor Name Measuring Range Resolution Sensor Measurement Function
XUpstream 5 mm 0.05 µm Horizontal Upstream Beam Center Position BFW Manual Stage
YUpstream 5 mm 0.05 µm Vertical Upstream Beam Center Position BFW Manual Stage
XDownstream 5 mm 0.05 µm Horizontal Downstream Beam Center Position BPM Manual Stage
YDownstream 5 mm 0.05 µm Vertical Downstream Beam Center Position BPM Manual Stage
YMidstream 5 mm 0.05 µm Middle Edge of Girder at Beam Height for System Roll
XQuad 5 mm 0.05 µm Horizontal Position at Beam Height for Quad Manual Stage
YQuad 5 mm 0.05 µm Vertical Position at Beam Height for Quad Manual Stage
XUpstream Translation 40 mm 0.5 µm Upstream Undulator Segment Position for Roll-Away System
XDownstream Translation 40 mm 0.5 µm Downstream Undulator Segment Position for Roll-Away System
YFloor 1 -250 mm/500 mm 2.0 µm Upstream Outboard Vertical Position of Girder Relative to Floor
YFloor 2 -250 mm/500 mm 2.0 µm Downstream Outboard Vertical Position of Girder Relative to Floor
YFloor 3 -250 mm/500 mm 2.0 µm Inboard Middle Edge Vertical Position of Girder Relative to Floor
11Support/Mover System Testing
XDownstream Translation
XQuad
YQuad
XDownstream
YDownstream
YFloor 2
12Support/Mover Roll out System Testing
LCLS Undulator Roll out Requirements 8.12
Wire center ? ?40 mm (not in PRD) in ID roll-out
condition.
Girder Upstream
BPM/Quad center ? ?25 mm in ID roll-out condition.
Girder Downstream
Total weight 4060 lbs. ID weight 2140 lbs. ID
motion range 80 mm. Load change max /-350
lbs.
13Support/Mover Roll out System Testing
Test Results with the Original System
Wire center X16 mm, Y37 mm in ID roll-out
condition.
Girder Upstream
CAM 5
CAM 4
BPM/Quad center X103 mm, Y10 mm in ID roll-out
condition.
Girder Downstream
CAM 2
CAM 3
CAM 1
14Modified Downstream Wedge Blocks both from 45 to
25.6 and 43
Test Results with the Cam System swapped end to
end with 1 modified wedge block (overcorrected
negative)
Wire center X66 mm, Y22 mm in ID roll-out
condition.
BPM/Quad center X-23 mm, Y-12 mm in ID
roll-out condition.
Fully optimized system meets spec
15Modified Downstream Outboard Wedge Block from 45
to 25.6/41.9
Readings from the Keyence Sensors During a Full
Cycle of the 80 mm. Roll-Out and Roll-In Cycles
(2 sets of data/round trip)
16Support/Mover System Testing
Conclusions
- The Cam-Mover System Tests Resolution and
Backlash Results are Excellent for all Degrees
of Motion Freedom and Well Within Specifications - With Feedback Added, The Cam-Mover System is
Able to Achieve Any Move Within the Command
Space to Within 2 µm with No More Than One
Iteration - The Roll-Away System Backlash and Resolution
Results are Excellent and Well Within
Specifications - All Motions for Both Motion Systems are
Extremely Repeatable - With the New Gearbox Design Motor Heating
Effects are Non-Existent - Engineering Solutions to Make the System Even
Better are Underway
17Control System Testing
18Control System Testing
- The electronic rack for the SUT incorporates
most of the hardware control systems for the
undulator components. - It requires 120 volts and an Ethernet
connection. - The real rack will conform to SLAC rack systems
earthquake specs
19Control System Testing
The SUT control system is based on Lab View. Here
is the main operating screen The Epics control
system will be utilized on the Long Term
Tests The engineering operating screens will be
designed and integrated with SLAC (Stein, Xu and
Dalesio)
20Control System Testing
Wiring on SUT was point to point traditionally
wired. Prototype cableway for control and
monitoring system has been developed. Locates
under Undulator Girder. Final design is being
reviewed now. Vendor-made with standardized
connectors. gt30 matching cables will be
manufactured to interconnect with hardware e.g.
motors, thermocouples, potentiometers, BFW, etc.
etc. 33 cableways needed x 30 cables each
1000 cables. Installation will be easy
commissioning will be even easier due to ISO 9000
build and testing.
21Control System Testing
Special test equipment was constructed to aid
with control system testing. Keyence Inclinometer
Thermal Vibration
22Mock Vacuum System Testing
23Vacuum Chamber Adjustment Mechanism
Compound screws - 5/8-18 screw - 7/16-20
screw
Z-adjustment 5/16-18 screws
X-adjustment 5/16-18 screw
- Y Vertical Adjustment - Compound screws
- Total 26 threaded holes
- 14 screws for vertical adjustment
- Other 12 threaded holes for lifting / adjustments
- X-Z Horizontal Adjustments Cap screws
24Compound Screw Tests
- Performed the compound screw adjustment tests (2,
6, 14 screws). - Adjustment test showed that it is possible to get
fine adjustment, but it was cumbersome to align.
It also showed that the locking nut makes the
process difficult, but that it is sufficient to
use. It works in both directions to adjust the
vertical height of the mockup. - A laboratory test is set-up with a single
compound screw and with the proper selection of
materials, EP SST and MoS2 lub, also brass. The
backlash is small enough not to hinder micron
level adjustments. - Finally, we chose 5/8-18 Brass and 7/16-20 SST
compound screws to prevent galling
Six Compound Screws Set-up (42 long)
Fourteen Compound Screws Full Chamber Mock-up
25Lifting tests
- Lifting spreader was designed to help lifting up
the vacuum chamber assembly and lifting plan was
documented. - Lifting spreader was certified from the ESH
inspector after QA inspection and static load
test (500 lb). - No hazards found during the chamber installation.
Figure 7. Figure
8. Figure 9.
26Breakdown of the spacing
between the undulator and the vacuum chamber
27 Mock Vacuum System Testing Vacuum Chamber
alignment
mm
Vertical Adjustment Screws (14)
28Diagnostic Systems Testing
- Ersatz Quad, Beam Position Monitor and Beam
Finder Wire alignment and positioning was
successful. -
- The Support and translation systems for these
items have been studied and the designs are
acceptable. All positioning and roll out specs
have been met.
29Assemblies and Cross Sections
Bellows Flange
BFW Flange Seal
Locating Pins
Beam Tube Spider
Shielding Cut-out
Vacuum Flange
Vacuum Chamber Flange
30Diagnostic Systems Testing
- Beam Finder Wire
- As part of the SUT, vibration tests were run on a
BFW system mock-up. The mock-up was sufficiently
stable. - As part of the SUT, the mounting system for the
BFW was tested for positioning accuracy. The
mount system can locate the Chamber to within /-
10 µm in X and Y.
31Kinematic Undulator Replacement
32SUT Undulator Segment Replacement Testing
Background
- The Magnetic Axis of each Undulator Segment is
Fiducialized to a Fixed Horizontal and Vertical
Dimension using Shim Plates Underneath and on
the Ends of the Undulator Support Plates in
order to make all Undulator Segments Identical
and Interchangeable. - When Referenced to the Undulator Alignment Pins
on the Stage Transition Plates, Undulator
Segments can be Interchanged Without the need for
Realignment. - The Total Tolerance Budget Mandates that this
Process Must be Repeatable to within 180 µm rms
Horizontally and 70 µm rms Vertically. In
Reality, the Process Needs to be Repeatable to
Within a Percentage of this Tolerance to Allow
for Additional Tolerance Stack Up Elsewhere.
Purpose
- Using only One Undulator Segment, Determine the
Positioning Repeatability at Both End of the
Undulator after Removal and Reinstallation.
From Robert Rulands 7/7/05 Presentation
Alignment Considerations
33SUT Undulator Segment Replacement Testing
34SUT Undulator Segment Replacement Testing
Lifting/Positioning Fixture
35SUT Undulator Segment Replacement Testing
August 2006 Testing Method
- Dual Sets of Four Keyence Sensors were used to
Measure the X and Y Displacement at Both Ends of
the Undulators Relative to the Girder. The
Dummy Undulator and the Actual Undulator had
their Own Dedicated Set of Keyence Sensors so
that Zero Positions Could be Maintained when
Switching Between the 2 Undulators - Positions were Zeroed at the Undulator Zero
Position. The Undulator was then Retracted to
the 80 mm Position, Unbolted and Removed from the
Stages using our Lifting and Positioning
Fixtures. - The Weight of the Undulator was Removed from the
Girder using a Forklift. - The Undulator was then Lowered to the Lifting
Fixtures and Brought back Down onto the Stages. - Bolts were Retightened using a Torque Wrench and
then the Undulator was Returned to the Home
Zero Position. The Keyence Sensors were Read
and Recorded at this Time and Compared with the
Laser Tracker System Results. - This Method was Repeated 4 Times for the Dummy
Undulator and 3 Times for the Actual Undulator.
36SUT Undulator Segment Replacement Testing
Xupstream
Yupstream
37SUT Undulator Segment Replacement Testing
38SUT Undulator Segment Replacement Testing
Kinematic replacement of undulator Conclusions
- The Process of Replacing an Undulator Segment is
Quick and Easy Using the Lifting and Positioning
Fixtures. - The Process is Very Accurate and Repeatable.
- The Worst Case Repeatability for Vertical
Alignment is Less than 10 Microns. - The Worst Case Repeatability for Horizontal
Alignment is Less than 40 Microns. - The Laser Tracker Network Established around the
SUT Provides Excellent Results that are in Good
Agreement with the Keyence Sensor Measurements. - The Laser Tracker Network will be Used
Throughout SUT Testing to Provide a Secondary
Set of Measurements for Comparison to The Keyence
Sensors and Positioning Potentiometers.
39Support/Mover System Testing
Survey Alignment Support
- LEICA LTD 500 Laser Tracker System Used for
System Alignment - Local Reference Network Established with 9 Fixed
Monuments Distributed Around the SUT at Various
Elevations - Largest Measured Distance was around 3.5 m and
Thus the Measurement Accuracy was On the Order
of Tens of Microns - Mini-Monuments Used on the Girder, Undulator,
and Fixed Bases for Alignment of these
Components. Tracker Also Used to Set Translation
Stage Alignment Pins - Optical Level System Used to Align Vacuum
Chamber - Taylor-Hobson Talyvel 4 Used for System
Distortion Measurements During the Roll-Away
Cycle
40Final Alignment Summary
Support/Mover System Testing
- Support Stands were set in elevation, pitch and
roll to 0.10 mm. - The Interface Plates fell within 0.05 mm in all
areas. - Final alignment of the girder was achieved to
within 10 µm in pitch, roll and elevation, yaw
and x were within 40 µm. - 80mm roll out tests were successfully tracked
with the laser and compared very well against
Keyence sensor results.
41So how did we do? - We learned a lot!
- Support Mover (inc. fixed supports) System
Testing - Initial tests were very successful Most
of the requirements have been achieved and we
learned what we had to change to meet or exceed
the remaining requirements. Final designs will
incorporate all of the experience we gained and
changes required to meet these specs. - Changes include modifications to the fixed
supports, girder, translation stages, wedge
blocks, cam movers and gearboxes. - Undulator Roll Out
- Testing and rapid wedge block development has
resolved very challenging specs that could have
been a significant problem. - Kinematic Undulator Replacement
- Initial tests (dummy only) were very successful
We appeared to be well in spec but had to
complete the tests with the First Article 1 and
the dummy undulator. Final numbers are well in
spec. Making all undulator equal in production
will be a relatively easy process. - Diagnostic System Testing
- Initial installation, alignment and integration
of ersatz BPM and BFW look very good. - Setting the stages (settability) to a go to
position is very good.
42Final Design enhancements
- Larger clearance holes on the base plate.
- More anchor points around the base plate.
- Illustration of possible mounting points. (8)
total points will be used in the final design. - Larger diameter support structure.
- Standard parts will be investigated for this
improvement. - Larger threaded rods between the base top plate
and the interface plate. - Thinner grout with an improved floor mounting
method.
43Design Summary
Earthquake Restraints
Cam Mounting Pads
1 ½ Interface Plate
1 ½ Top Plate
1½ Support Rod
3 Fiber Wool Insulation (Not Shown)
1- 8 Base Leveling / Anchor Bolts
1 ½ Bottom Plate
Support Pads
Expanding Grout (Not Shown)
44 45Integration
- Rodd Pope is talking about schedule and assembly
integration at SLAC. Heres a different look at
an example of some of our project integration. - in?te?grate '?n t??gre?t
verb (used with object)
1 to make up, combine, or complete to produce a whole or a larger unit, as parts do.
2 to bring together or incorporate (parts) into a whole.
We made up the following integration tool and are
currently developing it. It will be web
accessible by Lehman Review.
46Integration
We all need to ASK for information to integrate
efficiently. This is called the ASK
system. Assembly Sub-assembly Kit
- Example
- Select Support mover on this interactive web
page. - Support Mover box opens up main three areas
- 2. Select Fixed Support
47Integration
Fixed Support Assembly. wbs 1.04.03.08 B.O.M A.
S.K. S.O.W Installation info
48Integration
49Integration
Microsoft Access Links P3 Information PARIS
Procurement info Intralink Free form entry allows
input from QAR CAMs SLAC integration engineers.