TRD Integration Status - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

TRD Integration Status

Description:

Cable length was optimized for L0 & L1, and produced by Tom. ... Thanks to people (Raphaelle, Silvia, Anton, Christian, Tom, Chilo... – PowerPoint PPT presentation

Number of Views:42
Avg rating:3.0/5.0
Slides: 15
Provided by: wwwali
Category:
Tags: trd | cable | integration | status | tom

less

Transcript and Presenter's Notes

Title: TRD Integration Status


1
TRD Integration Status
  • K. Oyama
  • Apr. 10, 2006
  • TRD status meeting in GSI

2
KIP Experimental Hall Today
3
Overview of the 1st-SM Layer-0 Test Setup
Gas
E.SW
DCSP.S.
Y
C
C
Y
DCSPD
L0C1004
L0C1002
L0C0015
L0C1001
L0C1003
O2M
S.B.
D
opt.patch
A
C
Readout PC
Cosmic paddles
HV
Trigger TTC
LVP.S.
HVP.S.
  • Super-module cage.
  • 2 power-bus-bars installation.
  • Capacitors at power bus bar ends.
  • (812) x 70 mm2 L.V. wires preparation.
  • 38 ROB L.V. cables production and installation.
  • H.V. patch boxes and 10 H.V. connections.
  • CERES P.S. as DCS P.S..
  • 5 Ethernet lines Cisco Ethernet SW Y.
  • Shuetten Box and TTC connections.
  • Preliminary opt. patch R.O. PC with ACEX.
  • Cosmic paddles and trigger preparation.
  • Gas preparation.

4
ROC Preparations
  • ROB aging and tests. Thanks Ivan, Jorge, Stefan.
  • Capacitors patchworks. Thanks Behrooz.
  • Mounting HV filter boxes were well done. Thanks
    Raphaelle, Silvia, Anton, Christian, Behrooz.
    Technology transfer was done. It is expected that
    ROC production sites can do it.
  • Some problem in/around HV filter box found by
    Rainer (necessary for applying HV before going to
    SM after HV is put).
  • Mounting ROBs were well done. Thanks Raphaelle,
    Silvia, Anton, Christian, Behrooz). Many people
    know how to do.
  • Cable channel preparation. Thanks Clemens.
  • Long HV cables attaching.
  • gateDB is fine! Thanks Tom.
  • Allready prepared ROCs
  • 4 x L0C1
  • 1 x L0C0
  • 4 x L1C1

5
Power-Bus-Bar and ROC Installation
  • Almost no geometrical problem except for around
    drift HV wire.
  • Excellent preparation of the cage by Bernd and
    his team.
  • Power bus bars were attached onto side-panel by
    double sided tape spacer (with same thickness
    as cooling pipe). Thanks Christian, Tom.
  • Lying chambers takes only few hours. Gas
    interconnection is so easy!

6
ROB L.V. Connections, etc.
  • Cable length was optimized for L0 L1, and
    produced by Tom.
  • All cables are screwed onto power bus bar using
    cable shoes.
  • 304 screws connections were finished. Thanks to
    people (Raphaelle, Silvia, Anton, Christian, Tom,
    Chilo and more) although difficult positions!
  • Later, power bus bar side panel LV cables are
    pre-assembled.
  • H.V. Cabling space is fine.

7
A and C Sides Preparations
  • 4 x 1000 uF capacitors are put on each power bus
    bar end. Will be more.
  • TTC Fibers and Shuetten Box were installed.
    Thanks David.
  • Davids HV patch panels (driftleft and
    anoderight) were placed in preliminary positions
    and 5 chambers are connected.
  • Gas connections were done. Thanks Chilo and
    Clemens.
  • DCS Power cables and Ethernet were placed. Thanks
    Christian.

8
Powering up and Configuring 1st-SM Layer-0
  • DCS Power OK.
  • LV on power bus bar OK.
  • H.V. OK. (Clemens saw problem in one of the
    chambers).
  • Ethernet there was problem with certain switch
    but not with Cisco switch or 24 port NETGEAR
    switch. Shielding and DCS groundings do not help
    for bad switch (unshielded is bit better).
  • ROCs were connected to bus bars one by one.
  • TRAPs successfully configured!!
  • Stand-by (wait_pre) power consumption
  • A3.3 50 A
  • D3.3 20 A
  • A1.8 70 A
  • D1.8 60 A
  • Significant voltage drop resulted over-voltage
  • trip at P.S. due to thin LV wire (16 mm2).
  • Solved by 70 mm2 wires.
  • Thanks for Marc, Tom and .

9
Optical Fibers Installations
  • It is just easy to run on ROCs (over cooling
    pipes).
  • Installation might be difficult and risky when
    big cooling pipes are there.
  • Replacing of ROCs anyway almost impossible
    (possible one by one from side, due to gas
    interconnection etc).
  • Mixing with and damaged by heavy cables (power,
    HV) can be avoided.

10
Trigger Preparations
  • Scintillation paddles for cosmic trigger were
    prepared by Marc and Min-Jung. Super-module can
    be scanned by cosmic trigger.
  • TTC trigger propagation test by Marc and
    Min-Jung
  • TTCex ? Shuetten Box ? TTCrx ? TRAPs
  • were tested and all event counters were ok.
  • Pretrigger system must be tested
  • for triggering TRAPs with pretrigger,
  • L0, and L1. Overall jitter measurement
  • is necessary.

11
Missing Items for 1st-SM Completion till P.C. in
May
  • 20 more prepared ROCs for L2 L5.
  • LV distribution scheme on the front of SMEC must
    be fixed before Layer-1
  • Wiener LV PS (coming soon).
  • Power bus bars (ordered by Christian and some
    more already arrived).
  • Power bus bar safety covers capacitors LEDs
    modules.
  • Cooling pipes on ROBs (almost done by Ana).
  • Cooling pipes below power bus bars, and on the
    SMEC.
  • DCS power distribution box (design have done by
    Dirk and Mr. Rausch).
  • Final Ethernet cables (exotic cable is expensive.
    normal CAT5 fits).
  • JTAG cables (metric PVC cable was rejected. 2.54
    mm flat solution is taken).
  • ORI fiber patch panel ?
  • ORIs (being produced).
  • GTU
  • Pre-Trigger System (at least the Control Box).
  • Some more in gas system?
  • HV Distribution Box (Greek Box).
  • LV diagnose sensor (voltage divider).
  • Temperature sensor (well known).

12
Noise L0C1003 2006/Mar./01 stand-alone
13
Noise L0C1003 2006/Apr. 07 as in 1st-SM L0S4
14
Conclusions
  • ROC preparations are on going without big problem
    and technology was transferred.
  • 1st super-module Layer-0 test started.
  • No problem to power up 5 chambers and configure.
  • Noise level 1.17 LSB (1230 e) outside SM ? 1.09
    LSB (1150 e) inside..
  • But bad channels were introduced by moving into
    super-Module.
  • Preparation for full chain test including
    control system and DAQ is on going right now.
  • Still there is significant number of missing
    components.
Write a Comment
User Comments (0)
About PowerShow.com