Title: The Alpha Magnetic Spectrometer
1Magnet Test Rig
In April we reported that the magnet had been
suspended inside the MATR
2 and that hydraulic, electronic, and
superconducting connections were being made.
3Fixing the instrumentation wiring took longer
than anticipated
4 although we had additional help from colleagues
from Beijing.
5Extensometers were mounted in the bore of the
magnet
6 to measure structural deformations.
7The magnet test rig (MATR) was completed by
- Finishing the inner vacuum chamber (IVC)
- Finishing the 80 K radiation shield
- Finishing the 5 K radiation shield
- Finishing the outer vacuum case (OVC).
8Operation of the MATR.
9Cool down to 100 K.
10Cool down to 20 K.
11Cool down to 4.2 K.
12Operation at 1.8 K.
13Details of the IVC.
14External leak test showed the IVC was leak
tight. But on assembly, the IVC was leaking to
the OVC. The system therefore had to be
disassembled to try to find the leak.
15Internal leak test on the IVC revealed a small
leak on the flange. This was improved by
overloading the bolts
16 then the cryostat was reassembled.
17Cool down started on 18 June when the liquid
nitrogen tank was filled.
18Initial cool down by radiation from the 80 K
shield only.
19Cool down to 100 K using the liquid nitrogen heat
exchanger (MATR sensors).
20Cool down to 100 K using the liquid nitrogen heat
exchanger (magnet sensors).
21Cool down of the IVC to 20 K by direct injection
of liquid helium.
22Cool down of the magnet to 4.2 K by filling the
liquid helium vessel.
23Persistent switch test.
24Cool down of the magnet to 1.8 K by pumping on
the liquid helium vessel.
25Dipole quench heater test pulse (zero current).
26Charging to 100 A (persistent switch).
27Charging to 100 A (magnet temperatures).
28Deliberate quench from 100 A.
29Re-cool after the 100 A quench.
30Charging to 230 A (persistent switch).
31Charging to 230 A (stray field measurement).
32Charging to 230 A (extensometer measurement).
33Deliberate quench from 230 A.
34Deliberate quench from 230 A.
35Deliberate quench from 230 A (helium level).
36After the quench from 230 A, a number of the
voltage taps on the magnet were open circuit.
Without these taps the quench detector is
inoperable, so it is not possible to charge the
magnet to high currents without risk of damage
until the high voltage wiring is repaired. To
check that the magnet was NOT damaged, a further
charge to 50 A was carried out.
37Re-cool to 4.2 K with liquid helium.
38Charge to 50 A at 4.2 K. No change in the magnet
behaviour.
39Warming up to room temperature to repair the
high-voltage wiring.
40Summary (1) The helium tank has been cleaned to
the level necessary for flight. All the
components required to continue with the leak
testing have been installed.
41Summary (2) The procedures for covering the
helium tank with Cryocoat have been fully
developed. The Cryocoat material is in stock at
Culham.
42Summary (3) The magnet has been tested to 50 of
its nominal field, and set persistent (at a lower
current). Repairs are required to the high
voltage wiring in the test rig, then testing at
higher fields will continue.