NEH Safety Systems - PowerPoint PPT Presentation

1 / 24
About This Presentation
Title:

NEH Safety Systems

Description:

... is through TCP/IP to buffer' Allen-Bradley PLC, then via DeviceNet (serial data communication) ... Hoover, Luc Lessard, Paul Miller, Robert Mueller, Mike ... – PowerPoint PPT presentation

Number of Views:41
Avg rating:3.0/5.0
Slides: 25
Provided by: wwwssrlSl
Category:
Tags: neh | allen | paul | safety | systems

less

Transcript and Presenter's Notes

Title: NEH Safety Systems


1
NEH Safety Systems
  • Enzo Carrone
  • June 30th , 2009

2
PPS and BCS Status
  • Both systems are currently ready for safe
    operation to the FEE
  • PPS successfully certified (IAT) on June 24-26
  • BCS components certified on June 26.
  • Hutch systems
  • HPS will be ready by the end of July.

3
Safety Systems Section
  • PPS and BCS Systems combined into a single
    Section.
  • Full-time QC Group Leader (M. Saleski).
  • Manages Review Process.
  • Oversees Engineering Change Order Process.
  • Full-time Documentation Manager (S. Starner).
  • Documentation system compliant to DOE Order
    414.1C and ISO 9001-2000.

4
(No Transcript)
5
Safety Systems Section Documentation Structure
6
(No Transcript)
7
(No Transcript)
8
Safety Systems QA
  • Subject to a new Engineering Change Order (ECO)
    process
  • Better tracking of requirements, specifications,
    reviews (peer and formal), and system
    documentation.
  • New project QA approach
  • Bench and pre-IAT field test of system software
  • Acceptance tests performed for complex SLAC-built
    assemblies (such at stoppers)
  • Cold and energized checkout of installed hardware
  • Und Complex lessons learned with subcontractors
  • Formal IAT reviews with stakeholders
  • Overall, better management of schedule
  • Indirectly affects quality

9
Documentation Control
  • A single on line repository is available for all
    released documents.
  • Formal Documentation Control is in place.
  • Measures taken to regulate the Preparation,
    Change, Withdrawal, Review, Approval, Release,
    Distribution, Access, Availability, Storage,
    Disposal of documents.
  • Document management Plan, Document Change Control
    Procedure, design Review Plan, Drawing Management
    Procedure, Engineering Change Order Procedure.

10
Configuration Control Elements
  • Prevention of Unintended Change
  • Physical Security of System
  • Labeling
  • Training
  • Control of Intended Change
  • Work Planning (adequate review of design)
  • Work Authorization (RSWCF)
  • Verification of Work (RSWCF)
  • Periodic Confirmation of System Integrity
  • Routine testing and inspections

11
Configuration Management Documentation
  • Document Management Plan
  • Document Change Control Procedure
  • Document Change Order
  • Design Review Plan
  • Software Configuration Management
  • Engineering Change Order Procedure
  • Engineering Change Order
  • Drawing Management Procedure

12
Software Configuration Management Support
  • Software versions are checked during annual
    certification.
  • Written procedures exist for extracting PPS code
    from CVS and for uploading it to PLCs.
  • A documented training program tracks personnel
    PLC qualifications in the Section.

13
Software Configuration Management Procedure
  • PPS Software is stored in a dedicated PPS
    repository.
  • Released software always has N.0.0 version tag.
  • Documented software bench testing is performed
    prior to deployment.

14
Software Configuration Control Issues
  • Program Security
  • All communication to the safety-critical PLCs is
    through TCP/IP to buffer Allen-Bradley PLC,
    then via DeviceNet (serial data communication).
  • Safety-critical program smart card cannot be
    written to while in the PLC
  • Communication from the safety-critical PLCs is
    through DeviceNet to buffer Allen-Bradley PLC
    and output to control system via TCP/IP
  • Network Access Security
  • Hardwire Enable from MCC required
  • Only specific IP addresses are allowed to issue
    PPS commands
  • Physical Access Security
  • PLCs and DeviceNet are inside locked racks.

15
Software Version Management
  • Version Management
  • Software versions are checked during annual
    certification
  • Written procedures Exist for extracting PPS code
    from CVS and uploading it to PLCs
  • A documented training program tracks personnel
    PLC qualifications in the Section

16
Implementation, Operations, and Maintenance
17
Proposed PLC PPS Dev and Rev
18
Established SSS ECO
  • Emphasis on review and development documentation
  • Enables a project management approach
  • Collects development and review docs for
    auditability.

19
FEE/NEH PPS Checkouts
  • Cold Checkout
  • Verifies Hardware and Cable Plant is installed
    and wired correctly
  • Verifies No Ground Shorts in the Cable Plant
  • EEIP Hardware and Racks
  • Hot Checkout
  • Verifies Functionality of Hardware, Devices, and
    PLCs
  • Hi-Pot Cable Plant

20
Review Status
  • Final Design Review 2 (April 22, 2009)
  • Initial Acceptance Test Review (internal and
    external)
  • Starting this week.

21
PPS Review Status for FEE NEH
  • Major Review to Date
  • LCLS SCR May 31st 2007 Bong, Stefan, Horton,
    Hastings
  • LCLS PDR Feb 29th 2008 Lessard, Tompkins,
    Schmerge, Anthony
  • LCLS FDR Oct 22nd 2008 Anthony, Mueller(LBNL),
    Lessard
  • RSC Oct 31st 2008
  • LCLS FDR2 Apr 22nd 2009 Perry Anthony, Zoe Van
    Hoover, Luc Lessard, Paul Miller, Robert Mueller,
    Mike Woods

22
PPS FEE Schedule
23
FEE/NEH Schedule
24
Conclusions
  • PPS/BCS has a Quality Assurance model in place
  • LCLS management is aware of the Safety Systems
    process and supports it throughout the project
    lifecycle (from conception to certification)
  • LCLS, Operations, Radiation Physics are heavily
    involved in all review phases from early on (from
    requirements/specifications to user manual).
Write a Comment
User Comments (0)
About PowerShow.com