Title: MuCool Activities
1MuCool Activities
- Muon Cooling RD
- ISS Meeting at KEK
- January 24, 2006
- A. Bross
2MuCool
- Mission
- Design, prototype and test all cooling channel
components - 201 MHz RF Cavities, LH2 absorbers, SC solenoids
- Perform high beam-power engineering test of
cooling section components - Support MICE (cooling demonstration experiment)
- Consists of 9 institutions from the US and Japan
RF Development ANL Fermilab IIT JLAB LBNL Univ.
of Mississippi
Absorber RD Fermilab IIT KEK NIU U.
Mississippi U. Osaka
Solenoids LBNL
3MuCool
- RD Focus of MuCool
- Component testing Fermilab
- High Power
- Both RF and Beam
4MuCool Test Area
- Facility to test all components of cooling
channel (not a test of ionization cooling) - At high beam power
- Designed to accommodate full Linac Beam
- 1.6 X 1013 p/pulse _at_15 Hz
- 2.4 X 1014 p/s
- 600 W into 35 cm LH2 absorber _at_ 400 MeV
- RF power from Linac (201 and 805 MHz test stands)
- Waveguides pipe power to MTA
5MTA Hall
6MTA
- The MTA is the focus of our Activities
- RF testing (805 and 201 MHz)
- Installation/commissioning of Cryo-Infrastructure
- High pressure H2 gas-filled RF
- LH2 Absorber tests
- High Intensity Beam
- Will start with low intensity
7MTA Cryo-Infrastruture
Compressor Installation and piping are complete
Heat exchanger
Towards Experimental Hall
Needed for Magnet Operations and LH2 Absorber
Tests
- Compressor Room
- Two 400 HP 2-stage oil injected screw compressors
- Refrigerator Room
- Tevatron satellite refrigerator to be operated
on 5 K mode and 14 K mode (3 DE, 3 WE) - Helium and nitrogen Dewar
8MTA High Intensity Beam
- 400 MeV beamline for the MTA has been designed
- Under Craig Moore
- External Beams Department
- Developed Engineering Design
- Cost
- Schedule
- Safety Analysis
- Linac Area and Beamline
- Shielding Assessment for MTA
- The current beam line design allows for Linac
diagnostic - High-Quality emittance measurement
- Our goal is to bring Low Intensity to the MTA as
soon as possible
MTA
9MTA Near Term Test Program
- 805 MHz Pill Box preparation complete 11/30/05
- Low power testing and conditioning begins
- Currently have reached approximately 1MV/m
- 805 MHz high-power testing begins 1/1/06
- TiN coated curved Be windows tests
- Currently at 18 MV/m (1 MW power)
- Various B field configurations
- 201 MHz cavity ready for testing 2/1/06
- LH2 Absorber test 3/06
- Second phase of testing with KEK convective
- absorber
- This is dependent on new safety review
10RF Cavity R and D
11Fundamental Focus Of RF RD
- Study the limits on Accelerating Gradient in NCRF
cavities in magnetic field - However
- We believe that the behavior of RF systems in
general can be accurately described (predicted)
by - Tensile strength of the material(s) used in the
cavity fabrication (T) - Local surface field enhancements (beq)
- Esurf Ö(2T/eo)/beq
- This applies to all accelerating structures
- Follows universal curve
12Phase I of RF Cavity Closed Cell Magnetic Field
Studies (805 MHz)
- Data seem to follow universal curve
- Max stable gradient degrades quickly with B field
- Sparking limits max gradient
- Copper surfaces the problem
Gradient in MV/m
Peak Magnetic Field in T at the Window
13Phase II of 805 MHz studies
- Study breakdown and dark current characteristics
as function of gradient and applied B field in
Pillbox cavity - Curved Be window Test
- TiN coated
- System now conditioning
- _at_18MV/m (1 MW)
- Study
- Max stable gradient as function of B field
- Dark current and breakdown
- Cavity stability as funciton of power
- Button test
- Evaluate various materials and coatings
- Allows for quick turn around no conditioning
needed
14RF RD 201 MHz Cavity Design
- The 201 MHz Cavity is now in the MTA ready for
test - Final hook-up should be starting this week
15201 MHz Cavity Hookup
16Local Electrode Atom Probe (LEAP) Tomography
- Atom probe experiments in collaboration with
Northwestern U. - Prof. David Seidman Jason Sebastian
(Northwestern), - P. Bauer, C. Boffo (FNAL), J. Norem (ANL)
- High Gradient material studies relevant to both
NCRF and SCRF ILC, Neutrino Factory, Muon
Collider, CLIC. - Surface microstructure
- Surface contamination (oxides etc.)
- Breakdown and Dark Currents
- Data from these tests expand our knowledge of
breakdown phenomena, will allow us to develop a
detailed model of the physics of breakdown in
cavities, and can provide a guide for
materials/fabrication procedures for RF cavities
Atom Probe Data from Nb sample _at_ 10 GV/m
Modeling Fracture
17Absorber R and D
18Absorber Design Issues
- 2D Transverse Cooling
- and
- Figure of merit MLRdEm/ds
- M2 (4D cooling) for different absorbers
H2 is clearly Best - Neglecting Engineering
Issues Windows, Safety
19Absorber Design Issues
- Design Criteria
- High Power Handling
- Study II few 100 W to 1 KW with upgraded
(4MW) proton driver - 10 KW in ring cooler
- Must remove heat
- Safety issues regarding use of LH2 (or gaseous
H2) - Window design paramount
- H2 containment
- Proximity to RF adds constraints (ignition
source) - Two Design Approaches
- Convective Cooling
- Shown to the right
- Forced flow
- High power handling
H2 implies engineering complexity
20Forced-Flow Absorber
- Heat removed with external heat exchanger
- LH2 pumped from absorber to heat exchanger
- Nozzles in flow path establish turbulent flow
- Simulation via 2D and 3D FEA
- Preliminary engineering design for implementation
in the MTA - Have taken possession of cooling loop heat
exchanger from SAMPLE experiment _at_ Bates/MIT - Prototype Absorber manifold has been fabricated
21MuCool Plans for the Coming Year
- After a long pause due to the loss of our 805 MHz
RF test facility in Lab G at Fermilab, we are
starting up again - 805 MHz RF studies
- Be Window tests
- Materials tests
- Surface treatment
- Use information from LEAP studies
- Start 201 MHz RF test program
- 805 MHz testing likely to continue interleaved
with 201 testing - Second round of tests with KEK convective
absorber - Complete MTA cryo infrastructure installation and
commission system - Start installation of 400 MeV beam line from
Linac - Have the capability for low-intensity experiments
22The MuCool Test Area Potential
- The MuCooL Test Area is becoming a tremendous
resource - It has the potential to provide a Unique
(World-wide) RD facility - Multi-frequency RF test capability (NC and SC)
- Hydrogen Safety
- Absorbers
- Gas-filled RF cavities
- Cryo-infrastructure (LN, high capacity LHe)
- High-Intensity beam