Title: MSEW
1MSEW RSS Design, Specifications, and
Construction
- Brian Collins, PE
- MDT Geotechnical Section
- Missoula District
2Acronyms
- MSEW Mechanically Stabilized Earth Wall
- SRW Segmental Retaining Wall (a.k.a. modular
block wall) - MBW Modular Block Wall (a.k.a. segmental
retaining wall) - RSS Reinforced Soil Slope
3Presentation Overview
- What are MSEW and RSS?
- Types of Retaining Walls
- Advantages
- Disadvantages
- Design
- Specifications
- Construction
4MSEW Mechanically Stabilized Earth Wall
5RSS Reinforced Soil Slope
6So, whats the difference between MSEW and RSS?
7Reinforced slopes steeper than 70 degrees are
considered walls (per FHWA Design Manual).
8Reinforced Backfill
- MSE walls - Use select backfill for reinforced
fill (lt15 fines,
nonplastic A-1-a) - Reinforced Soil Slopes - Use low plasticity
granular material for reinforced fill
(lt50 fines, PIlt20)
9Types of Walls
2 - Cut Walls
10Types of Walls
- Cut Walls
- Braced
- Tie Backs
- Soil Nails
11Types of Walls
- Fill Walls
- Cantilever
- Gravity
- Reinforced Soil
12- MSEW Applications
- ROW restrictions
- Bridge abutments
- Wing walls
- Areas with poor foundation soils
- Areas with slope stability problems
- In place of reinforced concrete or gravity wall
- RSS Applications
- Unstable or failed slopes
- Slopes susceptible to surface erosion
- ROW restrictions
13Vicinity White Coyote Rd South Ravalli
14South Ravalli Medicine Tree
15South Helena Interchange
16Lost Trail Pass (Hwy 93 at MT/ID border)
17Beartooth Highway
18North Arlee Vic. White Coyote
19US Hwy 2 Goat Lick
20Garryowen Lodge Grass
21Bighorn River Bridge - Hardin
22Advantages of MSEW
- Simple and relatively fast to construct
- Do not require special skills
- Require less site preparation
- Need less space in front of wall for construction
operations - Reduce ROW acquisitions
- Tolerant to settlement (relatively)
- Cost effective
- Can be constructed to heights in excess of 80 feet
23Advantages of RSS
- Usually the most economical alternative when a
soil slope does not fit - Lower quality material can be used for reinforced
fill compared to what would be required for a
wall - Reduce ROW acquisitions
- RSS with vegetated faces will blend with the
natural environment better than a wall - Safer than a flatter soil slope with the same
factor of safety
24Disadvantages of MSEW RSS
- Require a relatively large space behind wall/face
for reinforcement (fill walls) - MSEW require special borrow (A-1-a) for
reinforced fill - MSEW are proprietary designs
- Specifications and contracting practices have not
been standardized - MSEW design requires shared responsibility
between contractor/supplier and owner (MDT) - Montana Contractors dont have much experience
with MSEW or RSS
25(No Transcript)
26DESIGN
27MSEW Design
28Preliminary Design
- Consider all possible alternatives
- Choose a system (MSEW or RSS)
- Consider facing options
- Develop performance criteria (loads, height,
embedment, etc.) - Consider effects on site on corrosion/degradation
of reinforcements
29Facing Options
30MSEW Design
- Sizing for external stability
- Sliding
- Overturning
- Bearing capacity
- Global stability
- Sizing for internal stability
- Internal failure surfaces
- Maximum tensile forces in reinforcement
- Pullout
- Seismic stability
- Connection strength
31External Stability - MSEW
32Internal Stability - MSEW
- POTENTIAL INTERNAL FAILURE SURFACES
- INEXTENSIBLE ETENSIBLE
33Internal Stability - MSEW
- MAXIMUM TENSILE FORCE IN REINFORCEMENT
- Tmax sHSv
- Tmax maximum tension in each reinforcement
layer - sH horizontal stress at each reinforcement
level - Sv vertical reinforcement spacing
-
- PULLOUT
- Tmax (1/FSPO) F g Zp Le C Rc a
34Internal Stability - MSEW
35Internal Stability - MSEW
- CONNECTION STRENGTH
- The allowable connection strength is the lesser
of - The design allowable strength of the
reinforcement - The connection strength developed by friction or
structural means - A reduced connection strength where bodkin joints
or geotextile seams are used
36(No Transcript)
37RSS Design
38Failure Modes for Reinforced Soil Slopes
39External Failure Modes for Reinforced Slopes
SLIDING INSTABILITY
DEEP SEATED OVERALL STABILITY
LOCAL BEARING CAPACITY FAILURE
EXCESSIVE SETTLEMENT
40Analysis of Reinforced Soil Slopes
41ReSSA
42What is the most important aspect of design for
both mechanically stabilized earth walls and
reinforced soil slope?
43- DRAINAGE DRAINAGE DRAINAGE DRAINAGE DRAINAGE
DRAINAGE DRAINAGE DRAINAGE DRAINAGE DRAINAGE
DRAINAGE DRAINAGE DRAINAGE DRAINAGE DRAINAGE
DRAINAGE DRAINAGE DRAINAGE DRAINAGE DRAINAGE
DRAINAGE DRAINAGE DRAINAGE DRAINAGE DRAINAGE
DRAINAGE DRAINAGE DRAINAGE DRAINAGE DRAINAGE
DRAINAGE DRAINAGE DRAINAGE DRAINAGE DRAINAGE
DRAINAGE DRAINAGE DRAINAGE DRAINAGE DRAINAGE
DRAINAGE DRAINAGE DRAINAGE DRAINAGE DRAINAGE
DRAINAGE DRAINAGE DRAINAGE DRAINAGE DRAINAGE
DRAINAGE DRAINAGE DRAINAGE DRAINAGE DRAINAGE
DRAINAGE DRAINAGE DRAINAGE DRAINAGE DRAINAGE
DRAINAGE DRAINAGE DRAINAGE DRAINAGE DRAINAGE
DRAINAGE DRAINAGE DRAINAGE DRAINAGE DRAINAGE
DRAINAGE DRAINAGE DRAINAGE DRAINAGE DRAINAGE
DRAINAGE DRAINAGE DRAINAGE DRAINAGE DRAINAGE
DRAINAGE DRAINAGE DRAINAGE DRAINAGE DRAINAGE
DRAINAGE DRAINAGE DRAINAGE DRAINAGE DRAINAGE
DRAINAGE DRAINAGE DRAINAGE DRAINAGE DRAINAGE
DRAINAGE DRAINAGE DRAINAGE DRAINAGE DRAINAGE
44Why is drainage so important?
45from Simac (2006)
46from Simac (2006)
47from Simac (2006)
48from Simac (2006)
49(No Transcript)
50(No Transcript)
5120
20
5
5220
H25
Hw20
5
LATERAL EARTH PRESSURES
53Lateral Earth Pressure on Back of MSEW due to Soil
- sh g H Ka
- Fa ½ g H2 Ka
- g 125 pcf for retained soil
- H 25 ft
- Ka tan2(45-f/2) tan2(45-34/2) .283
- Fa ½(125pcf)(25ft)2(0.283) 11,055 lb/ft
-
54Lateral Earth Pressure on Back of MSEW due to
Water
- su gw Hw
- Fw ½ gw Hw2
- g 62.4 pcf
- Hw 20 ft
- Fw ½(62.4pcf)(20ft)2 12,480 lb/ft
-
55Total Lateral Earth Force on Back of MSEW
- FT Fa Fw
- 11,055 lb/ft 12,480 lb/ft
- 23,535 lb/ft
56Rules of Thumb for Design
- 1. K.I.S.S. Keep It Simple Stupid (Michael
Scott). Dont create a wall or slope that will
be difficult to construct
57Use only one or two types of reinforcement
58Keep the lengths and spacing of reinforcement
relatively uniform
59Rules of Thumb for Design
- Maximum vertical spacing between reinforcement
layers 2 ft - Minimum length of reinforcement 70 of wall
height (AASHTO) - Include a drainage system (behind the
reinforcement)
60Drainage
61Rules of Thumb for Design
- Minimum embedment below grade for MSEW frost
depth (3-5 ft in Montana) - Dont forget global stability
62SPECIFICATIONS
633 Contractual Methods for MSE
- Agency or supplier design.
- End result design approach.
- Standard designs.
64Advantages
- Agency or supplier design
- Much longer design period
- In house expertise
- End result design approach
- Design performed by experienced staff
- System components routinely used together
- Lessens design costs and manpower required for
owner - Standard designs
- Agency has more responsibility for details
- Systems and components approved before bid
- Agency makes design decisions
- Filters out substandard work
65Disadvantages
- Agency or supplier design
- Requires more time from geotechnical staff
- Reduces competitive bidding by wall manufacturers
- Problems designing certain design details due to
patents - End result design approach
- Difficult for owner to review and approve new
technology - Short time frame to deal with complex phasing or
special details - Standard designs
- Lots of time and effort required to develop
generic designs - Can only be used when site conditions meet
certain criteria
66MDTs Approach to MSEWs
- End Result Design Approach
- MDT completes subsurface investigation
- MDT Geotechnical Section performs feasibility and
global stability calculations for the proposed
wall layout - Specify beginning and end of wall stationing
- Specify top of wall elevation and finished grade
elevation in front of wall - Specify minimum wall embedment depth
- Specify minimum reinforcement length
- Specify reinforced backfill properties and design
parameters - Specify required safety factors
- Specify maximum spacing of reinforcement
- Specify settlement criteria
- Specify facing options
67MDTs Approach to RSSs
- MDT completes subsurface investigation
- MDT Geotechnical performs complete design
calculations - Specify RSS layout
- Specify reinforcement locations, lengths and
minimum property requirements - Specify reinforced fill material properties
68MSEWCONSTRUCTION
69(No Transcript)
70Keep in mind
a retaining wall is a structure, not an
embankment, inspect it as you would a bridge
abutment.
71Required Contractor Submittals
- Design Submittal calculations working
drawings - 30 days before start of wall excavation
- submit to MDT Geotechnical Section
- allow 21 calendar days for review
- Backfill Source Approval
- Submit sample 30 days before beginning
construction - Reinforcement Source Approval
- Submit Manufacturers Certificate of Compliance
- Submit sample 5 feet in length by the full
reinforcement width - Allow 30 days for evaluation
72Excavation
- Complete as shown on approved on working drawings
- Contractor is responsible for any temporary
excavation support (as required) - Always perform excavations in accordance with
OSHA requirements
73Foundation Preparation
- Grade the foundation level for the length of
reinforcement plus 1 foot - Compact the foundation level with a smooth-drum
vibratory roller - Proofroll subgrade remove and replace any
unsuitable foundation material with select gravel - Keep the foundation excavation dry at all times
7405 MAY 2006
7518 MAY 2006
7602 JUNE 2006
7702 JUNE 2006
7819 JUNE 2006
7919 JULY 2006
80Spend time to ensure the foundation is ready
from Simac (2006)
81Leveling Pad
82Leveling Pad
- Used to align facing panels/blocks and provide
temporary foundation support elevation should
be within 1/8 tolerance - Minimum dimensions 6 thick x 12 wide
- Concrete or crushed gravel
- Allow concrete to cure min. 12 hrs
83Modular Block MSE Walls
- The first course of blocks is critical
- Level front to back and side to side
- Ensure proper alignment
- Dont leave gaps between blocks
- Level front to back on courses above geogrid and
shim as needed
84Modular Block MSE Walls
(from Keystone Construction Manual)
85Modular Block Connections
(from Keystone Construction Manual)
86Modular Block Connections
(from Mesa Installation Manual)
87Unit / Drainage Material
- All modular blocks must be filled
- Usually ¾-minus well-graded crushed stone
- Provides additional bond between courses of
blocks - Provides friction between geogrid reinforcement
and blocks - Increases weight of wall facing
- Provides drainage behind wall face
- Prevents loss of material in gaps between blocks
(from Keystone Construction Manual)
88Place unit fill and backfill after each lift
89Backfill Placement
- Place following each course of facing
- Maximum 8 lifts
- Do not leave voids below the reinforcement behind
the wall face - Compact all backfill, there is no such thing as
self-compacting fill
90Wall failure due to no compaction within 3-5 feet
of wall face
91Compaction
- Compact to 95 of MT-230 density at 2 of
optimum moisture content - Use a rolling pattern if backfill material has
too much oversized gravel to perform proctor test - A large smooth-drum vibratory roller should be
used away from the wall face - Use lightweight (walk behind) compaction
equipment within 4 feet of wall face - Do not use sheepsfoot rollers
92Geogrid Placement
Uniaxial geogrid Machine/Longitudinal Direction
(MD) no splices or overlaps allowed Cross-Machin
e/ Transverse Direction (XD, XMD) Ribs Junctions
/nodes
Shims may be required at front face of blocks
use scrap ribs of geogrid
(from Mesa Installation Manual)
93Geogrid Placement
(from Mesa Installation Manual)
Dont shim right at front face of blocks too
much stress
94Pull geogrid tight (remove wrinkles and folds)
and hold in place with pins, stakes, soil piles,
etc.
(from Mesa Installation Manual)
95Geogrid Cutoff Lengths
96Geogrid Placement - Curves
(from Mesa Installation Manual)
97Installation of Guardrail Posts
(from Mesa Installation Manual)
98RECo Wall System
99System Components
- Concrete leveling pad
- Precast concrete facing panels
- Facing panel joint materials
- Rubber bearing blocks
- Rubber shims
- Filter cloth
- Reinforcing strips or ladder strips
- Fasteners
- Select granular backfill
100Steel ladder reinforcing or steel strip
reinforcing
101Construction Procedures
- Prepare subgrade (foundation) and install
drainage system - Install leveling pad
- Set and brace first course alternating full-
and half-height panels - Use wooden wedges and clamps to hold panels in
position - Attach filter cloth with adhesive (Do not put
adhesive in gap between panels)
102(from RECo Installation Manual)
103Construction Procedures, contd
- Place backfill in lifts up to 1-2 above the
lowest level of reinforcing - Connect reinforcing elements
- Place bearing blocks and set second course of
full panels - Repeat cycle
- Place backfill
- Compact
- Place reinforcement
- Install bearing blocks
- Install panels
- Place geotextile filter
104(from RECo Installation Manual)
105(from RECo Installation Manual)
106BACKFILL LEVELS
(from RECo Installation Manual)
107Construction Procedures, contd
- After each course is completed, remove wooden
wedges in the course 3 levels below - Set top panels and finish backfilling and
compaction - Remove all wedges and clamps
- Install any concrete coping, traffic barriers, or
CIP concrete as required
108GABION WALLS
109GABION WALLS
110Gabion Assembly
(from Maccaferri Installation Manual)
111Gabion Assembly, contd
(from Maccaferri Installation Manual)
112Gabion Internal Bracing
113Gabion Installation
- Prepare subgrade (foundation) and install
drainage system - Assemble gabion baskets
- Place a number of gabion baskets in position and
tie adjoining baskets together - Tie adjacent courses of gabions together after
tensioning - Fill gabions while keeping gabions stretched
longitudinally to maintain alignment
114Fill each course of gabions in stages
(from Maccaferri Installation Manual)
Overfill each basket by 50-75 mm to allow for
settlement
115Gabion Wall Construction, contd
- Place reinforcing mesh on the top surface of a
finished layer at the elevations shown on the
plans - Wire the next course of gabions in place at the
front of the wall before placing backfill - Place backfill and compact
116Gabion Basket Connections
117Welded Wire Wall System
118Wall Parts
(from Hilfiker Construction Guide)
119(No Transcript)
120Welded Wire Wall Construction
- Prepare subgrade (foundation)
- Install drainage system
- STEP 1 Install first row of mats
121(No Transcript)
122STEP 2 Install backing mat
123STEP 3 Place backfill and geotextile. Then
place rock in face.
124(No Transcript)
125(No Transcript)
126STEP 45 Start next course. Repeat steps 1-3.
127(No Transcript)
128Welded Wire Walls
(from Hilfiker Construction Guide)
129Welded Wire Walls
(from Hilfiker Construction Guide)
130Welded Wire Walls curves corners
(from Hilfiker Construction Guide)
131Welded Wire Walls backing mats
(from Hilfiker Construction Guide)
132Welded Wire Walls using hardware cloth
(from Hilfiker Construction Guide)
133(from Hilfiker Construction Guide)
134Guardrail Penetration
(from Hilfiker Construction Guide)
135Culvert Through Wall
(from Hilfiker Construction Guide)
136Culvert Through Wall, contd
(from Hilfiker Construction Guide)
137Culvert Through Wall, contd
(from Hilfiker Construction Guide)
138MSE Construction - Summary
- Review all plans and specifications
- Review approved working drawings
- Review materials requirements and approval
submittals - Spend time to ensure the foundation is ready
before starting the wall - Verify that the correct type and length of
reinforcement is installed at the locations shown
on the plans - Test backfill for compaction and gradation
requirements during construction - Verify that the wall batter is within the
tolerance listed in the specifications - Keep water away from the work area
139Questions?