Presentazione di PowerPoint - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

Presentazione di PowerPoint

Description:

Development of respective national ... Project in Central Asia Kyrgyzstan Uzbekistan Tajikistan FOUR SITES SELECTED Rapid risk assessment and ranking of environment ... – PowerPoint PPT presentation

Number of Views:78
Avg rating:3.0/5.0
Slides: 17
Provided by: Bruno225
Category:

less

Transcript and Presenter's Notes

Title: Presentazione di PowerPoint


1
REHRA PROJECT STATUS, OUTLOOK AND REMARKS
2

PROJECTs AIM
  • Better understanding, monitoring and controlling
    environmental pollution and public health risks
    posed by industrial activities in the Fergana
    Valley.
  • Development of respective national and regional
    monitoring strategies, plans, networks as well as
    the institutional strengthening of the regulatory
    bodies and their supporting scientific background
    institutions.

3
FOUR SITES SELECTED
ENVSEC Initiative - REHRA Project in Central Asia
4

PROJECTs OBJECTIVES/STEPS
  •  Rapid risk assessment and ranking of environment
    and health mutual trans-boundary risks originated
    by the selected industrial sites, with
    prioritisation of risks related to individual
    sites.
  • Definition of preventive and mitigation measures
    necessary reduce the identified risks, including
    recommendations for emergency situations
    management.

5

PROJECTs OBJECTIVES/STEPS
  • To promote the public participation on the risk
    management.
  • To support the institutional strengthening of the
    national Bodies competent in monitoring and
    management of industrial risks.
  • To provide scientific support to the competent
    Institutions.

6
  • THE APPROACH
  • Transfer and share of experiences and
    organization (not only external expertise)
  • Work performed by trained CIEs, with assistance
    of ICARO
  • Orientation toward the problem-solving, since
    the very beginning

7
Pilot project
Driving lines
PILOT TO SOLUTION APPROACH
Feasibility, project, funds
Risks lowering interventions
8
MILESTONES
  • April 2005 Training seminar in Cortona and
    designation of CIEs
  • May-June First mission in Uzbekistan,
    contracting Osh Unit
  • June-July Starting info/data organization
    collection
  • August Training informatic seminar for Osh Unit
  • September Transfer of informatic tools, starting
    in Kyr/Taj
  • October November Starting of investigations
    supplementary campaign in Kir and Taj Starting
    assessment process in Kyr
  • December 2005 January 2006 Restarting and
    rerouting the Project in Uzbekistan
  • January 2006 Completion of investigation
    supplementary campaing in Kyrkyzstan

9
(No Transcript)
10
STATUS
  • General info/data framework acquired
  • Drilling and sampling in the pond completed.
  • Chemical analysis of the mud, nearby river waters
    and wells performed
  • Air sampling and analysis in programme

HAIDARKEN ANTIMONY FACTORY WASTES POND
  • Maps elaboration Topographic, geologic and
    hydrogeologic
  • Assessment to be completed within March 2006
  • Reporting to be completed within April 2006

11
STATUS
  • General info/data framework acquired
  • Drilling and sampling in the tailing ponds
    completed.
  • Chemical analysis of the muds, nearby water wells
    in progress
  • Air sampling and analysis in programme

KADAMJAJ ANTIMONY FACTORY WASTES POND
  • Maps elaboration Topographic, geologic and
    hydrogeologic
  • Assessment to be completed within March 2006
  • Reporting to be completed within April 2006

12
STATUS
  • General info/data framework acquired
  • Drilling and sampling in the dump in progress.
  • Chemical analysis of the dump samples and nearby
    water wells in programme
  • Air sampling and analysis in programme

KANIDABAM PESTICIDES DUMP
  • Maps elaboration Topographic available, geologic
    and hydrogeologic in programme
  • Assessment to be completed within April 2006
  • Reporting to be completed within April-May 2006

13
STATUS
  • General info/data framework to be restarted
  • CIEs organization and cooperation framework to be
    established
  • No investigations supplementary campaign
    programmed (Industrial accident risk assessment)
  • Informatic tools to be delivered
  • Maps elaboration Topographic, geologic and
    hydrogeologic in programme

FERGANA OIL REFINERY
  • Assessment to be completed within May 2006
  • Reporting to be completed within June 2006

14
OUTLOOK
PROJECT AND FEASIBILITY STUDY FOR RECLAMATION AND
PUT-IN-SAFETY OF THE DUMP.
KANIDABAM PESTICIDES DUMP
Proposal has been already presented to possible
donors, since the Bratislava meeting (Under POP
Convention or other forms). The Project shall be
shared and jointly led with local experts and
structures and shall foresee the utilization of
the national resources
15
OUTLOOK
FEASIBILITY STUDY FOR RECLAMATION AND
PUT-IN-SAFETY OF THE POND.
HAIDARKEN WASTES POND
Proposal has been already presented to possible
donors, since the Bratislava meeting (Under POP
Convention or other forms). The Project shall be
shared and jointly led with local experts and
structures and shall foresee the utilization of
the national resources
16
REMARKS
ENVIRONMENTAL MONITORING (?) ENVIRONMENTAL AND
TERRITORY BASIC DATA/INFO PUBLIC AWARENESS AND
PARTICIPATION PROACTIVE ATTITUDE FOR PROTECTING
THE ENVIRONMENT
Write a Comment
User Comments (0)
About PowerShow.com