Title: The Alpha Magnetic Spectrometer
1(No Transcript)
2- Magnet status S Harrison (30 min)
- Helium vessel at HBE H Bieri (15 min)
- Status of CGSE Y Shi, Zhang, A Grechko (30 min)
- CAB Status H Cuesta (10 min)
3- AMS Superconducting Magnet
- progress over the last 3 months
- April 2007
- Steve HarrisonScientific Magnetics
4- Magnet
- Helium vessel
- Magnet test facility
5Magnet
In January the magnet was mechanically complete,
and work had just started on the inter-coil
links, the cryogenic plumbing, and the heat
shunts.
6Dipole heat shunt
Racetrack heat shunt
Cool down loop
Conductor stabiliser
Superfluid cooling loop
Steel
Cool down loop
Copper
7Inter-coil conductors had been made from
ultra-high purity aluminium, copper-plated for
soldering.
8Coil ends
Unsupported length (max 30 mm)
Trial fit-up was under way.
9The geometry of the flight cooling loops is not
suitable for use in the test cryostat, so
simplified loops are required.
10Both cooling loops had been mechanically attached
to the magnet, but not yet connected to the heat
shunts.
11The magnet joints have now been soldered together
and insulated with Kapton
12 and protected with a PTFE spiral overwrap.
13Instrumentation and quench heater wiring has been
completed
14 with a final set of quench heaters installed on
the outer coil formers.
15Mounting points on the coils for extensometer
attachment.
16For soldering on the heat shunts
17 the magnet had to be rotated
18 to allow the soldering to be carried out
horizontally.
19Helium Vessel
In January, the helium vessel lower half had been
received from HBE and was being worked on at
Culham.
20One of the feedthroughs had a small leak, and had
been cut out for repair.
21A new weld set-up was designed and trialled
22 and a replacement feedthrough was welded into
the tank by the SCL welder at Culham.
23The new weld was successfully qualified, X-ray
tested
24 and leak tested
25 allowing the remaining components to be mounted
inside the vessel.
26While the vessel was at Culham, a trial fit was
carried out to check that the magnet will fit in
the bore.
27(No Transcript)
28(No Transcript)
29There is not a great deal of room to spare.
30The profile of the weld between the vessel
central ring and cylinder was measured.
31Instrumentation inside the vessel was thoroughly
checked.
32Finally the vessel half was packed in a clean
room bag for shipping back to HBE.
33The tank left Culham in the rain.
34The completed tank was returned from HBE on 3
April. The truck penetrated one of the site
ducts.
35The tank itself was never at risk
36 although it had to be recovered by mobile crane.
37The vessel box was eventually transferred into
the SCL workshop and turned over.
38(No Transcript)
39(No Transcript)
40(No Transcript)
41The vessel was lifted out
42 and carried across the workshop
43 to the clean room for basic cleaning.
44(No Transcript)
45Next we have to check that the vessel will fit in
the 1.8 K leak test system.
46Liquid nitrogen vessel fits in the bore of the
helium vessel.
47The helium vessel was lifted out of the clean
room and placed over a hole in the floor
48 allowing the nitrogen vessel to be lowered in.
49There was a small discrepancy between the leak
test rig and the helium vessel, so minor
modifications have been made to the test rig.
50Now the vessel will be mounted in this frame for
detailed cleaning before assembly into the leak
test facility.
51Magnet Test Rig
Progress on the magnet test rig between October
2006 and January 2007 was limited because work on
the STA was given priority.
52The vacuum vessels and radiation shields were
nested together.
53The upper section containing the cryogenic
vessels was mounted.
54The dished ends were mounted on the inner vacuum
case (IVC) for leak testing.
55The magnet was turned axis horizontal for
mounting in the IVC.
56The magnet was picked up on a fork lift
57 and carefully inserted in the test rig.
58The magnet suspended from the test rig supports.
59Mechanical mounting of the magnet is complete.
60Connections for superconductors, persistent
switch, instrumentation, and superfluid helium
are required.
61Here most of the connections are complete.
62Summary Rapid progress has been made with
preparations for the magnet test the test itself
is expected to start in May. Good progress has
also been made with the helium tank, and final
preparations are under way for the 1.8 K leak
test.