1REHRA PROJECT STATUS, OUTLOOK AND REMARKS
2 PROJECTs AIM
- Better understanding, monitoring and controlling
environmental pollution and public health risks
posed by industrial activities in the Fergana
Valley. - Development of respective national and regional
monitoring strategies, plans, networks as well as
the institutional strengthening of the regulatory
bodies and their supporting scientific background
institutions.
3FOUR SITES SELECTED
ENVSEC Initiative - REHRA Project in Central Asia
4 PROJECTs OBJECTIVES/STEPS
- Rapid risk assessment and ranking of environment
and health mutual trans-boundary risks originated
by the selected industrial sites, with
prioritisation of risks related to individual
sites. - Definition of preventive and mitigation measures
necessary reduce the identified risks, including
recommendations for emergency situations
management.
5 PROJECTs OBJECTIVES/STEPS
- To promote the public participation on the risk
management. - To support the institutional strengthening of the
national Bodies competent in monitoring and
management of industrial risks. - To provide scientific support to the competent
Institutions.
6- THE APPROACH
- Transfer and share of experiences and
organization (not only external expertise) - Work performed by trained CIEs, with assistance
of ICARO - Orientation toward the problem-solving, since
the very beginning
7Pilot project
Driving lines
PILOT TO SOLUTION APPROACH
Feasibility, project, funds
Risks lowering interventions
8MILESTONES
- April 2005 Training seminar in Cortona and
designation of CIEs - May-June First mission in Uzbekistan,
contracting Osh Unit - June-July Starting info/data organization
collection - August Training informatic seminar for Osh Unit
- September Transfer of informatic tools, starting
in Kyr/Taj - October November Starting of investigations
supplementary campaign in Kir and Taj Starting
assessment process in Kyr - December 2005 January 2006 Restarting and
rerouting the Project in Uzbekistan - January 2006 Completion of investigation
supplementary campaing in Kyrkyzstan
9(No Transcript)
10STATUS
- General info/data framework acquired
- Drilling and sampling in the pond completed.
- Chemical analysis of the mud, nearby river waters
and wells performed - Air sampling and analysis in programme
HAIDARKEN ANTIMONY FACTORY WASTES POND
- Maps elaboration Topographic, geologic and
hydrogeologic - Assessment to be completed within March 2006
- Reporting to be completed within April 2006
11STATUS
- General info/data framework acquired
- Drilling and sampling in the tailing ponds
completed. - Chemical analysis of the muds, nearby water wells
in progress - Air sampling and analysis in programme
KADAMJAJ ANTIMONY FACTORY WASTES POND
- Maps elaboration Topographic, geologic and
hydrogeologic - Assessment to be completed within March 2006
- Reporting to be completed within April 2006
12STATUS
- General info/data framework acquired
- Drilling and sampling in the dump in progress.
- Chemical analysis of the dump samples and nearby
water wells in programme - Air sampling and analysis in programme
KANIDABAM PESTICIDES DUMP
- Maps elaboration Topographic available, geologic
and hydrogeologic in programme - Assessment to be completed within April 2006
- Reporting to be completed within April-May 2006
13STATUS
- General info/data framework to be restarted
- CIEs organization and cooperation framework to be
established - No investigations supplementary campaign
programmed (Industrial accident risk assessment) - Informatic tools to be delivered
- Maps elaboration Topographic, geologic and
hydrogeologic in programme
FERGANA OIL REFINERY
- Assessment to be completed within May 2006
- Reporting to be completed within June 2006
14OUTLOOK
PROJECT AND FEASIBILITY STUDY FOR RECLAMATION AND
PUT-IN-SAFETY OF THE DUMP.
KANIDABAM PESTICIDES DUMP
Proposal has been already presented to possible
donors, since the Bratislava meeting (Under POP
Convention or other forms). The Project shall be
shared and jointly led with local experts and
structures and shall foresee the utilization of
the national resources
15OUTLOOK
FEASIBILITY STUDY FOR RECLAMATION AND
PUT-IN-SAFETY OF THE POND.
HAIDARKEN WASTES POND
Proposal has been already presented to possible
donors, since the Bratislava meeting (Under POP
Convention or other forms). The Project shall be
shared and jointly led with local experts and
structures and shall foresee the utilization of
the national resources
16REMARKS
ENVIRONMENTAL MONITORING (?) ENVIRONMENTAL AND
TERRITORY BASIC DATA/INFO PUBLIC AWARENESS AND
PARTICIPATION PROACTIVE ATTITUDE FOR PROTECTING
THE ENVIRONMENT