Title: ORR Readiness
1ORR Readiness
- Mark Colavita Peter Wizinowich
- KISWG
- Pasadena 10/29/2003
2Question to Address (2/3/2003 pre-ORR
presentation)
- At the ORR
- Will the instrument be capable of achieving the
requirements in the PLRA at the start of routine
science operations? (V2 mode) - What are the relevant performance metrics and
current performance? (V2 mode) - Today
- What are the specific performance requirements,
and how do they relate to the PLRA? - How will compliance be demonstrated?
- Are they technically achievable?
- What is the current performance?
- What is the plan to get from current performance
to ORR? Is the plan realistic? - What are the risks for routine science operation?
How will they be mitigated? Are there additional
risks not yet identified that need to be
addressed?
3Specific Performance Requirements (2/3/2003
pre-ORR presentation)
- PLRA requirements for V2
- System Performance Goals
- Provide 5 rms accuracy V2 amplitude measurements
for targets as faint as K9 using the two Keck
telescopes - Provide at least 90 uptime for the
interferometer and 90 uptime for the two 10m
telescopes and their AO systems - System Performance Requirement
- Provide at least 90 uptime for the
interferometer and 80 uptime for the two 10m
telescopes and their AO systems
Program Level Requirements Appendix to Navigator
Program Plan
4Pre-ORR Testing from Oct Observing Run
- Targets included measurements of
well-characterized PTI binary - Used neutral density filters to attenuate this
bright star to simulate K9 ORR requirements - Data accuracy still being assessed
- Observation
- K9 spec will need to be qualified with a V or R
magnitude, as stars faint to AO are less well
corrected, and provide less flux into fringe
tracker - (Fringe tracker measures flux Strehl)
- Plan to provide this for ORR
- Also tests of fringe tracker low-V2 tracking limit
5Oct Data(Most processing still in-progress)
6Prior (May, Jan) accuracy tests
7Other tests
8Provide at least 90 uptime for the
interferometer and 90 uptime for the two 10m
telescopes and their AO systems (2/3/2003 pre-ORR
presentation)
- Quoted directly from the PLRA
- NB not a measure of open shutter time or
efficiency, which is actually quite low for any
instrument, like IF, that is calibration-limited - A measure equal to 100 minus the downtime
required to fix IF hardware or software problems
during scheduled science observing - Telescopes/AO addressed in a few slides
- Demonstrating compliance
- Mostly proper bookkeeping
- Identify a timekeeper to track system state vs.
time - Demonstrate compliance on two runs prior to ORR
with good weather and median or better seeing
9System uptime scans per hour
10Uptime summary
- Interferometer uptime ? 90 2/5 runs
- Facility uptime ? 90 1/5 runs ? 80 3/5 runs
- October run problem areas
- Major
- Telescope control system crashes
- K2 continued to have problems after the IF run
supporting DEIMOS - Problem may be resolved need to test
- Minor most in process of being addressed
- Facility
- AO offload problem (possible interaction from IF
angle tracker) - K2 AO Wavefront controller crashes
- Interferometer
- Sequencer crashes
- Aligner crate reboots
- Telemetry server memory growth solved
- Goal is to achieve ORR metric performance on next
two runs
11Performance, functionality, efficiency goals
(2/3/2003 pre-ORR presentation)
- These follow from the desire to maximize the
science achievable at the specified performance
level
12Performance, functionality, efficiency goals, 1
(2/3/2003 pre-ORR presentation)
13System uptime scans per hour
14Scans per hour
- 86 science plus engineering scans in 22.5 clear
hours - Peak scans on each of 4 nights
- 2, 3, 6, 8
- Sustained high throughput impacted by
- System faults
- Ease of observing target
- Faint targets, requiring optimization of AO, KAT,
FATCAT, or which end up not being trackable,
count against scans per hour - Weather (light to moderate cirrus, which doesnt
count against weather loss) - May need to qualify our 6 scan/hr goal to apply
to sources not pushing system limits
Night 3 of Oct run
Peak scans/hr for this night
15Performance, functionality, efficiency goals,
1updates to 2/3/2003 pre-ORR presentation
16Performance, functionality, efficiency goals, 2
17Performance, functionality, efficiency goals, 3
18Procedural Requirements for the ORR
- From the PLRA
- Provide an operational infrastructure including
trained staff, facilities, hardware and software,
so that the Keck Interferometer will operate as a
facility for use by the community scientists.
19Procedural Requirements for the ORR
- From LaPiana Need (A) requirements which you
can track against your progress to actually
achieve the metric performances, and the (B)
ability to do it routinely and having an
organization in place that is well trained to do
so with robust and stable software (at WMKO
MSC). - Questions to address at the ORR from LaPiana
- Will the ground data system (at WMKO and at MSC)
implementation and testing be complete prior to
the start of routine science operations? - Will the required operations plans and
procedures, including those for anomaly
responses, be completed and tested prior to start
of routine science operations? - Are the operations organization, staff and
facilities in place (WMKO and MSC)? - Will the necessary training activities be
completed prior to start of routine science
operations? - Are the necessary set of commands and sequences
ready to support nominal operations? Will all
action items, liens, etc., be satisfactorily
dispositioned? - Are the risks well understood and acceptable for
routine science operations?
201. Ground Data System Completion
- Will the ground data system (at WMKO and at MSC)
implementation and testing be complete prior to
the start of routine science operations? - At the pre-ORR The primary demonstration will be
successful CARA operation of the interferometer
for V2 science. - We will track this performance over the next 7
runs. - The last 3-runs prior to the ORR will be
performed at the full ORR requirement level. - CARA personnel have successfully operated the
interferometer for most of these runs. We have
tracked performance during these runs. Many, but
not all, of performance numbers demonstrated in
Oct. run. - At most can demonstrate full ORR-level compliance
during only 2 runs (Nov. Jan.) prior to ORR.
212. Operations Plans Procedures
- Will the required operations plans and
procedures, including those for anomaly
responses, be completed and tested prior to start
of routine science operations? - Operations procedures for daytime checkout
night-time operation are in place. - Anomaly responses need completion
- Including spares troubleshooting training
- Configuration management (software,
opto-mechanical electronics) need to be defined
agreed upon - Especially important during ongoing development
- Major software upgrade will happen with RTC 2.1
- Also need upgrade plan (plan to implement
upgrades without compromising operational
system). - Would be easier if some subsystems had already
been handed over to CARA - Need to approve/implement plan for maintaining
cleanliness of optics/basement
222. Operations Plans Procedures
- Current operations procedures
- Punchlist with new priorities distributed after
each run. Reviewed bi-weekly. - Schedule for summit activities maintained.
Reviewed weekly. Incorporated in Observatory
scheduling. - Daytime summit activities entered into IFDEV
Observatory daylog. - Observing support personnel (daytime, nighttime
on-call) list distributed prior to run. - Setup observing procedures available on-line
(next slide). - Afternoon pre-observing checklist/procedure
performed. - Plan for nights observing distributed.
- Observing log maintained published to telescope
nightlog. - Post-run summary distributed, including
priorities for next run. - Punchlist with old priorities closed out.
- Post-run review held with Observatory/Project
management.
23OperationsProcedures
2434. Operations Organization Training
- Are the operations organization, staff and
facilities in place (WMKO and MSC)? - Will the necessary training activities be
completed prior to start of routine science
operations? - Organization
- John Gathright has assumed Operations Coordinator
role - Responsible for coordinating/scheduling/staffing
activities in support of observing runs,
observing prep daytime experiments - 2 (of 3) technicians report directly to him
2534. Operations Organization Training
- Facilities
- Control rooms set up at headquarters summit
- Control rooms routinely used for interferometer
operation - Instrument performance capabilities need to be
made available to the community for observing
planning
2634. Operations Organization Training
- Staff
- 3 Interferometer specialists trained in operation
of Interferometer for daytime alignments,
checkouts tests, night-time operations - 2 technicians trained in daytime alignments
checkouts - Plan to hire an interferometer operator an
interferometer specialist to relieve operational
load on above personnel - Software engineers (2) able to support day
night-time troubleshooting. - Electronics engineer able to support daytime
troubleshooting. - Mechanical engineer gaining some instrument
familiarity.
2734. Operations Organization Training
- Staff
- Currently 1 JPL 1 MSC person participates in
each run. Can we fill their roles after the ORR?
- JPL person really helps with troubleshooting
- We are gaining more familiarity with instrument
resolving problems (JPL still on-call) - MSC person really understands science priorities
- We need more insight /or MSC on-call
285. Commands Sequences
- Are the necessary set of commands and sequences
ready to support nominal operations? Will all
action items, liens, etc., be satisfactorily
dispositioned? - Alignment
- Procedures exist and are used.
- All mirrors and shutters needed are remotely
controlled. - Pre-Observing checklist
- Checklist exists and routinely used by CARA
personnel. - Observing procedure/checklist
- CARA personnel routinely operate.
- MSC tools procedures
- CARA personnel recently operating.
- Post-Observing
- Tapes written and shipped.
295. Commands Sequences
- Target acquisition (Manual Automated steps)
- Interferometer Sequencer (IS) operator selects
target from list - IS loads parameters initiates Telescope
Sequencer (TS) - IS configures FDLs for observation
- TS initiates the following (can change for repeat
observation) - Telescope control system slews, then tracks, the
telescopes - Auto-acquisition tool positions brightest target
on acquisition camera for AO system - AO auto-setting tool optimizes AO parameters on
target - AO operator reports AO loops locked to IS
operator - AO system offloads tip/tilt and focus to the
telescope - IS operator closes Angle Tracker (KAT) loop
- KAT loop automatically offloads IF tip/tilt
mirror to AO wavefront sensor offsets - AO operator unloads offsets to field steering
mirrors if gt threshold - IS operator initiates IS to acquire fringes
- IS scans to peak signal on fringe tracker
- IS searches for fringes
305. Commands Sequences
- Remaining issues
- Automated night-time LDL repositioning (manual
too slow) - This is currently a high priority
- Automated daytime alignment (labor telescope
intensive) - Likely a lien at the ORR
- User interface is complex distributed (can make
mistakes) - Plan to implement a simpler quick-look
- Better version will come after RTC 2.1 upgrade
- Observing sequence automation should be improved
to achieve scans/hour with reduced human
interaction - Selectable level of telescope sequencer operation
- Offloading wavefront sensor centroids to FSMs
- Reuse of AO parameters
- Remote configuration
- A few remaining hands-on operations
316. Risks
- Are the risks well understood and acceptable for
routine science operations? - Risks identified at ORR requirements review
- Weather, wind shake and seeing
- There are nights when IF observing simply cannot
be done productively or when only bright targets
can be used. - Best choice in some conditions would be to switch
to another instrument program that can succeed
with poor seeing. - Hardware failures
- Mitigation List of critical spares and backup
approaches to be identified implemented prior
to ORR.
326. Risks
- Development during operations
- Mitigation Configuration control.
- Observatory-wide software configuration plan
currently being approved. Will apply to
Interferometer AO ops. - Inteng tag of intdev nearly in place to protect
software. - ECR process in place for AO opto-mechanics.
- Mitigation Careful coordination of development
operations activities (using current operations
procedures). - Number of shared risk TAC allocated V2 science
nights - Too many nights could result in inadequate CARA
involvement in development /or inadequate access
to interferometer for development. - Possible mitigation
- Limit the number of science nights.
- Additional operations staff.
- New Load on CARA staff if system requires lots
of hand-holding
33ORR readiness summary
- Will probably be OK on V2 accuracy spec need to
complete analysis of Oct data - Uptime still problematic
- Working on major (and minor) problems from Oct
- With satisfactory resolution of major, and
several of the minor problems, should be possible
to achieve in November Jan. - Scans per hour still low, although brief good
peak performance - Some issues with brightness of target will not
apply if target requires extensive optimization - Improvements to system uptime and user interface
should improve performance - OK on most other areas, except for LDL
automation, which is a current focus