Title: Presentazione di PowerPoint
1- General meeting LAGUNA
- LAGUNA Fréjus site
- Geotechnical feasability
- (Rewiew of WP2 Munich January 26th-27th, 2009)
- March 30th.- April 2nd 2009, Wroclaw
2CURRENT SITUATION GENERAL PLAN
LSM Underground Laboratory Modane
Road tunnel
Railway tunnel
Longitudinal section
gt1500 m rock overburden
6,2 km
6,6 km
12.8 km
3Geotechnical parameters of rock mass
- Unit weight 27 kN/m3
- Elastic modulus 15 GPa
- Poissons ratio 0.2
- Friction angle 35/40 (lower/mean value)
- Peak cohesion 3000 kPa
- Residual cohesion 2000 kPa (short term)
500-750 kPa (medium term) 200-300
kPa (long term) - Plastic strain 0.5 (for reach residual
cohesion) - Dilation angle 3
4Main characteristics of calc-schists
- Time-dependent behaviour of rock mass
(displacements) - Tendency to wedge instability on roof
- Anisotropy of rock mass properties (effect of
schistosity) - Reduction of rock mass strength after failure
- No water circulation in the rock mass (OK for
cavern stability - and thermal losses during reservoir operation)
5Cavern design
LENA 221'000 m3
GLACIER 320'000 m3
MEMPHYS 558'000 m3
9 m
17 m
21.9
41.9
19 m
47.5
110 m
70 m
D76 m
D67 m
25 m
D35 m
6Memphys 3D model (FLAC)
7Memphys Displacements Long term
8Memphys Failure zone Long term
9Memphys Analysis of wedge stability
10Large excavations at Frejus - Conclusions
- The construction of the large excavations for
the 3 detector types of Laguna is feasible at
Frejus site. - For Glacier it is possible to built a unique
large tank. The division into - 2 smaller tanks can reduce the total
construction costs of the caverns. - For Lena it is not necessary to have curved
walls - The final lining should be placed at least 2-3
months after the excavation - in order to reduce the rock pressure in the
long term (excavation from - top to bottom, construction of final lining
from bottom to top).
11Interaction between tank and rock mass
- The stability of the rock mass during excavation
is ensured by anchors and reinforced shotcrete - The definitive cavern is sustained by a concrete
lining. - Glacier needs a inner, independent tank.
- The rock loads are supported by the concrete
lining and will not be - transferred on the steel tank.
- The water from the rock mass can cause an
external load on the - imperious tank (even if apparently the rock
appears dry). To avoid this - type of load, it is necessary to design an
external drainage system. - The earthquake is not a problem for the steel
tank, if there is not an - active fault crossing the cavern (atypical
situation).
12Location LAGUNA
Safety tunnel
Road tunnel
LAGUNA
Railway tunnel
13LAYOUT (top view)
Access Tunnel
Control room, offices, storage, power
Safety Tunnel
Electronics
Air and water purification
Electronics
Road Tunnel
Electronics
14LAYOUT (side view)
Air and water purification
Road Tunnel
Electronics
Electronics
Control room, offices, storage, power
Access Tunnel
15LAYOUT
Access Tunnel
Safety Tunnel
Electronics
Air and water purification
Storage
Control room
Offices
Power
Electronics
Cables, piping etc
Electronics